PRE SUBMITTAL REQUIREMENTS Clause Samples

PRE SUBMITTAL REQUIREMENTS. A. Scope Definition: Prior to GMP submittal, the Construction Manager shall thoroughly review the GMP Construction Document package with the Owner and determine if the scope is sufficiently defined and identify those areas requiring additional scope definition. As a minimum the following should be defined: Program building size, site limits and access, utility systems (existing and new), complete building systems descriptions, materials outline by division, MEP systems descriptions including materials, MEP system options shall be defined and accepted. Refer to the section “PDRI For Buildings” which is an attachment to the Contract for additional guidelines. The PDRI checklist must be completed at this time. B. Schedule: The anticipated Notice to Proceed and Substantial Completion dates for Construction shall be coordinated and approved by the User (Component Institution) and ODR.
PRE SUBMITTAL REQUIREMENTS. A. Scope Definition: Prior to GMP submittal, the Contractor shall thoroughly review the GMP construction document package with the Owner and determine if the scope is sufficiently defined and identify those areas requiring additional scope definition. As a minimum the following should be defined: Program building size, site limits and access, utility systems (existing and new), complete building systems descriptions, materials outline by division, MEP systems descriptions including materials, MEP system options shall be defined and accepted. Refer to the section “PDRI For Buildings” which is an attachment to the Agreement for additional guidelines. The PDRI checklist must be completed at this time. B. Schedule: The anticipated Notice to Proceed and Substantial Completion dates for Construction shall be coordinated and approved by the User and OFPC. C. Value Engineering: Proposed value engineering items included in the GMP shall be updated from previously submitted value engineering and should reflect the “final acceptance” of VE items, which are part of the scope of work. The VE schedule shall identify current acceptance and the date of acceptance in an adjacent column. VE items must be resolved and accepted by the Owner prior to GMP submittal. D. Pre-submittal Conference: The Contractor shall schedule a conference with the Project Manager no later than six (6) weeks prior to submitting the initial draft of the GMP to the Owner. Issues regarding the required materials to be included in the GMP should be reviewed so that there is a clear understanding of the format and contents of each division of work to be submitted. The Contractor shall obtain a copy of the “OFPC Standard Schedule of Values Format” from the OFPC Project Manager. Additionally, a review of acceptable “General Condition” items, as defined in the Agreement, is required.
PRE SUBMITTAL REQUIREMENTS. A. Scope Definition: Prior to GMP submittal, the Construction Manager shall thoroughly review the GMP construction document package with the Owner and determine if the scope is sufficiently defined and identify those areas requiring additional scope definition. As a minimum the following should be defined: Program building size, site limits and access, utility systems (existing and new), complete building systems descriptions, materials outline by division, MEP systems descriptions including materials, MEP system options shall be defined and accepted. B. Estimated Construction Cost: Cost estimates shall be updated concurrently with the construction document development. C. Schedule: The anticipated Notice to Proceed with Construction and Substantial Completion dates for Construction shall be coordinated and approved by the Owner. D. Value Engineering (VE): Proposed value engineering items included in the GMP shall be updated from previously submitted value engineering and should reflect the “final acceptance” of VE items, which are part of the scope of work. The VE schedule shall identify current acceptance and the date of acceptance in an adjacent column. VE items must be resolved and accepted by the Owner prior to GMP submittal.
PRE SUBMITTAL REQUIREMENTS. A. Scope Definition: Prior to GMP submittal, the Contractor shall thoroughly review the GMP construction document package with the City and determine if the scope is sufficiently defined and identify those areas requiring additional scope definition. As a minimum the following should be defined: Program building size, site limits and access, utility systems (existing and new), complete building systems descriptions, materials outline by division, MEP systems descriptions including materials, MEP system options shall be defined and accepted. B. Schedule: The anticipated Notice to Proceed, Substantial Completion and Final Completion dates shall be coordinated and approved by the City.
PRE SUBMITTAL REQUIREMENTS. A. Scope Definition: Prior to GMP submittal, ▇▇▇▇ shall thoroughly review the GMP construction document package with County to determine if the Scope is sufficiently defined and identify those areas requiring additional scope definition. As a minimum, the following shall be defined: 1. Program 2. Building size
PRE SUBMITTAL REQUIREMENTS. A. Scope Definition: Prior to GMP submittal, ▇▇▇▇ shall thoroughly review the GMP construction document package with County to determine if the Scope is sufficiently defined and identify those areas requiring additional scope definition. As a minimum, the following shall be defined: 1. Program 2. Building size 3. Site limits and access 4. Utility systems (existing and new) 5. Complete building systems descriptions 6. Materials outline by division 7. MEP systems descriptions including materials 8. MEP system options. B. Estimated Construction Cost: Cost estimates shall be updated concurrently with the construction document development. C. Schedule: The anticipated Notice to Proceed with Construction and Substantial Completion dates for Construction shall be coordinated and approved by County. D. Value Engineering (VE): Proposed value engineering items included in the GMP shall be updated from previously submitted value engineering and shall reflect the “final acceptance” of VE items, which are part of the scope of work. The VE schedule shall identify current acceptance and the date of acceptance in an adjacent column. VE items must be resolved and accepted by County prior to GMP submittal.

