Residual Impacts Clause Samples

The Residual Impacts clause defines how certain effects or consequences that remain after a contract's completion or termination are addressed. Typically, this clause clarifies which party is responsible for managing or mitigating ongoing impacts, such as environmental effects, data retention, or lingering liabilities, that persist beyond the contract period. Its core function is to allocate responsibility for these ongoing issues, ensuring that both parties understand their obligations and reducing the risk of future disputes related to unresolved impacts.
Residual Impacts. 5.4.5.1 Prediction of mitigated noise levels are presented in the following sections. Various mitigation measures for different construction phases are proposed. Worst case noise levels are presented in the tables and noise levels at other elevations are given in Appendix 5.1.
Residual Impacts. 4.7.5.1 No adverse residual air quality impacts, from vehicle or odour emissions, are anticipated from the operation phase of the Telegraph Bay Development.
Residual Impacts. 11.9.1.1 No residual terrestrial archaeological and built heritage impacts are predicted after the implementation of the recommended mitigation measures. 11.9.1.2 In addition, no marine archaeological impacts are predicted and as such, no residual impacts will occur.
Residual Impacts. Impacts that remain after the effect of mitigation measures have been accounted for. Specific, Measurable, Achievable, Relevant, Time-bound (specific) objective. Generic term used to describe environmental assessment as applied to policies, plans and programmes. An appraisal of the economic, environmental and social effects of a plan from the outset of the preparation process to allow decisions to be made that accord with sustainable development. A widely-used and accepted international definition of sustainable development is ‘Development which meets the needs of the present without compromising the ability of future generations to meet their own needs’.
Residual Impacts. Residual Landscape Impact
Residual Impacts. 13.7.1.1 No significant contaminated land impacts are predicted during the construction and operational phases and as such, no residual impacts are also predicted.
Residual Impacts 

Related to Residual Impacts

  • Decommissioning (a) The Contractor shall submit to the Designated Authority, for its approval, pursuant to sub-paragraph 4.11(d)(v), a Decommissioning Plan for the Development Area and a schedule of provisions for the Decommissioning Costs Reserve. (b) The Decommissioning Plan shall be revised and resubmitted to the Designated Authority for its approval at such times as are reasonable having regard to the likelihood that the Decommissioning Plan (including cost estimates thereunder) may need to be revised. (c) The Contractor shall carry out the Decommissioning Plan substantially in accordance with its terms. (d) Estimates of the monies required for the funding of the Decommissioning Plan shall be charged as Recoverable Costs beginning in the Calendar Year following the Calendar Year in which Commercial Production first occurs. The amount charged in each Calendar Year shall be calculated as follows: (i) The total Decommissioning costs at the expected date of Decommissioning shall first be calculated. (ii) There shall be deducted from such total Decommissioning costs the additions made to the Decommissioning Costs Reserve made, and taken as Recoverable Costs, in all previous Calendar Years together with interest on such Recoverable Costs calculated to the approved date of Decommissioning at the actual or forecast rate of Uplift (whichever is applicable). (iii) The residual Decommissioning costs, resulting from the calculations under sub-paragraph 4.14(d)(i) and (ii), shall then be discounted to the Calendar Year in question at the forecast rate of Uplift for each Calendar Year remaining until the Calendar Year of Decommissioning. (iv) The discounted total of residual Decommissioning costs shall then be divided by the total number of Calendar Years remaining prior to the Calendar Year of Decommissioning itself, including the Calendar Year in question. (v) The resultant amount shall be the addition to the Decommissioning Costs Reserve for the Calendar Year in question. (vi) It is the intention of this provision that the total accumulated provision allowed, including interest calculated to the Calendar Year of Decommissioning at the rate of Uplift, will equal the total Decommissioning costs. (vii) If the amount in sub-paragraph 4.14(d)(v) is a negative amount, then such amount shall be treated as a reduction of Recoverable Costs for the Calendar Year in question.

  • Operating Environment Per specifications given in Ref. [1]

  • Initiating Interconnection 4.1 If ENT determines to offer Telephone Exchange Services and to interconnect with Verizon in any LATA in which Verizon also offers Telephone Exchange Services and in which the Parties are not already interconnected pursuant to this Agreement, ENT shall provide written notice to Verizon of the need to establish Interconnection in such LATA pursuant to this Agreement. 4.2 The notice provided in Section 4.1 of this Attachment shall include (a) the initial Routing Point(s); (b) the applicable technically feasible Point(s) of Interconnection on Verizon’s network to be established in the relevant LATA in accordance with this Agreement; (c) ENT’s intended Interconnection activation date; (d) a forecast of ENT’s trunking requirements conforming to Section 14.2 of this Attachment; and (e) such other information as Verizon shall reasonably request in order to facilitate Interconnection. 4.3 The interconnection activation date in the new LATA shall be mutually agreed to by the Parties after receipt by Verizon of all necessary information as indicated above. Within ten (10) Business Days of Verizon’s receipt of ENT’s notice provided for in Section 4.1of this Attachment, Verizon and ENT shall confirm the technically feasible Point of Interconnection on Verizon’s network in the new LATA and the mutually agreed upon Interconnection activation date for the new LATA.

  • Cost Responsibility for Interconnection Facilities and Distribution Upgrades 4.1 Interconnection Facilities 4.2 Distribution Upgrades

  • Proposing Integration Activities in the Planning Submission No integration activity described in section 6.3 may be proposed in a CAPS unless the Funder has consented, in writing, to its inclusion pursuant to the process set out in section 6.3(b).