Termination without fault of the Contractor. 5.7.1 The Agency shall have the right at any time to terminate this Contract either wholly or in part by giving written notice by registered mail. In the case of termination of a Contract by the Agency without fault of the Contractor, the Contractor shall, on receipt of the Agency’s instructions, forthwith take the necessary steps to implement them. The Parties shall use their best efforts to mitigate the consequences of the termination. The period to be allowed to implement them shall be agreed between the Parties but shall not exceed three (3) months. 5.7.2 Subject to the Contractor conforming with the instructions referred in Article 5.8.1, the Agency shall take over from the Contractor at a fair and reasonable price all finished parts not yet delivered to the Agency, all unused and undamaged material, bought-out components and items in the course of manufacture in the possession of the Contractor and properly obtained by or supplied to the Contractor for the performance of the Contract, except such materials, bought- out components and items in the course of manufacture as the Contractor shall, with the agreement of the Agency, elect to retain. a) The Agency shall indemnify the Contractor against such part of any loss of profit as is attributable to the termination of the Contract and against any damage resulting from the termination of the Contract, in particular against any commitments, liabilities or expenditure which are reasonably and properly chargeable by the Contractor and are related to the Contract, in so far as the said commitments, liabilities or expenditure would otherwise, subject to the conditions stated in Article 5.6.1, represent a loss by the Contractor by reason of the termination of the Contract. b) The amount of compensation payable under Article 5.8.3a) shall be fixed on the basis of evidence produced by the Contractor and accepted by the Agency. It shall take account of the proportion of the Contract completed and shall be consistent with the provisions of Article 5.8.4 5.7.4 The Agency shall in no circumstances be liable to pay any sum which, when added to the other sums paid, due or becoming due to the Contractor under the Contract, exceeds the total price for the Work set forth in the Contract.
Appears in 1 contract
Sources: Contract
Termination without fault of the Contractor. 5.7.1 The Agency shall have the right at any time to terminate this Contract either wholly or in part by giving written notice by registered mail. In the case of termination of a Contract by the Agency without fault of the Contractor, the Contractor shall, on receipt of the Agency’s instructions, forthwith take the necessary steps to implement them. The Parties shall use their best efforts to mitigate the consequences of the termination. The period to be allowed to implement them shall be agreed between the Parties but shall not exceed three (3) months.
5.7.2 Subject to the Contractor conforming with the instructions referred in Article 5.8.15.7.1, the Agency shall take over from the Contractor at a fair and reasonable price all finished parts not yet delivered to the Agency, all unused and undamaged material, bought-out components and items in the course of manufacture in the possession of the Contractor and properly obtained by or supplied to the Contractor for the performance of the Contract, except such materials, bought- bought-out components and items in the course of manufacture as the Contractor shall, with the agreement of the Agency, elect to retain.
a) The Agency shall indemnify the Contractor against such part of any loss of profit as is attributable to the termination of the Contract and against any damage resulting from the termination of the Contract, in particular against any commitments, liabilities or expenditure which are reasonably and properly chargeable by the Contractor and are related to the Contract, in so far as the said commitments, liabilities or expenditure would otherwise, subject to the conditions stated in Article 5.6.1, represent a loss by the Contractor by reason of the termination of the Contract.
b) The amount of compensation payable under Article 5.8.3a5.7.3a) shall be fixed on the basis of evidence produced by the Contractor and accepted by the Agency. It shall take account of the proportion of the Contract completed and shall be consistent with the provisions of Article 5.8.45.7.4
5.7.4 The Agency shall in no circumstances be liable to pay any sum which, when added to the other sums paid, due or becoming due to the Contractor under the Contract, exceeds the total price for the Work set forth in the Contract.