Other Work at the Site Clause Samples

The 'Other Work at the Site' clause defines how the presence of additional contractors or third parties performing work at the project location is managed. It typically outlines the responsibilities of the primary contractor to coordinate with others, avoid interference, and ensure safety and efficiency on site. For example, if electrical and plumbing contractors are working simultaneously, this clause clarifies how their activities should be scheduled and coordinated. Its core function is to prevent conflicts, delays, or safety issues arising from multiple parties working at the same site, thereby ensuring smooth project progress.
Other Work at the Site. A. In addition to and apart from the Work of the Contractor, other work may occur at or adjacent to the Site. Contractor shall take reasonable and customary measures to avoid damaging, delaying, disrupting, or interfering with the work of Owner, any other contractor, or any utility owner performing other work at or adjacent to the Site.
Other Work at the Site. Buyer reserves the right to perform other work outside of the scope of the Works or to enter into other contracts in connection with the SJ 5&6 Units. Seller shall afford Buyer and its other contractors a reasonable opportunity for the introduction and storage of their materials and the execution of their work and shall properly connect and coordinate Seller's work with the work performed by Buyer and its other contractors. If any part of Seller's work depends for proper execution or results upon the work of Buyer or of any other contractor, Seller shall inspect and promptly report to Buyer any defects in such work or any conflicts between such work and that of Seller, Buyer to decide, if necessary, the course to be followed by each party. Wherever work being done by Buyer's own forces or by other contractors is contiguous to work covered by this Agreement, Buyer will secure the completion of the various portions of the work so as not to interfere with the Work. Whenever, in the opinion of Buyer, the orderly progress of the entire Project requires the use by Buyer's own forces or by other contractors, of construction equipment installed and operated by Seller for his own use, Buyer will arrange with Seller for such use, at times, and in locations which will not interfere with the work being done under this Dependent upon Mitsubishi agreeing to the same. A-2 Agreement, and will reimburse Seller for any incremental costs incurred by Seller as a result of any such use.
Other Work at the Site. A. In addition to and apart from the Work of the Contractor, other work may occur at or adjacent to the Site. Contractor shall take reasonable and customary measures to avoid damaging, delaying, disrupting, or interfering with the work of Owner, any other contractor, or any utility owner performing other work at or adjacent to the Site. B. Contractor shall notify Owner, the owners of adjacent property, the owners of underground facilities and other utilities (if the identity of such owners is known to Contractor), and other contractors and utility owners performing work at or adjacent to the Site when Contractor knows that prosecution of the Work may affect them; and Contractor shall cooperate with them in the protection, removal, relocation, and replacement of their property or work in progress.
Other Work at the Site. Related Work at Site
Other Work at the Site. Section 3.01 Related Work at Site (a) City may perform other work related to the Project at the Site with City’s employees, or through other direct contracts therefor, or have other work performed by utility owners.‌ (b) If the proper execution or results of any part of Contractor’s Work depends upon work performed by others under this Article, Contractor shall inspect such other work and promptly report to City in writing any delays, defects, or deficiencies in such other work that render it unavailable or unsuitable for the proper execution and results of Contractor’s Work. (c) Contractor’s failure to so report will constitute an acceptance of such other work as fit and proper for integration with Contractor’s Work except for latent defects and deficiencies in such other work. (d) Access to Work (i) City, its consultants and other representatives and personnel of City, independent testing laboratories, and governmental agencies with jurisdictional interests will have access to the Site and the Work at reasonable times for their observation, inspection, and testing. Contractor shall provide them proper and safe conditions for such access and advise them of Contractor’s safety procedures and programs so that they may comply therewith as applicable. Section 3.02 Hazardous Environmental Condition at the Site (a) Contractor shall not be responsible for any Hazardous Environmental Condition uncovered or revealed at the Site which was not shown or indicated in Drawings or Specifications or identified in the Contract Documents to be within the scope of the Work. (b) Contractor shall be responsible for a Hazardous Environmental Condition created with any materials brought to the Site by Contractor, Subcontractors, Suppliers, or anyone else for whom Contractor is responsible. (c) If Contractor encounters a Hazardous Environmental Condition or if Contractor or anyone for whom Contractor is responsible creates a Hazardous Environmental Condition, Contractor shall immediately do all of the following: (i) secure or otherwise isolate such conditions; (ii) stop all Work in connection with such condition and in any area affected thereby (except in an emergency); and (iii) notify City (and promptly thereafter confirm such notice in writing). City shall promptly shall take such actions as are necessary to permit City to timely obtain required permits and provide Contractor the written notice as required by herein.

Related to Other Work at the Site

  • Demolition work (i) As of 1 March 2024 where Employees are directly performing demolition works that would require a demolition permit that allows the performance of such work, they will receive the amount of $9.70 per hour or the site allowance, whichever is the greater. This allowance will be adjusted annually in accordance with CPI (All Groups, Melbourne) movements measured in the twelve month period ending the previous December quarter effective as of 1 March 2025, rounded to the nearest 5 cents. (ii) As of 1 March 2024 where Employees are employed in connection with, and on work, with employees of demolition contractors (ie. working within the demolition zone and/or subject to the additional disabilities arising from that demolition), they will receive the amount of $8.70 per hour or the site allowance, whichever is the greater. This allowance will be adjusted annually in accordance with CPI (All Groups, Melbourne) movements measured in the twelve month period ending the previous December quarter effective as of 1 March 2025, rounded to the nearest 5 cents.

  • Architect Engineer shall provide assistance to Owner through the commissioning consultant/agent for the purpose of advising and counseling Owner’s personnel in the usage, operation and maintenance of the building mechanical, electrical, and plumbing systems.

  • Completion of Improvements Within ninety (90) days of completion of any construction herein permitted, Company will cause to be prepared and delivered to Authority record documents as required under the Tenant Work Permit process, including but not limited to as-builts, legal descriptions, boundary surveys, and certified final cost of construction. The submission of record document electronic media will be in accordance with Authority’s Standard Procedure for computer aided design and drafting and drawings, as may be revised from time to time.