Project Change Clause Samples

The Project Change clause defines the process for making modifications to the scope, timeline, or deliverables of a project after the initial agreement has been established. Typically, this clause outlines how either party can propose changes, the steps required for review and approval, and any adjustments to costs or deadlines that may result. By formalizing how changes are managed, the clause helps prevent misunderstandings and disputes, ensuring that both parties remain aligned and that the project can adapt to evolving needs without jeopardizing its success.
POPULAR SAMPLE Copied 1 times
Project Change. If either a R&D Services Provider or a R&D Services Recipient proposes changes in a Project, the R&D Services Providers and R&D Services Recipients for the applicable Statement of Work shall discuss such changes, but no changes shall be binding unless mutually agreed upon in writing. If the applicable R&D Services Providers and R&D Services Recipients do not agree to any changes proposed with respect to a given Project, either the R&D Services Providers or the R&D Services Recipients may terminate that Project upon providing the other party with at least forty-five (45) days’ prior written notice of their intention to terminate, provided that the R&D Services Providers or the R&D Services Recipients, as applicable, shall reimburse the other party for any and all reasonable, direct and documented costs of the early termination; provided, further that the R&D Services Providers and the R&D Services Recipients shall exercise reasonable efforts in good faith to mitigate and reduce such costs, including applying resources to other Projects, where feasible. Other than with respect to the foregoing right of termination, if the R&D Services Recipients fail to agree on a change, the Project scope, funding, timing, and other items shall remain, and the R&D Services shall proceed, as specified in the applicable Statement of Work.
Project Change. If either GE Digital or the applicable ▇▇▇▇▇ ▇▇▇▇▇▇ Entity proposes changes in a Project, GE Digital and the applicable ▇▇▇▇▇ ▇▇▇▇▇▇ Entity for the applicable Statement of Work shall discuss such changes, but no changes shall be binding unless mutually agreed upon in writing. Other than with respect to the foregoing right of election, if GE Digital and the applicable ▇▇▇▇▇ ▇▇▇▇▇▇ Entity fails to agree on a change, the Project scope, funding, timing, and other items shall remain, and the New Services shall proceed, as specified in the applicable Statement of Work.
Project Change. The Recipient shall not, without the prior written consent of the City, alter the scope or timing of the Project or permit or cause any material change to the Project.
Project Change. 7.1 During the Project and the Provider Royalty Period, if either party wishes to make changes to the Licensed Software, or change any component thereof (collectively referred to as a "Change"), both parties shall comply with the procedures set forth in Sections 7.2 through 7.5
Project Change. In the event CLIENT, the Project owner, Architect, Structural/Civil Engineer or other party makes any changes in the initial information provided by the client, including, but not limited to the size and location of the planned improvements, or makes any changes or alterations to any plans and/or specifications provided to ALPHA, CLIENT agrees to defend and hold ALPHA harmless from any liability arising out of such changes, and CLIENT assumes full responsibility for any claims, damages or liabilities arising out of or related to such changes unless CLIENT has given ALPHA prior written notice of such changes and has received from ALPHA written consent for such changes.
Project Change. 5.1. The Team Leader may require a project change at any time (which may include reducing or increasing the scope of the Product Vision). 5.2. Any change to the Charges shall be calculated in accordance with Schedule 22 (Charges and Invoicing).
Project Change. See §9.2. Project Costs All costs and expenses of any kind which have been or will be incurred in connection with the Project, including, without limitation, the acquisition of the Land and the construction, equipping, operation, financing, marketing, sale, leasing, and maintenance of the Project through the Maturity Date.
Project Change sany (1) change tothe Total Project Costs forecastsin excess ofive percent 5(%) of total forecastedEligible Project Costs or (2) any proposedchange to the construction schedule for the Project in excess of five percent 5( %) of the total number of days reflected in the Crouncstiton Schedule attached aSschedule II;
Project Change. You must let us know of any circumstances that have, or could, result in a Project Change as soon as practicable, but no more than 7 days, after you become aware of such circumstances. You must meet with us as soon as practicable, but no more than 7 days, after notifying us of any circumstances that have, or could, result in a Project Change. Notification of a Project Change should consider, among other things: – The details of, and reasons for, a Project Change; – What effect, if any, a Project Change could have on other Projects; – Strategies on how to remove or limit any negative effect of a Project Change; – If relevant, a proposed new completion date for the Project or Projects; and – Any criteria under which the funding or resources were granted.

Related to Project Change

  • Project Changes Project changes prior to bid opening shall be made by addendum to plans and specifications. Changes after bid opening shall be made by change order. The Local Government shall submit all addenda and all change orders to the Department for an eligibility determination. After execution of all construction, equipment and materials contracts, the Project contingency may be reduced.

  • Contract Changes Changes may not be made in the terms and conditions of this contract without the agreement and written permission of the Director of Housing.

  • Project Budget A Project Budget shall be prepared and maintained by Grantee. The Project Budget shall detail all costs for which the Grant will be used during the Term. The Project Budget must be approved in writing by the Project Monitor. Grantee shall carry out the Project and shall incur costs and make disbursements of funds provided hereunder by the Sponsor only in conformity with the Project Budget. The current approved Project Budget is contained in Attachment “C”. Said Project Budget may be revised from time to time, but no Project Budget or revision thereof shall be effective unless and until the same is approved in writing by Project Monitor. The funds granted under this Grant Contract cannot be used to supplant (replace) other existing funds.

  • Construction Budget The total amount of funds indicated by the District for the entire Project plus all other costs, including design, construction, administration, and financing.

  • Project Schedule Construction must begin within 30 days of the date set forth in Appendix A, Page 2, for the start of construction, or this Agreement may become null and void, at the sole discretion of the Director. However, the Recipient may apply to the Director in writing for an extension of the date to initiate construction. The Recipient shall specify the reasons for the delay in the start of construction and provide the Director with a new start of construction date. The Director will review such requests for extensions and may extend the start date, providing that the Project can be completed within a reasonable time frame.