Recovery of Schedule Delays Sample Clauses

POPULAR SAMPLE Copied 2 times
Recovery of Schedule Delays. If the Design Professional determines that the Project is one week or more behind schedule, per the approved Overall Project Schedule, the Design Professional shall so notify the Contractor in writing. Within seven days of the date of the Design Professional's notice, the Contractor shall deliver to the Design Professional and Owner a written plan explaining how the Contractor intends to bring the Project back on schedule. The Contractor's plan must provide sufficient detail to allow the Design Professional and Owner to determine the proposal's feasibility.
Recovery of Schedule Delays. If the Program Manager determines that the Project is one week or more behind schedule, per the approved Overall Project Schedule, the Program Manager shall so notify the Design-Builder in writing. Within seven days of the date of the Program Manager's notice, the Design-Builder shall deliver to the Program Manager and Owner a written plan explaining how the Design-Builder intends to bring the Project back on schedule. The Design-Builder's plan must provide sufficient detail to allow the Program Manager and Owner to determine the proposal's feasibility.
Recovery of Schedule Delays. If the Executive Administrator determines that the Project is one week or more behind schedule, per the approved Overall Project Schedule, the Executive Administrator shall so notify the Design-Builder in writing. Within seven days of the date of the Executive Administrator's notice, the Design- Builder shall deliver to the Executive Administrator and Owner a written plan explaining how the Design-Builder intends to bring the Project back on schedule. The Design-Builder's plan must provide sufficient detail to allow the Executive Administrator and Owner to determine the proposal's feasibility.
Recovery of Schedule Delays. Anytime after the first sixty (60) days of the Contract Time, if it is found by the Architect that the Project is two (2) weeks or more behind schedule, the Architect shall notify the Construction Manager in writing. Within seven (7) days of the date of the Architect notice, the Construction Manager shall, at no cost to the Owner, deliver to the Architect a written proposal explaining how the Construction Manager intends to bring the Project back on schedule. The Construction Manager's proposal must provide sufficient detail to allow the Architect to determine the proposal's feasibility. Further, at any time during the last sixty (60) days of the Contract Time that the Architect finds that the Construction Manager is one (1) week or more behind schedule per the Contract Time, the Architect shall notify the Construction Manager in writing. Within seven (7) days of the date of the Architect notice, the Construction Manager shall, at no cost to the Owner, prepare and deliver to the Architect a written proposal explaining how the Construction Manager intends to bring the Project back on schedule. The Construction Manager's proposal must provide the Architect with sufficient detail to allow the Architect to determine the proposal's feasibility.

Related to Recovery of Schedule Delays