Common use of Schedule Requirements Clause in Contracts

Schedule Requirements. 2.4.4.2.1 The CPM schedule shall clearly show sequential interdependencies, with activity duration and float clearly represented. Sequence(s) of activities with no float shall be clearly identified as critical path(s). The scheduling system shall be capable of baseline comparison analysis. Upon development and approval of the schedule, the Contractor shall ‘freeze’ the initial schedule as the baseline schedule. As Work progresses, Construction Manager shall provide graphics displaying actual progress bars versus baseline or target bars. Activity durations shall be in calendar days. 2.4.4.2.2 The CPM schedule shall include pre-construction tasks, construction tasks (bid items), Shop Drawing submittal and approval process, material and equipment ordering and delivery, submittal of as-built drawings, clean up and punchlist, inspection coordination activities, utility relocation, final inspection and certificate of completion, and final payment. Submittal activities shall be scheduled to allow sufficient time for materials and equipment to be procured and installed, even if the submittal is unacceptable and resubmittal is required. The CPM schedule shall reflect anticipated delays, such as weather delays. 2.4.4.2.3 Construction Manager shall submit the initial schedule, complete revisions, and periodic reports in three hard copies, one reproducible and two prints or plots, and one copy digitally on CD or DVD. This schedule shall include the completed network program consisting of ▇▇▇▇▇ chart and mathematical analysis within ten (10) days of the executed Agreement. Allow five (5) days for the City to review. Construction Manager shall submit the schedule of submittal activities extracted from the master schedule within ten (10) days after receipt of Notice to Proceed. During the preparation period, Construction Manager shall review this information with the City. 2.4.4.2.4 Submittals to the City of initial and monthly CPM schedule charts shall include three (3) sets of all reports as outlined below. Plots shall be color, blueline, printed or photocopied prints and, if segmentally generated, fully assembled. Highlight the critical path when the critical path is not clearly defined. 2.4.4.2.5 The Construction Manager will participate in the City’s review and evaluation of submitted network diagrams and mathematical analysis of diagrams. Resubmit revisions necessary due to review within five (5) days after the review. Construction Manager and major Subcontractors shall review the network CPM schedule before final submittal.

Appears in 2 contracts

Sources: Construction Manager Agreement, Construction Manager Agreement

Schedule Requirements. 2.4.4.2.1 8.49.2.1 The CPM schedule shall clearly show sequential interdependencies, with activity duration and float clearly represented. Sequence(s) of activities with no float shall be clearly identified as critical path(s). The scheduling system shall be capable of baseline comparison analysis. Upon development and approval of the schedule, the Contractor shall 'freeze' the initial schedule as the baseline schedule. As Work progresses, Construction Manager Contractor shall provide graphics displaying actual progress bars versus baseline or target bars. Activity durations shall be in calendar days. 2.4.4.2.2 8.49.2.2 The CPM schedule shall include pre-construction tasks, construction tasks (bid items), Shop Drawing submittal and approval process, material and equipment ordering and delivery, submittal of as-built drawings, clean up and punchlist, inspection coordination activities, utility relocation, final inspection and certificate of completion, and final payment. Submittal activities shall be scheduled to allow sufficient time for materials and equipment to be procured and installed, even if the submittal is unacceptable and resubmittal is required. The CPM schedule shall reflect anticipated delays, such as weather delays. 2.4.4.2.3 8.49.2.3 Construction Manager shall submit the initial schedule, complete revisions, and periodic reports in three hard copies, one reproducible and two prints or plots, and one copy digitally on CD or DVD. This schedule shall include the completed network program consisting of ▇▇▇▇▇ chart and mathematical analysis within ten (10) days of the executed Agreement. Allow five (5) days for the City to review. Construction Manager shall submit the schedule of submittal activities extracted from the master schedule within ten (10) days after receipt of Notice to Proceed. During the preparation period, Construction Manager shall review this information with the City. 2.4.4.2.4 8.49.2.4 Submittals to the City of initial and monthly CPM schedule charts shall include three (3) sets of all reports as outlined below. Plots shall be color, blueline, printed or photocopied prints and, if segmentally generated, fully assembled. Highlight the critical path when the critical path is not clearly defined. 2.4.4.2.5 8.49.2.5 The Construction Manager will participate in the City’s 's review and evaluation of submitted network diagrams and mathematical analysis of diagrams. Resubmit revisions necessary due to review within five (5) days after the review. Construction Manager and major Subcontractors shall review the network CPM schedule before final submittal.

Appears in 1 contract

Sources: Construction Manager Agreement