Potholing. Prior to commencement of any tree replacement or ▇▇▇▇▇ grinding, Contractor shall physically locate, verifying horizontal and vertical locations, and map existing underground facilities within the work area that are marked by Underground Service Alert (USA) or shown on the drawings. Contractor shall protect all such facilities from damage due to construction activities for the duration of the project. Contractor shall deliver a plan with the location of each potholed utility to the Engineer. Repair of damage to such facilities shall be at the Contractor's expense and shall be considered as integral to this item of work. Contractor shall be responsible for following all applicable rules and regulations concerning work in the vicinity of underground and/or overhead utilities. The cost for potholing shall be included in the unit prices bid for the various contract items, and no additional compensation will be allowed therefor.