Planned Services Availability Date Clause Samples

The Planned Services Availability Date clause establishes the specific date by which the service provider is expected to make the contracted services available to the client. In practice, this clause sets a clear timeline for project delivery, often referencing a calendar date or a period following contract execution, and may include provisions for adjusting the date in case of unforeseen delays. Its core function is to ensure both parties have a mutual understanding of when services will commence, thereby reducing uncertainty and helping to coordinate related activities or dependencies.
Planned Services Availability Date in relation to each School, the date shown as the Planned Services Availability Date in Schedule 4 (Schools) or such later date as may be allowed in accordance with the terms of this Agreement;54 any insurance cost saving which arises from the Contractor changing the placement of the Required Insurances from being on a stand alone project-specific basis assumed at Financial Close and reflected in the Base Cost, to being on the basis of a policy (or policies) also covering risks on other projects or other matters which are outside the scope of the Project so as to benefit from portfolio savings. A Portfolio Cost Saving is defined to be a positive sum and cannot be less than zero; in relation to each Site, those parts of the Works to be completed after the Services Availability Date in accordance with the Construction Programme;55] in respect of a Site, a certificate issued by the Independent Certifier confirming that the Post Completion Works Acceptance Requirements in respect of that Site have been met;] in relation to any Post Completion Works in respect of a Site, the date on which a Post Completion Works Acceptance Certificate is issued;] in relation to a Site, the satisfaction of the relevant tests set out in Part 2 of Schedule 5 (Completion Requirements);] for the purposes of clause 51.2 (Retendering Procedure), for the whole or any part of a month for the period from the Termination Date to the Compensation Date, an amount equal to the Monthly Unitary Charge which would have been payable in that month under this Agreement had this Agreement not been terminated, less an amount equal to the aggregate of:
Planned Services Availability Date in relation to each School, the date shown as the Planned Services Availability Date in Schedule 4 (Schools) or such later date as may be allowed in accordance with the terms of this Agreement;4857 any insurance cost saving which arises from the Contractor changing the placement of the Required Insurances from being on a stand alone project-specific basis assumed at Financial Close and reflected in the Base Cost, to being on the basis of a policy (or policies) also covering risks on other projects or other matters which are outside the scope of the Project so as to benefit from 47 Suggested drafting to56 To be used where there isare post -Services Availability works eeg.g pitches and demolition. The date may be fixed by reference to the Services Availability Date. This will only be appropriate in cases where Post Completion Works must necessarily commence following completion of the main Works.
Planned Services Availability Date in relation to each School, the date shown as the Planned Services Availability Date in Schedule 4 (Schools) or such later date as may be allowed in accordance with the terms of this Agreement;5457 any insurance cost saving which arises from the Contractor changing the placement of the Required Insurances from being on a stand alone project- specific basis assumed at Financial Close and reflected in the Base Cost, to being on the basis of a policy (or policies) also covering risks on other projects or other matters which are outside the scope of the Project so as to benefit from portfolio savings. A Portfolio Cost Saving is defined to be a positive sum and cannot be less than zero; in relation to each Site, those parts of the Works to be completed after the Services Availability Date in accordance with the Construction Programme;5558]

Related to Planned Services Availability Date

  • EPP service availability Refers to the ability of the TLD EPP servers as a group, to respond to commands from the Registry accredited Registrars, who already have credentials to the servers. The response shall include appropriate data from the Registry System. An EPP command with “EPP command RTT” 5 times higher than the corresponding SLR will be considered as unanswered. If 51% or more of the EPP testing probes see the EPP service as unavailable during a given time, the EPP service will be considered unavailable.

  • DNS service availability Refers to the ability of the group of listed-­‐as-­‐authoritative name servers of a particular domain name (e.g., a TLD), to answer DNS queries from DNS probes. For the service to be considered available at a particular moment, at least, two of the delegated name servers registered in the DNS must have successful results from “DNS tests” to each of their public-­‐DNS registered “IP addresses” to which the name server resolves. If 51% or more of the DNS testing probes see the service as unavailable during a given time, the DNS service will be considered unavailable.

  • Service Availability You understand that Service availability is at all times conditioned upon the corresponding operation and availability of the communication systems used in communicating your instructions and requests to the Credit Union. We will not be liable or have any responsibility of any kind for any loss or damage thereby incurred by you in the event of any failure or interruption of such communication systems or services resulting from the act or omission of any third party, or from any other cause not reasonably within the control of the Credit Union.

  • Services Available To help resolve employment relationship problems, the Ministry of Business, Innovation and Employment provides:

  • RDDS availability Refers to the ability of all the RDDS services for the TLD, to respond to queries from an Internet user with appropriate data from the relevant Registry System. If 51% or more of the RDDS testing probes see any of the RDDS services as unavailable during a given time, the RDDS will be considered unavailable.