Testing (Preliminary Acceptance Test), Trial Run And Final Acceptance Test Clause Samples

The Testing (Preliminary Acceptance Test), Trial Run, and Final Acceptance Test clause defines the procedures and standards for evaluating whether delivered goods, equipment, or systems meet contractual requirements before final acceptance. Typically, this clause outlines a sequence where the supplier must first demonstrate functionality through preliminary tests, followed by a trial run under operational conditions, and finally a comprehensive acceptance test witnessed by the buyer. These steps ensure that any defects or non-conformities are identified and rectified before the buyer formally accepts the deliverables. The core function of this clause is to protect the buyer by ensuring that only fully compliant and operational products are accepted, thereby reducing the risk of post-delivery issues.
Testing (Preliminary Acceptance Test), Trial Run And Final Acceptance Test. 9.1 The End-user and the Seller will proceed with various tasks ranging from network planning, design, and equipment optimization, test to acceptance in accordance with the Schedule of Project Progress set out in Appendix 4. Within the term of this Contract, each of the End-user and the Seller should designate a representative in charge of dealing with technical issues in connection with this Contract, with their work plans to be determined through consultation among the representatives of all parties. In the event that any technical problem is identified or a dispute on technical problem arises, the representatives of the parties should analyze the reasons and clarify the responsibilities and coordinate to re-design. Day-to-day work and solutions shall be recorded in the work log during the commissioning and acceptance period. The daily record therein shall be confirmed by the respective representatives of the Parties by signature and each Party shall keep one copy. 9.2 The Seller shall be responsible for the network planning, design and optimization, the delivery, testing and Final Acceptance Test of Contracted Equipment, while the technical personnel of the End-user shall provide necessary assistance. 9.3 The acceptance testing shall recognize the requirement for conformity to the indexes and standards as set forth in Appendix 1 of this Contract, as well as the test procedures and standards of both Preliminary Acceptance Test and Final Acceptance Test set out in Appendix 6 of this Contract.

Related to Testing (Preliminary Acceptance Test), Trial Run And Final Acceptance Test

  • Acceptance Testing At the time of installation of a LIS trunk group, and at no additional charge, acceptance tests will be performed to ensure that the service is operational and meets the applicable technical parameters.

  • Acceptance Tests 11.1 If the Contract provides acceptance tests for Goods and/or the result of Services after their completion and/or delivery to the Purchaser, the acceptance shall only be considered as definitive when such tests have demonstrated the compliance of the Goods and/or the result of the Services to the requirements in the Contract. 11.2 Where the Contract provides for an acceptance procedure in the presence of both parties, at the successful completion of such procedure, the Purchaser shall issue the Supplier with an acceptance certificate which shall authorise the Supplier to invoice the Purchaser for any payment due on such acceptance. 11.3 The Purchaser shall at its discretion be entitled to issue and acceptancecertificate with reserves. The Supplier shall be obliged to remedy any non-conformities within the period set out in the acceptance certificate. Any payment which would otherwise have been due on acceptance may be withheld by the Purchaser in whole or part until the non- conformities underlying the reserves have been remedied.

  • Final Acceptance All Work has been completed and accepted by the County. The Contractor has provided all required close-out documentation and items as required by the Detailed Scope of Work for the specific Job Order, and these items and have accepted and approved by the County

  • Commercial Operation Date Testing and Modifications Prior to the Commercial Operation Date, the Connecting Transmission Owner shall test the Connecting Transmission Owner’s Attachment Facilities (including required control technologies and protection systems) and System Upgrade Facilities and System Deliverability Upgrades and Developer shall test the Large Generating Facility and the Developer’s Attachment Facilities to ensure their safe and reliable operation. Similar testing may be required after initial operation. Developer and Connecting Transmission Owner shall each make any modifications to its facilities that are found to be necessary as a result of such testing. Developer shall bear the cost of all such testing and modifications. Developer shall generate test energy at the Large Generating Facility only if it has arranged for the injection of such test energy in accordance with NYISO procedures.

  • Post-Commercial Operation Date Testing and Modifications Developer and Connecting Transmission Owner shall each at its own expense perform routine inspection and testing of its facilities and equipment in accordance with Good Utility Practice and Applicable Reliability Standards as may be necessary to ensure the continued interconnection of the Large Generating Facility with the New York State Transmission System in a safe and reliable manner. Developer and Connecting Transmission Owner shall each have the right, upon advance written notice, to require reasonable additional testing of the other Party’s facilities, at the requesting Party’s expense, as may be in accordance with Good Utility Practice.