Recovery on Termination. 94.1. Termination or expiry of the Contract shall be without prejudice to any rights and remedies of the Contractor and the Authority accrued before such termination or expiration and nothing in the Contract shall prejudice the right of either Party to recover any amount outstanding at such termination or expiry. 94.2. At the Expiry Date (and howsoever arising) the Contractor shall forthwith deliver to the Authority upon request all the Authority’s Property (including but not limited to materials, all data, documents, information, access keys) relating to the Contract in its possession or under its control or in the possession or under the control of any permitted suppliers or sub-contractors and in default of compliance with this clause the Authority may recover possession thereof and the Contractor grants licence to the Authority or its appointed agents to enter (for the purposes of such recovery) any premises of the Contractor or its permitted suppliers or sub-contractors where any such items may be held. 94.3. At the Expiry Date (howsoever arising) the Contractor shall forthwith provide assistance to the Authority and any new contractor appointed by the Authority to continue or take over the performance of the Contract in order to ensure an effective handover of all work then in progress. The Contractor shall provide such assistance free of charge. 94.4. The provisions of this clause shall survive the continuance of the Contract and indefinitely after its termination.
Appears in 1 contract
Sources: It Supplies and Services Contract
Recovery on Termination.
94.1. Termination or expiry of the Contract shall be without prejudice to any rights and remedies of the Contractor and the Authority accrued before such termination or expiration and nothing in the Contract shall prejudice the right of either Party to recover any amount outstanding at such termination or expiry.
94.2. At the Expiry Date (and howsoever arising) the Contractor shall forthwith deliver to the Authority upon request all the Authority’s Property (including but not limited to materials, all data, documents, information, access keys) relating to the Contract in its possession or under its control or in the possession or under the control of any permitted suppliers or sub-contractors and in default of compliance with this clause the Authority may recover possession thereof and the Contractor grants licence to the Authority or its appointed agents to enter (for the purposes of such recovery) any premises of the Contractor or its permitted suppliers or sub-contractors where any such items may be held.
94.3. At the Expiry Date (howsoever arising) the Contractor shall forthwith provide assistance to the Authority and any new contractor appointed by the Authority to continue or take over the performance of the Contract in order to ensure an effective handover of all work then in progress. The Contractor shall provide such assistance free of charge.
94.4. The provisions of this clause shall survive the continuance of the Contract and indefinitely after its termination.