Time Impact Analysis. B.4.4.1 When changes or delays are experienced because of a Change Order, Design Builder shall submit a written time impact analysis (“Time Impact Analysis”) to the City illustrating the influence of each change or delay in the Project Schedule. B.4.4.2 Each Time Impact Analysis shall include a fragment network analysis (fragnet), demonstrating the following: how Design Builder proposes to perform the changed Work including: