Project Schedule Detail Clause Samples

The Project Schedule Detail clause defines the specific timeline and milestones for completing a project. It typically outlines key dates, deliverables, and dependencies, providing a clear roadmap for both parties to follow throughout the project's duration. By establishing these details, the clause ensures that expectations are aligned, progress can be tracked, and accountability is maintained, ultimately reducing the risk of delays and misunderstandings.
Project Schedule Detail. Contractor shall submit a work breakdown structure and proposed project schedule that captures key features of work for each facility as defined in the task order PWS. Contractor schedule shall contain milestone start dates, end dates, and durations for pre-NTP, abatement, demolition, and site restoration for each facility. Contractor shall identify the project critical path and those activities that cannot slip without affecting the schedule for the overall contract. Contractor shall maintain project schedule through acceptance of the Demolition Final Report and shall communicate project and activity status to the COR. Contractor shall submit all proposed changes to the project schedule to the COR for review. Contractor shall not extend schedule beyond contract period of performance without written approval of the KO.
Project Schedule Detail. 7.1.1 Prior to issuance of Notice to Proceed with Design Services, DESIGN‐BUILDER shall submit for review and acceptance by TAX COLLECTOR the Project Schedule Detail. The Project Schedule Detail shall be in conformance with and incorporate the milestones indicated in Appendix 2 Project Schedule. The Project Schedule Detail (▇▇▇▇▇▇▇▇ ▇▇) shall be provided in the same format and shall provide the same level of detail as shown on the Project Schedule submitted with the DESIGN‐BUILDER’S Proposal. The Project Schedule Detail shall be in conformance with the requirements of the RFP Documents and this AGREEMENT.

Related to Project Schedule Detail

  • Project Schedule Construction must begin within 30 days of the date set forth in Appendix A, Page 2, for the start of construction, or this Agreement may become null and void, at the sole discretion of the Director. However, the Recipient may apply to the Director in writing for an extension of the date to initiate construction. The Recipient shall specify the reasons for the delay in the start of construction and provide the Director with a new start of construction date. The Director will review such requests for extensions and may extend the start date, providing that the Project can be completed within a reasonable time frame.

  • Development Schedule The Project shall substantially comply with the specific timetables and triggers for action set forth in Article 5 of this Agreement. The parties acknowledge that, as provided in G.S. 160A-400.25(b), the failure to meet a commencement or completion date shall not, in and of itself, constitute a material breach of this Agreement pursuant to G.S. 160A-400.27 but must be judged based upon the totality of the circumstances.

  • Contract Schedule The information set forth in the Contract Schedule is true and correct.

  • Project Plan Development of Project Plan Upon the Authorized User’s request, the Contractor must develop a Project Plan. This Project Plan may include Implementation personnel, installation timeframes, escalation procedures and an acceptance plan as appropriate for the Services requested. Specific requirements of the plan will be defined in the RFQ. In response to the RFQ, the Contractor must agree to furnish all labor and supervision necessary to successfully perform Services procured from this Lot. Project Plan Document The Contractor will provide to the Authorized User, a Project Plan that may contain the following items: • Name of the Project Manager, Contact Phone Numbers and E-Mail Address; • Names of the Project Team Members, Contact Phone Numbers and E-Mail Address; • A list of Implementation milestones based on the Authorized User’s desired installation date; • A list of responsibilities of the Authorized User during system Implementation; • A list of designated Contractor Authorized Personnel; • Escalation procedures including management personnel contact numbers; • Full and complete documentation of all Implementation work; • Samples of knowledge transfer documentation; and • When applicable, a list of all materials and supplies required to complete the Implementation described in the RFQ. Materials and Supplies Required to Complete Implementation In the event that there are items required to complete an Implementation, the Contractor may request the items be added to its Contract if the items meet the scope of the Contract. Negotiation of Final Project Plan If the Authorized User chooses to require a full Project Plan, the State further reserves the right for Authorized Users to negotiate the final Project Plan with the apparent RFQ awardee. Such negotiation must not substantively change the scope of the RFQ plan, but can alter timeframes or other incidental factors of the final Project Plan. The Authorized User will provide the Contractor a minimum of five (5) business days’ notice of the final negotiation date. The Authorized User reserves the right to move to the next responsible and responsive bidder if Contractor negotiations are unsuccessful.

  • Project Scope The physical scope of the Project shall be limited to only those capital improvements as described in Appendix A of this Agreement. In the event that circumstances require a change in such physical scope, the change must be approved by the District Committee, recorded in the District Committee's official meeting minutes, and provided to the OPWC Director for the execution of an amendment to this Agreement.