Common use of Response to Change Request Clause in Contracts

Response to Change Request. Contractor shall respond to any such requested change in writing to Purchaser within thirty (30) days after receipt of such requested change; provided, however, in the case of a stop Work direction, Contractor shall stop Work immediately to the extent specified by Purchaser. Contractor shall use commercially reasonable efforts to require its subcontractors with Major Subcontracts to agree to a stop Work provision that minimizes Contractor’s costs and is consistent with the terms of this Article 16.

Appears in 2 contracts

Sources: Contract for Terrestar 1 (Terrestar Corp), Contract for Terrestar 2 (Terrestar Corp)