Schematic Design Phase Services. § 3.2.1 The Architect shall review the program and other information furnished by the Owner, and shall review laws, codes, and regulations applicable to the Architect’s services. Architect will perform a detailed code and zoning review for the Project and consult with the Owner on any changes that impact the design. § 3.2.2 The Architect shall prepare a preliminary evaluation of the Owner’s program, schedule, budget for the Cost of the Work, Project site, the proposed procurement and delivery method, and other Initial Information, each in terms of the other, to ascertain the requirements of the Project. The Architect shall notify the Owner of (1) any inconsistencies discovered in the information, and (2) other information or consulting services that may be reasonably needed for the Project. § 3.2.3 The Architect shall present its preliminary evaluation to the Owner and shall discuss with the Owner alternative approaches to design and construction of the Project. The Architect shall reach an understanding with the Owner regarding the requirements of the Project. The Architect shall prepare and distribute meeting notes documenting the basic issues, resolutions and action items agreed to during the Schematic Design Phase. § 3.2.4 Based on the Project requirements agreed upon with the Owner, the Architect shall prepare and present, for the Owner’s approval, a preliminary design illustrating the scale and relationship of the Project components. § 3.2.5 Based on the Owner’s approval of the preliminary design, the Architect shall prepare Schematic Design Documents for the Owner’s approval. The Schematic Design Documents shall consist of drawings and other documents including a site plan, if appropriate, and preliminary building plans, sections and elevations; and may include some combination of study models, perspective sketches, or digital representations. Preliminary selections of major building systems and construction materials shall be noted on the drawings or described in writing. § 3.2.5.1 The Architect shall consider sustainable design alternatives, such as material choices and building orientation, together with other considerations based on program and aesthetics, in developing a design that is consistent with the Owner’s program, schedule and budget for the Cost of the Work. The Owner may obtain more advanced sustainable design services as a Supplemental Service under Section 4.1.1. § 3.2.5.2 The Architect shall consider the value of alternative materials, building systems and equipment, together with other considerations based on program and aesthetics, in developing a design for the Project that is consistent with the Owner’s program, schedule, and budget for the Cost of the Work. § 3.2.6 The Architect shall submit to the Owner an estimate of the Cost of the Work prepared in accordance with Section 6.3. The Architect shall submit to Owner an updated Project Schedule for the Project. § 3.2.7 The Architect shall submit the Schematic Design Documents to the Owner, and request the Owner’s approval. § 3.2.8 The Architect shall collaborate with the Owner to make adjustments to the scope of Work (Project requirements), Schematic Design cost opinion, and the Owner’s construction budget such that they are in agreement and approval prior to moving to the next phase.
Appears in 1 contract
Sources: Standard Form of Agreement Between Owner and Architect
Schematic Design Phase Services. § 3.2.1 3.3.1 The Architect shall review the program program, and other information furnished by the Owner, Owner and shall review laws, codes, and regulations applicable to the Architect’s services. Architect will perform a detailed code and zoning review for the Project and consult with the Owner on any changes that impact the design.Construction Manager,
§ 3.2.2 3.3.2 The Architect shall prepare a preliminary evaluation of review the Owner’s program, schedule, budget for the Cost of the Work, Project site, the proposed procurement and delivery method, and other Initial Information, each in terms of the other, to ascertain any changes to the requirements of the Project. The Architect shall notify the Owner of (1) any inconsistencies discovered in the information, and (2) other information or consulting services that may be reasonably needed for the Project. Substantial changes to the requirements of the Project following a successful referendum requiring rework or revision to the Architect’s completed documents or drawings are Additional Services.
§ 3.2.3 3.3.3 The Architect shall present its preliminary evaluation to the Owner and shall discuss with the Owner and Construction Manager alternative approaches to design and construction of the Project. The Architect shall reach an understanding with the Owner regarding the requirements of the Project. The Architect shall prepare and distribute meeting notes documenting the basic issues, resolutions and action items agreed to during the Schematic Design Phase.
§ 3.2.4 3.3.4 Based on the Project requirements agreed upon with the Owner, the Architect shall prepare and present, to the Owner and Construction Manager, for the Owner’s approval, a preliminary design illustrating the scale and relationship of the Project components.
