Replacement of the Engineer. If the Employer intends to replace the Engineer, the Employer shall, not less than 14 days before the intended date of replacement, give notice to the Contractor of the name, and address of the intended replacement Engineer.
Appears in 13 contracts
Sources: Crane Supply Contract, Crane Supply Contract, Crane Supply Contract
Replacement of the Engineer. If the Employer intends to replace the Engineer, the Employer shall, not less than 14 21 days before the intended date of replacement, give notice to the Contractor of the name, address and address relevant experience of the intended replacement Engineer. If the Contractor considers the intended replacement Engineer to be unsuitable, he has the right to raise objection against him by notice to the Employer, with supporting particulars, and the Employer shall give full and fair consideration to this objection.
Appears in 5 contracts
Sources: Contract Agreement, Construction Contract, Construction Contract
Replacement of the Engineer. If the Employer intends to replace the Engineer, the Employer shall, not less than 14 42 days before the intended date of replacement, give notice to the Contractor of the name, address and address relevant experience of the intended replacement Engineer. The Employer shall not replace the Engineer with a person against whom the Contractor raises reasonable objection by notice to the Employer, with supporting particulars.
Appears in 4 contracts
Sources: Contract Agreement, Contract Agreement, Contract Agreement
Replacement of the Engineer. If the Employer intends to replace the Engineer, the Employer shall, not less than 14 days before the intended date of replacement, give notice to the Contractor of the name, and address of the intended replacement Engineer. The Contractor may only raise objection by notice in writing to the Employer, on the grounds that the Engineer does not have the relevant competence to act under this Contract. The Contractor's objection must be supported by particulars.
Appears in 2 contracts
Sources: Contractor Agreement, Contractor Agreement
Replacement of the Engineer. If the Employer intends to replace the Engineer, the Employer shall, not less than 14 42 days before the intended date of replacement, give notice to the Contractor of the name, address, and address relevant experience of the intended replacement Engineer. The Engineer shall not replace the Engineer with a person against whom the Contractor raises reasonable objection by notice to the Employer, with supporting particulars.
Appears in 1 contract
Sources: Framework Agreement