REMOVAL OF SHOULDER BERMS Sample Clauses
The 'Removal of Shoulder Berms' clause requires the contractor to eliminate accumulated material or build-up along the roadway shoulders, known as berms. This typically involves grading or scraping the shoulder area to restore proper drainage and maintain the intended road profile. By mandating the removal of these berms, the clause ensures that water can flow off the roadway as designed, preventing water pooling, reducing the risk of pavement damage, and enhancing overall road safety.
REMOVAL OF SHOULDER BERMS. Purchaser shall remove berms from road shoulders to permit the escape of runoff. The construction of ditchouts will be required where ponding will result from the effects of sidecast debris.
REMOVAL OF SHOULDER BERMS. Purchaser shall remove berms from road shoulders to perit escape of runoff. Purchaser shall install culverts as part of this contract. Culverts must be installed concurrently with subgrade work and must be installed before subgrade compaction and rock application. Culvert locations and the minimum requirements for culvert length and diameter are designated on the CULVERT AND DRAINAGE LIST. Culvert, downspout, and flume lengths may be adjusted to fit as-built conditions and may not terminate directly on unprotected soil. Culverts must meet the specifications in Clauses 10-15 through 10-23.
REMOVAL OF SHOULDER BERMS. On the following road(s), Purchaser shall remove berms from road shoulders. The construction of ditchouts is required where ponding could result from the effects of sidecast debris. Purchaser shall install culverts as part of this contract. Culverts must be installed concurrently with subgrade work and must be installed before subgrade compaction and rock application. Culvert locations and the minimum requirements for culvert length and diameter are designated on the CULVERT LIST. Culvert, downspout, and flume lengths may be adjusted to fit as-built conditions and may not terminate directly on unprotected soil. Culverts must be new material and meet the specifications in Clauses 10-15 through 10-23.
REMOVAL OF SHOULDER BERMS. Purchaser shall remove berms from road shoulders to permit escape of runoff.
REMOVAL OF SHOULDER BERMS. Purchaser shall remove berms from road shoulders to permit escape of runoff. Purchaser shall install culverts as part of this contract. Culverts must be installed concurrently with subgrade work and must be installed before subgrade compaction and rock application. Culvert locations and the minimum requirements for culvert length and diameter are designated on the CULVERT AND DRAINAGE LIST. Culvert, downspout, and flume lengths may be adjusted to fit as-built conditions and may not terminate directly on unprotected soil. Culverts must be new material and meet the specifications in Clauses 10-15 through 10-23 except as provided in clause 5-6 USED CULVERT MATERIAL. Purchaser may install used culverts on the following roads. All other roads must have new culverts installed. Purchaser shall install culvert markers in accordance with the CULVERT MARKER DETAIL at all newly installed permanent culverts.
REMOVAL OF SHOULDER BERMS. Purchaser shall remove berms from road shoulders except as specified in Clause 8-7 ROAD SHOULDER BERM INSTALLATION.
REMOVAL OF SHOULDER BERMS. Purchaser shall remove berms from road shoulders, except as specified in Clause 8-1. The construction of ditchouts is required where ponding could result from the effects of sidecast debris.
REMOVAL OF SHOULDER BERMS. On the following road(s), Purchaser shall remove berms from road shoulders. The construction of ditchouts is required where ponding could result from the effects of sidecast debris. R‐120 0+00 to 23+50 Purchaser shall install culverts as part of this contract. Culverts must be installed concurrently with subgrade work and must be installed before subgrade compaction and rock application. Culvert locations and the minimum requirements for culvert length and diameter are designated on the CULVERT LIST. Culvert, downspout, and flume lengths may be adjusted to fit as‐built conditions and may not terminate directly on unprotected soil. Culverts may be new or used material and must must meet the specifications in Clauses 10‐17 through 10‐22.
REMOVAL OF SHOULDER BERMS. On the following roads, Purchaser shall remove berms from road shoulders. T5030 0+00 to 45+45 T5030 48+40 to 83+40
REMOVAL OF SHOULDER BERMS. On the following road(s), berms shall be removed from road shoulders to permit the escape of runoff. Material shall be disposed of in accordance with Clauses 4-35 through 4-38. The construction of ditchouts will be required where ponding will result from the effects of sidecast debris. At no time shall puncheon be used in the subgrade, unless approved by the Contract Administrator. Culverts shall be installed as part of this contract. Culverts shall be installed concurrently with subgrade work and shall be installed before subgrade compaction and rock application. Culvert locations and the minimum requirements for culvert length and diameter are designated on the Culvert List. Culvert, downspout, and flume lengths shall be adjusted to fit as-built conditions and shall not terminate directly on unprotected soil. Culverts shall be new and meet the material specifications in Clauses 10-15 through 10- 23.