Unit Price Items Sample Clauses

Unit Price Items. For all Work to be paid on a unit price basis, the value of such Work shall be determined by Owner on the basis of the actual number of acceptable units of Unit Price Items installed and complete in place, multiplied by the applicable Unit Price set forth in the Schedule of Prices. The actual number of acceptable units installed and complete in place shall be measured on the basis described in Attachment B to the Contract or, in the absence of such description, on the basis determined by Owner. The number of units of Unit Price Items stated in the Schedule of Prices are Owner’s estimate only and shall not be used in establishing the Progress or Final Payments due Contractor. The Contract Price shall be adjusted to reflect the actual number of acceptable units of Unit Price Items installed and complete in place upon Final Acceptance.
Unit Price Items. A. Payment for all Work shall be in accordance with the unit price bid items in the Schedule of Prices and shall be full compensation for all labor, materials and equipment required to furnish, install, construct and test the Work covered under the unit price Bid item. B. Payment will be made only for the actual quantities of work performed in compliance with the Drawings and Specifications and as approved by the Commissioner. The Contractor will be paid an amount equal to the approved quantity times applicable unit price. Any unused balance of the unit price work shall revert to the Commissioner upon completion of the project. C. All unit price work shall be considered as part of the Work to be performed within the time limits specified elsewhere for Substantial Completion and Project Completion. No increase in contract time will be allowed for increases in quantities of unit price Work performed beyond the quantities shown in the Notice to Proceed, unless it can be demonstrated that the additional Work performed under the unit price item is on the critical path of the Project Schedule.
Unit Price Items 

Related to Unit Price Items

  • Unit Price Work Work to be paid for on the basis of unit prices as defined and described in the Contract Documents. A percentage markup for overhead or profit shall be included in all unit prices.

  • Unit Price Unless the bidder clearly indicates that the price is based on consideration of being awarded the entire lot and that an adjustment to the price was made based on receiving the entire bid, any difference between the unit price correctly extended and the total price shown for all items shall be offered shall be resolved in favor of the unit price.

  • Unit Prices If unit prices are stated in the Contract Documents or subsequently agreed upon, and if the quantities originally contemplated are so changed in a Change Order that application of the agreed unit prices to the quantities of work proposed will cause substantial inequity to the Owner or the Contractor, the applicable unit prices shall be equitably adjusted as provided in the Special Conditions or as agreed to by the parties and incorporated into the Change Order.

  • Contract Price The Contractor shall supply the Contractor Deliverables to the Authority at the Contract Price. The Contract Price shall be a Firm Price unless otherwise stated in Schedule 3 (Contract Data Sheet). Subject to clause G2 the Contract Price shall be inclusive of any UK custom and excise or other duty payable. The Contractor shall not make any claim for drawback of UK import duty on any part of the Contract Deliverables supplied which may be for shipment Overseas. D Intellectual Property

  • C1 Contract Price In consideration of the Contractor’s performance of its obligations under the Contract, the Authority shall pay the Contract Price in accordance with clause C2 (Payment and VAT).