The Participating TO and Interconnection Clause Samples

The "Participating TO and Interconnection" clause defines the roles and responsibilities of the participating transmission owner (TO) in relation to the interconnection of a new facility or project to the existing transmission system. It typically outlines the obligations of the TO regarding the construction, operation, and maintenance of interconnection facilities, as well as the coordination required with the interconnecting party. For example, it may specify which party is responsible for upgrades or modifications to the transmission system and how costs are allocated. The core function of this clause is to ensure clear delineation of duties and responsibilities, thereby preventing disputes and facilitating a smooth and reliable interconnection process.
The Participating TO and Interconnection. Customer shall cooperate with the other Parties in the inspection, maintenance, and testing of control or power circuits that operate below 600 volts, AC or DC, including, but not limited to, any hardware, control or protective devices, cables, conductors, electric raceways, secondary equipment panels, transducers, batteries, chargers, and voltage and current transformers that directly affect the operation of a Party's facilities and equipment which may reasonably be expected to impact the other Parties. Each Party shall provide advance notice to the other Parties before undertaking any work on such circuits, especially on electrical circuits involving circuit breaker trip and close contacts, current transformers, or potential transformers.
The Participating TO and Interconnection. Customer shall cooperate with the other Parties in the inspection, maintenance, and testing of control or power circuits that operate below 600 volts, AC or DC, including, but not limited to, any hardware, control or protective devices, cables, conductors, electric raceways, secondary equipment panels, transducers, batteries, chargers, and voltage and current transformers that directly affect the
The Participating TO and Interconnection. Customer shall each be responsible for protection of its facilities consistent with Good Utility Practice.

Related to The Participating TO and Interconnection

  • Participating TO’s Interconnection Facilities The Participating TO shall design, procure, construct, install, own and/or control the Participating TO’s Interconnection Facilities described in Appendix A at the sole expense of the Interconnection Customer. Unless the Participating TO elects to fund the capital for the Participating TO’s Interconnection Facilities, they shall be solely funded by the Interconnection Customer.

  • Connecting Transmission Owner’s Scope of Work and Responsibilities The Connecting Transmission Owner will design, construct, own, operate and maintain all Connecting Transmission Owner’s Interconnection Facilities, except as otherwise stated above and in the Project Specific Specifications. The Connecting Transmission Owner will complete all engineering reviews, field verifications and witness testing, etc. in accordance with the ESBs and the Project Specific Specifications. Connecting Transmission Owner shall provide the revenue metering CT/PT units and meter socket enclosure. The Connecting Transmission Owner shall: • provide, run, and wire both ends of the color-coded cable for the revenue metering instrument transformer secondary wiring; • perform all terminations; and • supply and install the meter. The revenue meter may require a communications link to the RTU. The Connecting Transmission Owner will specify and run those communications cables. The Connecting Transmission Owner shall complete all wiring, testing and commissioning of the RTU.

  • Connecting Transmission Owner’s Attachment Facilities Connecting Transmission Owner shall design, procure, construct, install, own and/or control the Connecting Transmission Owner’s Attachment Facilities described in Appendix A hereto, at the sole expense of the Developer.

  • Obligations relating to Project Agreements 5.2.1 It is expressly agreed that the Concessionaire shall, at all times, be responsible and liable for all its obligations under this Agreement notwithstanding anything contained in the Project Agreements or any other agreement, and no default under any Project Agreement or agreement shall excuse the Concessionaire from its obligations or liability hereunder. 5.2.2 The Concessionaire shall submit to the Authority the drafts of all Project Agreements, or any amendments or replacements thereto, for its review and comments, and the Authority shall have the right but not the obligation to undertake such review and provide its comments, if any, to the Concessionaire within 15 (fifteen) days of the receipt of such drafts. Within 7 (seven) days of execution of any Project Agreement or amendment thereto, the Concessionaire shall submit to the Authority a true copy thereof, duly attested by a Director of the Concessionaire, for its record. For the avoidance of doubt, it is agreed that the review and comments hereunder shall be limited to ensuring compliance with the terms of this Agreement. It is further agreed that no review and/or observation of the Authority and/or its failure to review and/or convey its observations on any Document shall relieve the Concessionaire of its obligations and liabilities under this Agreement in any manner nor shall the Authority be liable for the same in any manner whatsoever. 5.2.3 The Concessionaire shall not make any addition, replacement or amendments to any of the Financing Agreements without the prior written consent of the Authority if such addition, replacement or amendment has, or may have, the effect of imposing or increasing any financial liability or obligation on the Authority, and in the event that any replacement or amendment is made without such consent, the Concessionaire shall not enforce such replacement or amendment nor permit enforcement thereof against the Authority. For the avoidance of doubt, the Authority acknowledges and agrees that it shall not unreasonably withhold its consent for restructuring or rescheduling of the Debt Due.

  • Returning to Work (a) Returning to work early (i) During the period of parental leave an Employee may return to work at any time as agreed between the Employer and the Employee, provided that time does not exceed four weeks from the recommencement date desired by the Employee. (ii) In the case of adoption, where the placement of an eligible child with an Employee does not proceed or continue, the Employee will notify the Employer immediately and the Employer will nominate a time not exceeding four weeks from receipt of notification for the Employee’s return to work. (b) Returning to work at conclusion of leave (i) At least four weeks prior to the expiration of parental leave, the Employee will notify the Employer of their return to work after a period of parental leave. (ii) Subject to 51.23(b)(iii), an Employee will be entitled to the position which they held immediately before proceeding on parental leave. In the case of an Employee transferred to a safe job pursuant to clause 51.12 above, the Employee will be entitled to return to the position they held immediately before such transfer. (iii) Where such position no longer exists but there are other positions available which the Employee is qualified for and is capable of performing, the Employee will be entitled to a position as nearly comparable in status and pay to that of their former position. (c) Returning to work at a reduced time fraction (i) To assist an Employee in reconciling work and parental responsibilities, an Employee may request to return to work at a reduced time-fraction until their Child reaches school age, after which the Employee will resume their substantive time-fraction. (ii) Where an Employee wishes to make a request under 51.23(c)(i) such a request must be made as soon as possible but no less than seven weeks prior to the date upon which the Employee is due to return to work from parental leave.