Related to PRE SUBMITTAL REQUIREMENTS

  • Submittal Requirements To comply with Subsection 4.1, Consultant shall submit the following: a. Certificate of Liability Insurance in the amounts specified in the section; and b. Waiver of Subrogation Endorsement as required by the section.

  • Capital Requirements If any Lender or the L/C Issuer determines that any Change in Law affecting such Lender or the L/C Issuer or any Lending Office of such Lender or such Lender’s or the L/C Issuer’s holding company, if any, regarding capital requirements has or would have the effect of reducing the rate of return on such Lender’s or the L/C Issuer’s capital or on the capital of such Lender’s or the L/C Issuer’s holding company, if any, as a consequence of this Agreement, the Commitments of such Lender or the Loans made by, or participations in Letters of Credit held by, such Lender, or the Letters of Credit issued by the L/C Issuer, to a level below that which such Lender or the L/C Issuer or such Lender’s or the L/C Issuer’s holding company could have achieved but for such Change in Law (taking into consideration such Lender’s or the L/C Issuer’s policies and the policies of such Lender’s or the L/C Issuer’s holding company with respect to capital adequacy), then from time to time the Borrower will pay to such Lender or the L/C Issuer, as the case may be, such additional amount or amounts as will compensate such Lender or the L/C Issuer or such Lender’s or the L/C Issuer’s holding company for any such reduction suffered.

  • Additional Requirements As a condition precedent to the execution and Delivery, the registration of issuance, transfer, split-up, combination or surrender, of any ADS, the delivery of any distribution thereon, or the withdrawal of any Deposited Property, the Depositary or the Custodian may require (i) payment from the depositor of Shares or presenter of ADSs or of an ADR of a sum sufficient to reimburse it for any tax or other governmental charge and any stock transfer or registration fee with respect thereto (including any such tax or charge and fee with respect to Shares being deposited or withdrawn) and payment of any applicable fees and charges of the Depositary as provided in Section 5.9 and Exhibit B, (ii) the production of proof reasonably satisfactory to it as to the identity and genuineness of any signature or any other matter contemplated by Section 3.1, and (iii) compliance with (A) any laws or governmental regulations relating to the execution and Delivery of ADRs or ADSs or to the withdrawal of Deposited Securities and (B) such reasonable regulations as the Depositary and the Company may establish consistent with the provisions of the representative ADR, if applicable, the Deposit Agreement and applicable law.

  • Minimum Vendor Legal Requirements Vendor shall remain aware of and comply with this Agreement and all local, state, and federal laws governing the sale of products/services offered by Vendor under this contract. Such applicable laws, ordinances, and policies must be complied with even if not specified herein.

  • Operational Requirements The Client will adhere to the deadlines and other operational requirements set out in the Client Publications, to facilitate meeting the requirements of CSD’s, Third Party Agents and Market Participants.