Schedule of Design Services Sample Clauses

The "Schedule of Design Services" clause defines the timeline and sequence for the delivery of design-related tasks within a project. It typically outlines key milestones, deadlines, and the order in which specific design services—such as concept development, schematic design, and final drawings—must be completed. By clearly establishing when each phase of design work is due, this clause helps coordinate project activities, manage expectations, and reduce the risk of delays or misunderstandings regarding deliverable timing.
POPULAR SAMPLE Copied 1 times
Schedule of Design Services. As a supplement to and consistent with the project schedule attached hereto and referenced in Paragraph 1.2, and to the extent not already a part of said project schedule, Design/Builder shall submit for Owner’s approval a design schedule for the performance of Design/Builder’s Design Services which shall include allowance for reasonable time required for Owner’s review of submissions and for approvals of authorities having jurisdiction over the Project, and which shall describe in detail the break-down of the portions of the Detailed Design specified by Design/Builder in completing the entire Detailed Design, and the dates by which those specified portions of the Detailed Design will be completed. The design schedule, when approved by Owner, shall not, except for good cause, be exceeded by Design/Builder. Should Design/Builder, at any time during the course of performing the Agreement, have any reason to believe that it will be unable to meet any completion date in accordance with the design schedule, it shall promptly notify Owner’s Representative in writing. In such notice, Design/Builder shall state the reason for the delay, including the party responsible, if any, and the steps being taken to remedy or minimize the impact of the delay. Failure of Design/Builder to submit such notice shall constitute a waiver by Design/Builder of any claim for an adjustment to the design schedule or the Contract Time. Subject to the provisions of Paragraph 12.7 of this Agreement, Owner shall review and approve, where appropriate, the design schedule, or any portion thereof. The design schedule shall be incorporated into and be a part of the project schedule.
Schedule of Design Services. Design/Builder shall submit for Owner's approval the Design Schedule for the performance of Design/Builder's Design Services which shall include allowance for reasonable time required for Owner's review of submissions and for approvals of authorities having jurisdiction over the Project. The Design Schedule, when approved by Owner, shall not, except for good cause, be exceeded by Design/Builder. Should Design/Builder at any time during the course of performing the Contract, have any reason to believe that it will be unable to meet any completion date in accordance with the Design Schedule, it shall immediately notify Owner's Representative in writing. In such notice, Design/Builder shall state the reason for the delay including the party responsible, if any, and the steps being taken to remedy or minimize the impact of the delay. Failure of Design/Builder to submit such notice shall constitute a waiver by Design/Builder of any claim for an adjustment to the Contract Price, the Design Schedule, or the Contract Time. All extensions of time shall be governed by Articles 16 and 17 of this Agreement. Subject to the provisions of Section 13.7 of this Agreement, Owner shall review and approve, where appropriate, the Design Schedule, or any portion thereof.
Schedule of Design Services. Design/Builder shall, within ten (10) calendar days after execution of the Contract, submit for Owner's approval the Design Schedule for the performance of Design/Builder's Design Services, which shall include allowance for reasonable time required for the Director's review of submissions and for approvals of authorities having jurisdiction over the Project. This Schedule shall, upon approval by the Director, be considered incorporated and made a part of this Contract as Exhibit A. The Design Schedule, when approved by the Director, shall not, except for good cause, be exceeded by Design/Builder. Should Design/Builder at any time during the course of performing the Contract, have reason to believe that it will be unable to meet any completion date in accordance with the Design Schedule, it shall immediately notify the Director in writing. Design/Builder shall state the reason for the delay in the notice, including the party responsible, if any, and the steps being taken to remedy or minimize the impact of the delay. Failure of Design/Builder to submit such notice shall constitute a waiver by Design/Builder of any claim for an adjustment to the Contract Price, the Design Schedule, or the Contract Time. All extensions of time shall be governed by Articles 16 and 17 of this Agreement. Subject to the provisions of Paragraph 13(G) of this Agreement, Owner shall review and approve, where appropriate, the Design Schedule, or any portion thereof.
Schedule of Design Services. Design/Builder shall begin design immediately after execution of the Contract. The Design Schedule is expected to last 150 days, but in no case will extend beyond December 31, 2020. The Design Schedule shall not, except for good cause, be exceeded by Design/Builder. Preliminary Design Submittal 08/20/2020 Final Design Submittal 11/28/2020 Permits 09/29/2020 Should Design/Builder at any time during the course of performing the Contract, have reason to believe that it will be unable to meet any completion date in accordance with the Design Schedule, it shall immediately notify the Director in writing. Design/Builder shall state the reason for the delay in the notice, including the party responsible, if any, and the steps being taken to remedy or minimize the impact of the delay. Failure of Design/Builder to submit such notice shall constitute a waiver by Design/Builder of any claim for an adjustment to the Contract Price, the Design Schedule, or the Contract Time. All extensions of time shall be governed by Articles 16 and 17 of this Agreement. Subject to the provisions of Paragraph 13(G) of this Agreement, Owner shall review and approve, where appropriate, the Design Schedule, or any portion thereof.
Schedule of Design Services. As a supplement to and consistent with the project schedule attached hereto and referenced in Paragraph 1.2, and to the extent not already a part of said project schedule, Design/Builder shall submit for Owner’s approval a design schedule for the performance of Design/Builder’s Design Services which shall include allowance for reasonable time required for Owner’s review of submissions and for approvals of authorities having jurisdiction over the Project, and which shall describe in detail the break-down of the portions of the Detailed Design specified by Design/Builder in completing the entire Detailed Design, and the dates by which those specified portions of the Detailed Design will be completed. The design schedule, when approved by Owner, shall not, except for good cause, be exceeded by Design/Builder. Should Design/Builder, at any time during the course of performing the Agreement, have any reason to believe that it will be unable to meet any completion date in
Schedule of Design Services. Design-Builder shall, within ten (10) calendar days after award of the Contract and prior to City’s issuance of a written Notice to Proceed, submit for City's approval the baseline Design Schedule, addressing each stage of design shown in EXHIBIT I: DESIGN TASKS AND DELIVERABLES FOR VERTICAL PROJECTS attached hereto and incorporated herein by reference, for the performance of Design-Builder's Design Services, which shall include allowance for fifteen (15) calendar days for City’s review of submissions and for approvals of authorities having jurisdiction over the Project. This Schedule shall, upon approval by City, be considered incorporated and made a part of this Contract, attached hereto, incorporated herein by reference and labeled as EXHIBIT F: DESIGN-BUILDER’S DESIGN SCHEDULE AND DESIGN FEE SCHEDULE. The Design Schedule, when approved by City, shall not, except for good cause, be exceeded by Design-Builder. Should Design-Builder at any time during the course of performing the Contract, have reason to believe that it will be unable to meet any completion date in accordance with the Design Schedule, it immediately shall notify City in writing, stating the reason for the delay, the party responsible for the delay (if any) and the steps being taken to remedy or minimize the impact of the delay. Failure of Design-Builder to submit such notification shall constitute a waiver by Design- Builder of any claim Design-Builder may have for an adjustment to the Contract Price, the Design Schedule or the Contract Time. All extensions of time shall be governed by ARTICLE VIII of City’s General Conditions for Design/Build Contracts. Subject to the provisions of ARTICLE VIII.2 of said General Conditions, City shall review and approve, where appropriate, the Design Schedule or any portion thereof.

