Common use of Submittals Not Subject to Prior Review, Comment or Approval Clause in Contracts

Submittals Not Subject to Prior Review, Comment or Approval. Whenever the Contract Documents indicate that Developer is to deliver a Submittal to the Department but express no requirement for Department review, comment, disapproval, prior approval or other Department action, then Developer is under no obligation to obtain Department approval of the Submittal before proceeding with further Work, and the Department shall have the right, but is not obligated, to at any time review, comment on, take exception to, object to, reject or disapprove the Submittal on the basis that such Submittal is not in accordance with the requirements of the Contract Documents. No failure or delay by the Department in delivering comments, exceptions, objections, rejections or disapprovals with respect to the Submittal shall constitute a basis for any claim for Extra Work Costs, Delay Costs, time extensions or other relief.

Appears in 2 contracts

Sources: Concession Agreement, Concession Agreement