Procedure for Change. 3.1 Any proposed Change will be considered by the STAR Steering Group at its next meeting. The STAR Steering Group will consider the impact of any proposed Change and how the Change should be implemented. 3.2 Following a STAR Steering Group decision on how best to implement a Change, the final decided approach will be notified to the Member as well as each other STAR Participant that has directly entered into an agreement with CTHS. 3.3 Where any variation is to be made to the terms of this Agreement, then the STAR Steering Group shall notify such variation to the Member thirty (30) days in advance of the implementation of such variation. The Member may terminate this Agreement in accordance with Clause 20.1 where it disagrees with any Change.
Procedure for Change of Scope beyond 5% (a) NGS/ SMC shall whenever it desires provision of addition/ deletion of works and services beyond 5%, issue to the Concessionaire a notice of Change of Scope (the "Change of Scope Notice") through the Independent Consultant.
Procedure for Change of Scope beyond 5% (a) NGS/ SMC shall whenever it desires provision of addition/ deletion of works and services beyond 5%, issue to the Concessionaire a notice of Change of Scope (the "Change of Scope Notice") through the Independent Consultant. (b) Upon receipt of Change of Scope Notice, the Concessionaire shall, within a period of 15 (fifteen) days, provide to the Independent Consultant such information as is necessary and reasonable together with preliminary documentation in support of the following: (i) the impact which the Change of Scope is likely to have on the Project Completion Schedule if the work is required to be carried out before COD, and (ii) the options for implementing the proposed Change of Scope and the effect, if any, each such option would have on the costs and time thereof, including a detailed breakdown by work classifications specifying the material and labour costs calculated in accordance with the schedule of rates applicable to the works assigned by the Authority to its contractors, along with the proposed premium/discount on such rates. (c) Independent Consultant shall review the information provided by the Concessionaire, assess the change in quantities of items of work, verify the analysis of rates if required, determine the addition/reduction in the cost to the Concessionaire as a result of such Change of Scope The Independent Consultant shall communicate its recommendation to the Monitoring Committee within a period of 15 (fifteen) days from the receipt of information from the Concessionaire. (d) NGS/ SMC shall issue the Change of Scope Order within a period of 15 (fifteen) days from the date of recommendation made by the Independent Consultant in accordance with preceding sub-article (c) above. (e) The Change of Scope Order shall be effective and binding upon receipt thereof by the Concessionaire. Notwithstanding a Dispute regarding cost and time for implementation of such order, the Concessionaire shall proceed with the performance of such order promptly following receipt thereof. Any Dispute regarding the extension in the Concession Period recommended by the Independent Consultant shall be resolved in accordance with the Dispute Resolution Procedure. (f) All calculations by the Concessionaire pursuant to this Article 13.2 shall be supported by such documentation as is reasonably sufficient for Independent Consultant to determine the accuracy thereof, including invoices from Contractors and certification of such calculatio...

Related to Procedure for Change

  • Procedure for Change of Scope 16.2.1 In the event of the Authority determining that a Change of Scope is necessary, it shall issue to the Concessionaire a notice specifying in reasonable detail the works and services contemplated thereunder (the “Change of Scope Notice”). 16.2.2 Upon receipt of a Change of Scope Notice, the Concessionaire shall, with due diligence, provide to the Authority such information as is necessary, together with preliminary Documentation in support of: (a) the impact, if any, which the Change of Scope is likely to have on the Project Completion Schedule if the works or services are required to be carried out during the Construction Period; and (b) the options for implementing the proposed Change of Scope and the effect, if any, each such option would have on the costs and time thereof, including a detailed breakdown by work classifications specifying the material and labour costs calculated in accordance with the schedule of rates applicable to the works assigned by the Authority to its contractors, along with the proposed premium/discount on such rates; provided that the cost incurred by the Concessionaire in providing such information shall be reimbursed by the Authority to the extent such cost is certified by the Independent Engineer as reasonable. 16.2.3 Upon receipt of information set forth in Clause 16.2.2, if the Authority decides to proceed with the Change of Scope, it shall convey its preferred option to the Concessionaire, and the Parties shall, with assistance of the Independent Engineer, thereupon make good faith efforts to agree upon the time and costs for implementation thereof. Upon reaching an agreement, the Authority shall issue an order (the “Change of Scope Order”) requiring the Concessionaire to proceed with the performance thereof. In the event that the Parties are unable to agree, the Authority may, by issuing a Change of Scope Order, require the Concessionaire to proceed with the performance thereof pending resolution of the Dispute, or carry out the works in accordance with Clause 16.5. 16.2.4 The provisions of this Agreement, insofar as they relate to Construction Works and Tests, shall apply mutatis mutandis to the works undertaken by the Concessionaire under this Article 16.

  • Procedure for Offer Subject to the terms hereof, Landlord shall notify Tenant (the “First Offer Notice”) prior to entering into any lease with a third party for the First Offer Space, which notice shall outline the base rent, allowance amounts if any, length of term, and other economic terms on which Landlord would be willing to lease the First Offer Space (as set forth in such proposal) to Tenant (the “Fundamental Terms”). Pursuant to such First Offer Notice, Landlord shall offer to lease to Tenant the applicable First Offer Space on the Fundamental Terms.

  • Procedure for Rebate The Association represents to the Board that an internal rebate procedure has been established in accordance with Section 4117.09(C) of the Revised Code and that a procedure for challenging the amount of the representation fee has been established and will be given to each member of the bargaining unit who does not join the Association and that such procedure and notice shall be in compliance with all applicable state and federal laws and the Constitutions of the United States and the State of Ohio.

  • Procedure for taking possession - The Promoter, upon obtaining the occupancy certificate* from the competent authority shall offer in writing the possession of the [Apartment/Plot], to the Allottee in terms of this Agreement to be taken within two months from the date of issue of occupancy certificate. [Provided that, in the absence of local law, the conveyance deed in favour of the allottee shall be carried out by the promoter within 3 months from the date of issue of occupancy certificate]. The Promoter agrees and undertakes to indemnify the Allottee in case of failure of fulfilment of any of the provisions, formalities, documentation on part of the Promoter. The Allottee, after taking possession, agree(s) to pay the maintenance charges as determined by the Promoter/association of allottees, as the case may be after the issuance of the completion certificate for the project. The promoter shall hand over the occupancy certificate of the apartment/plot, as the case may be, to the allottee at the time of conveyance of the same.

  • Procedure for Closing If Buyer shall not timely elect to terminate this Contract under Section 13.2 above, or if the loss, damage or condemnation is not substantial, Seller agrees to pay to Buyer at the Closing all insurance proceeds or condemnation awards which Seller has received as a result of the same, plus an amount equal to the insurance deductible, and assign to Buyer all insurance proceeds and condemnation awards payable as a result of the same, in which event the Closing shall occur without Seller replacing or repairing such damage. In the case of damage or casualty, at Buyer’s election, Seller shall repair and restore the Property to its condition immediately prior to such damage or casualty and shall assign to Buyer all excess insurance proceeds.