Related to Schedule of Design Services

  • SCHEDULE OF WORK FIRST PARTY’S proposed schedule for the various services required will be set forth in Exhibit A-1. In addition to services described in Section A1, the parties may from time to time agree in writing that FIRST PARTY, for additional compensation, shall perform additional services including but not limited to: • Change in the services because of changes in scope of the work. • Additional tasks not specified herein as required by the CITY. The CITY and FIRST PARTY shall agree in writing to any changes in compensation and/or changes in FIRST PARTY’s services before the commencement of any work. If FIRST PARTY deems work he/she has been directed to perform is beyond the scope of this agreement and constitutes extra work, FIRST PARTY shall immediately inform the CITY in writing of the fact. The CITY shall make a determination as to whether such work is in fact beyond the scope of this agreement and constitutes extra work. In the event that the CITY determines that such work does constitute extra work, it shall provide compensation to the FIRST PARTY in accordance with an agreed cost that is fair and equitable. This cost will be mutually agreed upon by the CITY and FIRST PARTY. A supplemental agreement providing for such compensation for extra work shall be negotiated between the CITY and the FIRST PARTY. Such

  • ATTACHMENT A Equity Funds

  • SERVICE LEVEL DESCRIPTION The Fund Accounting Agreement is hereby amended by deleting the Service Level Description attached thereto and replacing it in its entirety with the Service Level Description attached hereto.

  • AMENDED EXHIBIT A The Fund Accounting Agreement is hereby amended by changing the name of T. Rowe Price Capital Appreciation Fund to T. Rowe Price Capital Appreciation Fund, Inc.; by changing the name of T. Rowe Price Equity Income Fund to T. Rowe Price Equity Income Fund, Inc.; by changing the name of T. Rowe Price GNMA Fund to T. Rowe Price GNMA Fund, Inc.; by changing the name of T. Rowe Price New America Growth Fund to T. Rowe Price New America Growth Fund, Inc.; by changing the name of T. Rowe Price State Tax-Free Income Trust to T. Rowe Price State Tax-Free Funds, Inc.; by changing the names of Georgia Tax-Free Bond Fund, Maryland Short-Term Tax-Free Bond Fund, Maryland Tax-Free Bond Fund, Maryland Tax-Free Money Fund, New Jersey Tax-Free Bond Fund, New York Tax-Free Bond Fund, New York Tax-Free Money Fund, and Virginia Tax-Free Bond Fund to T. Rowe Price Georgia Tax-Free Bond Fund, T. Rowe Price Maryland Short-Term Tax-Free Bond Fund, T. Rowe Price Maryland Tax-Free Bond Fund, T. Rowe Price Maryland Tax-Free Money Fund, T. Rowe Price New Jersey Tax-Free Bond Fund, T. Rowe Price New York Tax-Free Bond Fund, T. Rowe Price New York Tax-Free Money Fund, and T. Rowe Price Virginia Tax-Free Bond Fund, respectively, on behalf of T. Rowe Price State Tax-Free Funds, Inc.; by removing T. Rowe Price California Tax-Free Income Trust as a Mutual Fund – Parent; and by changing the names of California Tax-Free Bond Fund and California Tax-Free Money Fund to T. Rowe Price California Tax-Free Bond Fund and T. Rowe Price California Tax-Free Money Fund, respectively, and moving them under T. Rowe Price State Tax-Free Funds, Inc. as Mutual Fund – Series.

  • Second Amendment to Exhibit A to Services Agreement Exhibit A to the Services Agreement shall be, and here by is, supplemented with the following: