Common use of Performance Deadlines Clause in Contracts

Performance Deadlines. To the extent one party’s performance of an obligation under this Agreement depends on the other party to provide data or information, a delay in providing the data or information will automatically extend the deadline for performance of the dependent task for a minimum of the time the initial task is complete. By way of example, if Contractor’s reporting depends on receipt of claims data from DVHA and DVHA does not send data for 45 days, Contractor’s deadline to report is automatically extended by 45 days.

Appears in 4 contracts

Sources: Contract for Services, Contract for Services, Service Agreement