Unit Price Method Sample Clauses

The Unit Price Method clause establishes that payments for goods, services, or work will be calculated based on a set price per unit of measurement. In practice, this means that the total contract amount is determined by multiplying the agreed unit price by the actual quantity delivered or performed, such as paying per cubic meter of concrete poured or per hour of labor provided. This approach ensures flexibility and fairness when the exact quantities required are uncertain at the outset, as it allows for adjustments in payment based on actual usage or delivery.
Unit Price Method. Where payment is based on the unit price method, the CONTRACTOR agrees that he will make no claim for damages, anticipated profits or otherwise on account of any differences which may be found between the quantities of work actually done, the material actually furnished under this contract and the estimated quantities contemplated and contained in the bid; provided, however, that in case the actual quantity of any major item should become as much as twenty percent (20%) above or below the estimated or contemplated quantity for such items, then either party to this Agreement, upon demand, shall be entitled to a revised consideration for said work that differs from the estimated quantity.
Unit Price Method. Where the Additional Work involved is covered or is of the same character as the original Contract, Unit Price Work by application of those unit prices to the quantities of the items involved;
Unit Price Method. 1. Whenever the AGENCY or its representative authorizes CONTRACTOR to perform on a Unit Price basis, the AGENCY’s authorization shall clearly state the: a. Scope of Work to be performed; b. Applicable Unit Price; and, c. Not to exceed amount of reimbursement as established by the AGENCY. 2. The applicable unit price shall include reimbursement for all direct and indirect costs of the Work, including overhead and profit. 3. CONTRACTOR shall only be paid under this method for the actual quantity of materials incorporated in or removed from the Work and such quantities must be supported by field measurement statements verified by the AGENCY.
Unit Price Method. 1. Whenever the County authorizes Contractor to perform Work on a Unit Price basis, the County’s authorization shall clearly state the: a. Scope of work to be performed; b. Applicable Unit Price; and c. Not to exceed amount of reimbursement as established by the County. 2. The applicable unit price shall include reimbursement for all direct and indirect costs of the Work, including Overhead and profit. 3. If the unit price will be applied to materials incorporated in or removed from the Work, the Contractor shall be paid under this method only for the actual quantities and such quantities must be supported by field measurement statements verified by the County.
Unit Price Method. If the actual amount of work to be done and the materials to be furnished differ from estimates and where the basis for payment is the unit price method, then payment shall be for the actual amount of accepted work done and materials furnished on the Project.
Unit Price Method. 1. The City may direct the Contractor to perform extra work on a Unit Price basis. Such authorization shall clearly state the: a. Scope of work to be performed; b. Applicable Unit Price; and c. Not to exceed amount of reimbursement as established by City. 2. The applicable unit price shall include reimbursement for all direct and indirect costs of the work, including Overhead and profit, as limited by paragraph 6.3,

Related to Unit Price Method

  • Unit Price Unless the bidder clearly indicates that the price is based on consideration of being awarded the entire lot and that an adjustment to the price was made based on receiving the entire bid, any difference between the unit price correctly extended and the total price shown for all items shall be offered shall be resolved in favor of the unit price.

  • Unit Price Work Work to be paid for on the basis of unit prices as defined and described in the Contract Documents. A percentage markup for overhead or profit shall be included in all unit prices.

  • Unit Prices If unit prices are stated in the Contract Documents or subsequently agreed upon, and if the quantities originally contemplated are so changed in a Change Order that application of the agreed unit prices to the quantities of work proposed will cause substantial inequity to the Owner or the Contractor, the applicable unit prices shall be equitably adjusted as provided in the Special Conditions or as agreed to by the parties and incorporated into the Change Order.

  • Measurement method An isolation resistance test instrument is connected between the live parts and the electrical chassis. The isolation resistance is subsequently measured by applying a DC voltage at least half of the working voltage of the high voltage bus. If the system has several voltage ranges (e.g. because of boost converter) in conductively connected circuit and some of the components cannot withstand the working voltage of the entire circuit, the isolation resistance between those components and the electrical chassis can be measured separately by applying at least half of their own working voltage with those components disconnected.

  • Billing Method 2.6.1 To receive payment for services rendered pursuant to this contract the Contractor shall submit a fully completed invoice for work previously performed to: 2.6.2 At a minimum, the invoice shall detail the following information: 2.6.2.1 Unique invoice number; 2.6.2.2 Contractor’s name, address, and telephone number; 2.6.2.3 Date of invoice and/or billing period; 2.6.2.4 Applicable Contract No.;