Three Month Rolling Programme. (1) The Three Month Rolling Programme shall be an expansion of the approved Works Programme, covering sequential periods of three months. The Three Month Rolling Programme shall provide more detail of the Contractor’s plan, organisation and execution of the work within these periods. In particular, the Contractor shall expand each activity planned to occur during the next three(3) month period, if necessary to a daily level of detail. (2) The Three Month Rolling Programme shall be developed as a Critical Path Method (CPM) network, and shall be presented in bar chart and time-scaled network diagram format. Bar charts shall be presented on an A4 and time-scaled networks diagrams on an A1 size reproducible media. Tasks in the programme shall be derivatives of and directly related to tasks in the approved Works Programme.
Appears in 73 contracts
Sources: Construction Contract, Construction Contract, Contract Agreement
Three Month Rolling Programme. (1) The Three Month Rolling Programme shall be an expansion of the approved Works Programme, covering sequential periods of three months. The Three Month Rolling Programme shall provide more detail of the Contractor’s plan, organisation organization and execution of the work within these periods. In particular, the Contractor shall expand each activity planned to occur during the next three(3) month period, if necessary to a daily level of detail.
(2) The Three Month Rolling Programme shall be developed as a Critical Path Method (CPM) network, and shall be presented in bar chart and time-scaled network diagram format. Bar charts shall be presented on an A4 and time-scaled networks diagrams on an A1 size reproducible media. Tasks in the programme shall be derivatives of and directly related to tasks in the approved Works Programme.
Appears in 2 contracts
Sources: Contract Agreement, Contract Agreement
Three Month Rolling Programme. (1) The Three Month Three-month Rolling Programme shall be an expansion of the approved Works Programme, covering sequential periods of three months. The Three Three- Month Rolling Programme shall provide more detail of the Contractor’s plan, organisation and execution of the work within these periods. In particular, the Contractor shall expand each activity planned to occur during the next three(3three (3) month period, if necessary to a daily level of detail.
(2) The Three Three-Month Rolling Programme shall be developed as a Critical Path Method (CPM) network, and shall be presented in bar chart and time-scaled network diagram format. Bar charts shall be presented on an A4 and time-scaled networks diagrams on an A1 size reproducible media. Tasks in the programme shall be derivatives of and directly related to tasks in the approved Works Programme.
Appears in 2 contracts
Sources: Construction Contract, Construction Contract
Three Month Rolling Programme. (1) The Three Month Rolling Programme shall be an expansion of the approved Works Programme, covering sequential periods of three months. The Three Month Rolling Programme shall provide more detail of the Contractor’s plan, organisation and execution of the work within these periods. In particular, the Contractor shall expand each activity planned to occur during the next three(3) month period, if necessary to a daily level of detail.
(2) The Three Month Rolling Programme shall be developed as a Critical Path Method (CPM) network, and shall be presented in bar chart and time-scaled network diagram format. Bar charts shall be presented on an A4 and time-time- scaled networks diagrams on an A1 size reproducible media. Tasks in the programme shall programmeshall be derivatives of and directly related to tasks in the approved Works Programme.
Appears in 1 contract
Sources: Construction Contract
Three Month Rolling Programme. (1) The Three Month Rolling Programme shall be an expansion of the approved Works Programme, covering sequential periods of three months. The Three Month Rolling Programme shall provide more detail of the Contractor’s plan, organisation or- ganisation and execution of the work within these periods. In particular, the Contractor Con- tractor shall expand each activity planned to occur during the next three(3) month period, if necessary to a daily level of detail.
(2) The Three Month Rolling Programme shall be developed as a Critical Path Method (CPM) network, and shall be presented in bar chart and time-scaled network diagram dia- gram format. Bar charts shall be presented on an A4 and time-scaled networks diagrams on an A1 size reproducible media. Tasks in the programme shall be derivatives de- rivatives of and directly related to tasks in the approved Works Programme.
Appears in 1 contract
Sources: Construction Contract
Three Month Rolling Programme. (1) The Three Month Rolling Programme shall be an expansion of the approved Works Programme, covering sequential periods of three months. The Three Month Rolling Programme shall provide more detail of the Contractor’s plan, organisation and execution of the work within these periods. In particular, the Contractor shall expand each activity planned to occur during the next three(3three (3) month period, if necessary to a daily level of detail.
(2) The Three Month Rolling Programme shall be developed as a Critical Path Method (CPM) network, and shall be presented in bar chart and time-scaled network diagram format. Bar charts shall be presented on an A4 and time-scaled networks diagrams on an A1 size reproducible media. Tasks in the programme shall be derivatives of and directly related to tasks in the approved Works Programme.
Appears in 1 contract
Sources: Construction Contract