Outage Scheduling. Unless otherwise directed by PECO, SELLER shall periodically submit for PECO's approval, such approval not to be unreasonably withheld, its planned maintenance schedule conforming to Section 6.5 hereof, for the subsequent thirty-six (36) months of operation. SELLER shall revise its planned and maintenance outage dates upon PECO's request for such changes
Appears in 1 contract
Sources: Contingent Capacity Purchase Addendum (NRG Generating U S Inc)
Outage Scheduling. Unless otherwise directed by PECO, SELLER shall periodically submit for PECO's approval, such approval not to be unreasonably withheld, its planned maintenance schedule conforming to Section 6.5 hereof, for the subsequent thirty-six (36) months of operation. SELLER shall revise its planned and maintenance outage dates upon PECO's request for such changes.