Technical and Interconnection Requirements. Seller shall ensure his SRTPV system complies with the following technical and interconnection requirement and shall: 1.1 Comply with the standards and conditions in respect of integrating the SRTPV system with the grid/distribution system. 1.2 Connect the SRTPV system to ESCOM’s distribution system and shall be bound by requirements of State Grid and distribution Code as amended from time to time. 1.3 Install, prior to connection of SRTPV system to ESCOM’s distribution system, an inverter with an automatic inbuilt isolation devise. 1.4 Provide external manual isolation mechanism with suitable locking facility so that SRTPV system will not back-feed into the ESCOM’s network in case of power outage of the ESCOM’s distribution system, and it shall be accessible for …… ESCOM to operate, if required, during maintenance / emergency conditions. 1.5 Install all the equipment of SRTPV system compliant with relevant International (IEEE/IEC) and Indian standards (BIS). 1.6 SRTPV system shall be designed, engineered and constructed and operated by the seller or on his behalf with reasonable diligence subject to all applicable Indian laws, rules, Regulations as amended from time to time and orders having the force of law. 1.7 Adhere to the following power quality measures as per the International and Indian standards and/or such other measures stipulated by KERC/ESCOM: a. Harmonic current: Harmonic current injections from a generation unit shall not exceed the limits specified in IEEE 519. b. Voltage at the injection point should be in the operating range of 80% to 110% of the nominal connected voltage.
Appears in 1 contract
Sources: Power Purchase Agreement
Technical and Interconnection Requirements. Seller shall ensure his SRTPV system complies with the following technical and interconnection requirement and shall:
1.1 Comply with the applicable standards and conditions conditions, in respect of integrating the SRTPV system with the grid/distribution system.
1.2 Connect and operate the SRTPV system to ESCOM’s GESCOM‟s distribution system and shall be bound by requirements of system, in accordance with the State Grid code, and distribution Code as amended from time to time.
1.3 Install, prior to connection of SRTPV system to ESCOM’s GESCOM‟s distribution system, an inverter with an automatic inbuilt isolation devise.
1.4 Provide external manual isolation mechanism with suitable locking facility facility, so that SRTPV system will not back-feed into the ESCOM’s GESCOM‟s network in case of power outage of the ESCOM’s GESCOM‟s distribution system, and it shall be accessible for …… ESCOM GESCOM to operate, if required, during maintenance / emergency conditions.
1.5 Install all the equipment of SRTPV system compliant with relevant International (IEEE/IEC) and Indian standards (BIS).
1.6 (a) The SRTPV system shall be designed, engineered and constructed and operated by the seller Seller or any other person on his behalf behalf, with reasonable diligence diligence, subject to all applicable Indian lawsLaws, rulesRules, Regulations as amended from time to time and orders having the force of law.
(b) The Seller, shall commission the SRTPV system, within six months from the date of approval of the PPA.
1.7 Adhere to the following power quality measures measures, as per the International and Indian standards and/or such other measures stipulated by KERC/ESCOM:
a. GESCOM: Harmonic current: Harmonic current injections from a generation unit shall not exceed the limits specified in IEEE 519.
b. i) Voltage at the injection point should be in the operating range of 80% to 110% of the nominal connected voltage.
Appears in 1 contract
Sources: Power Purchase Agreement
Technical and Interconnection Requirements. Seller shall ensure his SRTPV system complies with the following following, technical and interconnection requirement requirements and shall:
1.1 Comply with the applicable standards and conditions conditions, in respect of integrating the SRTPV system with the grid/distribution system.
1.2 Connect and operate the SRTPV system to ESCOMCESC’s distribution system and shall be bound by requirements of system, in accordance with the State Grid Code, and distribution Distribution Code as amended from time to time.
1.3 Install, prior to connection of SRTPV system to ESCOM’s CESC's distribution system, an inverter with an automatic inbuilt isolation devisedevice.
1.4 Provide external manual isolation mechanism with suitable locking facility facility, so that SRTPV system will not back-feed into the ESCOM’s network CESC's network, in case of power outage of the ESCOM’s CESC's distribution system, and it shall be accessible for …… ESCOM CESC, Mysuru to operate, if required, during maintenance / emergency conditions.
1.5 Install all the equipment of the SRTPV system system, compliant with relevant International (IEEE/IEC) and Indian standards Standards (BIS).
1.6 (a) The SRTPV system shall be designed, engineered and constructed and operated by the seller or any other person on his behalf behalf, with reasonable diligence diligence, subject to all applicable Indian lawsLaws, rulesRules, Regulations as amended from time to time and orders having the force of law.
(b) The Seller shall commission the SRTPV system, within six months from the date of approval of the PPA.
1.7 Adhere to the following power quality measures measures, as per the International and Indian standards and/or such other measures measures, stipulated by the KERC/ESCOMCESC,Mysuru:
a. Harmonic current: Harmonic current injections from a generation unit shall not exceed the limits specified in IEEE 519.
b. Voltage at the injection point should be in the operating range of 80% to 110% %, of the nominal connected voltage.
Appears in 1 contract
Sources: Power Purchase Agreement
Technical and Interconnection Requirements. Seller shall ensure his SRTPV system complies with the following technical and interconnection requirement and shall:
1.1 Comply with the applicable standards and conditions conditions, in respect of integrating the SRTPV system with the grid/distribution system.
1.2 Connect and operate the SRTPV system to ESCOMGESCOM’s distribution system and shall be bound by requirements of system, in accordance with the State Grid Code, and distribution Code as amended from time to time.
1.3 Install, prior to connection of SRTPV system to ESCOMGESCOM’s distribution system, an inverter with an automatic inbuilt isolation devisedevice.
1.4 Provide external manual isolation mechanism with suitable locking facility facility, so that SRTPV system will not back-feed into the ESCOMGESCOM’s network in case of power outage of the ESCOMGESCOM’s distribution system, and it shall be accessible for …… ESCOM GESCOM to operate, if required, during maintenance / emergency conditions.
1.5 Install all the equipment of SRTPV system compliant with relevant International (IEEE/IEC) and Indian standards (BIS).
1.6 (a) The SRTPV system shall be designed, engineered and constructed and operated by the seller Seller or any other person on his behalf behalf, with reasonable diligence diligence, subject to all applicable Indian lawsLaws, rulesRules, Regulations as amended from time to time and orders having the force of law.
(b) The Seller, shall commission the SRTPV system, within six months from the date of approval of the PPA.
1.7 Adhere to the following power quality measures measures, as per the International and Indian standards and/or such other measures stipulated by KERC/ESCOMGESCOM:
a. i) Harmonic current: Harmonic current injections from a generation unit shall not exceed the limits specified in IEEE 519.
b. ii) Voltage at the injection point should be in the operating range of 80% to 110% of the nominal connected voltage.