§ 3.2.5 3.3.5 Based on the Owner’s approval of the preliminary design, the Architect shall prepare Schematic Design Documents for Construction Manager’s review and the Owner’s approval. The Schematic Design Documents shall consist of drawings and other documents including a site plan, if appropriate, and preliminary building plans, sections and elevations; and may include some combination of study models, perspective sketches, or digital representations. Preliminary selections of major building systems and construction materials shall be noted on the drawings or described in writing.shall
§ 3.2.5.1 3.3.5.1 The Architect shall consider sustainable design alternatives, such as material choices and building orientation, choice together with other considerations based on program and aesthetics, in developing a design that is consistent with the th Owner’s program, schedule and budget for the Cost of the Work. The Owner may obtain more advanced sustainable mor design services as a Supplemental Service under Section 4.1.14.1.
§ 3.2.5.2 3.3.5.2 The Architect shall consider with the value of alternative materials, Owner and the Construction Manager the valu building systems and equipment, together with other considerations based on program and aesthetics, in developing a ae design for the Project that is consistent with the Owner’s program, schedule, and budget for the Cost of the Work.
§ 3.2.6 The Architect shall submit to the Owner an estimate of the Cost of the Work prepared in accordance with Section 6.3. The Architect shall submit to Owner an updated Project Schedule for the Project.
§ 3.2.7 The Architect shall submit the Schematic Design Documents to the Owner, and request the Owner’s approval.
§ 3.2.8 The Architect shall collaborate with the Owner to make adjustments to the scope of Work (Project requirements), Schematic Design cost opinion, and the Owner’s construction budget such that they are in agreement and approval prior to moving to the next phase.t
Appears in 1 contract
Sources: Standard Form of Agreement Between Owner and Architect
Schematic Design Phase Services. § 3.2.1 The Architect shall review the program and other information furnished by the Owner, and shall review laws, codes, and regulations applicable to the Architect’s services. Architect will perform a detailed code and zoning review for the Project and consult with the Owner on any changes that impact the design.
§ 3.2.2 The Architect shall prepare a preliminary evaluation of the Owner’s program, schedule, budget for the Cost of the Work, Project site, the proposed procurement and delivery method, and other Initial Information, each in terms of the other, to ascertain the requirements of the Project. The Architect shall notify the Owner of (1) any inconsistencies discovered in the information, and (2) other information or consulting services that may be reasonably needed for the Project.
§ 3.2.3 The Architect shall present its preliminary evaluation to the Owner and shall discuss with the Owner alternative approaches to design and construction of the Project. The Architect shall reach an understanding with the Owner regarding the requirements of the Project. The Architect shall prepare and distribute meeting notes documenting the basic issues, resolutions and action items agreed to during the Schematic Design Phase.
§ 3.2.4 Based on the Project requirements agreed upon with the Owner, the Architect shall prepare and present, for the Owner’s approval, a preliminary design illustrating the scale and relationship of the Project components.
§ 3.2.5 Based on the Owner’s approval of the preliminary design, the Architect shall prepare Schematic Design Documents for the Owner’s approval. The Schematic Design Documents shall consist of drawings and other documents including a site plan, if appropriate, and preliminary building plans, sections and elevations; and may include some combination of study models, perspective sketches, or digital representations. Preliminary selections of major building systems and construction materials shall be noted on the drawings or described in writing. Architect shall coordinate the consultants’ Schematic Design Services.
§ 3.2.5.1 The Architect shall consider sustainable design alternatives, such as material choices and building orientation, together with other considerations based on program and aesthetics, in developing a design that is consistent with the Owner’s program, schedule and budget for the Cost of the Work. The Owner may obtain more advanced sustainable design services as a Supplemental Service under Section 4.1.1.
§ 3.2.5.2 The Architect shall consider the value of alternative materials, building systems and equipment, together with other considerations based on program and aesthetics, in developing a design for the Project that is consistent with the Owner’s program, schedule, and budget for the Cost of the Work.
§ 3.2.6 The Architect shall submit to the Owner an estimate of the Cost of the Work prepared in accordance with Section 6.3. The Architect shall submit to Owner an updated Project Schedule for the Project.
§ 3.2.7 The Architect shall submit the Schematic Design Documents to the Owner, and request the Owner’s approval.
§ 3.2.8 The Architect shall collaborate with the Owner to make adjustments to the scope of Work (Project requirements), Schematic Design cost opinion, and the Owner’s construction budget such that they are in agreement and approval prior to moving to the next phase.
Appears in 1 contract
Sources: Standard Form of Agreement Between Owner and Architect