Technical and Interconnection Requirements. Seller shall ensure his SRTPV system complies with the following technical and interconnection requirement and shall: 1.1 Comply with the applicable standards and conditions, in respect of integrating the SRTPV system with the distribution system. 1.2 Connect and operate the SRTPV system to BESCOM’s distribution system, in accordance with the State Grid Code, and distribution Code as amended from time to time. 1.3 Install, prior to connection of SRTPV system to BESCOM’s distribution system, an inverter with an automatic inbuilt isolation device. 1.4 Provide external manual isolation mechanism with suitable locking facility, so that SRTPV system will not back-feed into the BESCOM’s network in case of power outage of the BESCOM’s distribution system, and it shall be accessible for BESCOM to operate, if required, during maintenance / emergency conditions. 1.5 Install all the equipment of SRTPV system compliant with relevant International (IEEE/IEC) and Indian standards (BIS). (a) The SRTPV system shall be designed, engineered and constructed and operated by the Seller or any other person on his behalf, with reasonable diligence, subject to all applicable Indian Laws, Rules, Regulations as amended from time to time and orders having the force of law. The Seller, shall commission the SRTPV system, within six months from the date of approval of the PPA. 1.7 Adhere to the following power quality measures, as per the International and Indian standards and/or such other measures stipulated by KERC/BESCOM: Harmonic current: Harmonic current injections from a generation unit shall not exceed the limits specified in IEEE 519. Voltage at the injection point should be in the operating range of 80% to 110% of the nominal connected voltage.
Appears in 2 contracts
Technical and Interconnection Requirements. Seller shall ensure his SRTPV system complies with the following technical and interconnection requirement and shall:
1.1 Comply with the applicable standards and conditions, in respect of integrating the SRTPV system with the distribution system.
1.2 Connect and operate the SRTPV system to BESCOM’s distribution system, in accordance with the State Grid Code, and distribution Code as amended from time to time.
1.3 Install, prior to connection of SRTPV system to BESCOM’s distribution system, an inverter with an automatic inbuilt isolation device.
1.4 Provide external manual isolation mechanism with suitable locking facility, so that SRTPV system will not back-feed into the BESCOM’s network in case of power outage of the BESCOM’s distribution system, and it shall be accessible for BESCOM to operate, if required, during maintenance / emergency conditions.
1.5 Install all the equipment of SRTPV system system, compliant with relevant International (IEEE/IEC) and Indian standards (BIS).
(a) The SRTPV system shall be designed, engineered and constructed and operated by the Seller or any other person on his behalf, with reasonable diligence, subject to all applicable Indian Laws, Rules, Regulations as amended from time to time and orders having the force of law. The Seller, shall commission the SRTPV system, within six months from the date of approval of the PPA.
1.7 Adhere to the following power quality measures, as per the International and Indian standards and/or such other measures stipulated by KERC/BESCOM: Harmonic current: Harmonic current injections from a generation unit shall not exceed the limits specified in IEEE 519. Voltage at the injection point should be in the operating range of 80% to 110% of the nominal connected voltage.
Appears in 1 contract
Sources: Power Purchase Agreement
Technical and Interconnection Requirements. Seller shall ensure his SRTPV system complies with the following technical and interconnection requirement and shall:
1.1 Comply with the applicable standards and conditions, in respect of integrating the SRTPV system with the distribution system.
1.2 Connect and operate the SRTPV system to BESCOM’s BESCOM‟s distribution system, in accordance with the State Grid Codecode, and distribution Code as amended from time to time.
1.3 Install, prior to connection of SRTPV system to BESCOM’s BESCOM‟s distribution system, an inverter with an automatic inbuilt isolation devicedevise.
1.4 Provide external manual isolation mechanism with suitable locking facility, so that SRTPV system will not back-feed into the BESCOM’s BESCOM‟s network in case of power outage of the BESCOM’s BESCOM‟s distribution system, and it shall be accessible for BESCOM to operate, if required, during maintenance / emergency conditions.
1.5 Install all the equipment of SRTPV system compliant with relevant International (IEEE/IEC) and Indian standards (BIS).
(a) The SRTPV system shall be designed, engineered and constructed and operated by the Seller or any other person on his behalf, with reasonable diligence, subject to all applicable Indian Laws, Rules, Regulations as amended from time to time and orders having the force of law. .
(b) The Seller, shall commission the SRTPV system, within six months from the date of approval of the PPA.
1.7 Adhere to the following power quality measures, as per the International and Indian standards and/or such other measures stipulated by KERC/BESCOM: :
i) Harmonic current: Harmonic current injections from a generation unit shall not exceed the limits specified in IEEE 519. .
ii) Voltage at the injection point should be in the operating range of 80% to 110% of the nominal connected voltage.