Systems Requirements. The Member must certify that the Generator meets the following requirements: The installation of the Generator and all equipment in the system comply with the latest published edition of IEEE 929. The Generator is a non-islanding type as defined in IEEE 929. Electrical Contractors and NEC Code Inspections: All installed wiring, protection devices, cabinets and connectors, etc. must comply with the latest published edition of the NEC as used by the local jurisdiction and all applicable local codes. An approved electrical inspection by the authority having jurisdiction is required. Isolation Device: An Isolation device as defined in Section 3.6 is required. The Cooperative in its sole discretion determines if the device is suitable.