Update SWMM Model Clause Samples

Update SWMM Model. This task includes updating the SWMM model to add completed projects since 2012, include sea level rise projections, update land use changes and any other changes requested by the CITY. The soil coverage values directly connected impervious areas (DCIA), storage values and other parameters will be updated based on the completed projects and known land use changes. The sea level rise projections will be based on the Southeast Florida Regional Climate Change Action Plan. The Regional Climate Action Plan was the result of collaboration of existing staff and resources from the various cooperating agencies including Palm Beach, Broward, Miami-Dade, Monroe Counties, their municipalities and other partners. The plan presented the Unified Southeast Florida Sea Level Rise Projection. This projection uses historic tidal information from Key West and was calculated by ▇▇▇▇▇▇▇▇▇▇ ▇▇▇▇▇▇▇▇ from the United States Army Corps of Engineers using USACE Guidance (USACE 2009) intermediate and high curves to represent the lower and upper bound for projected sea level rise in Southeast Florida. Consultant will execute the same five SFWMD design storms (2-year, and 5-year, 24-hour; and the 10-, 25-, and 100-year, 72-hour) using updated parameters and compare to the existing base model results. This model will then be used to compare against any proposed improvements.
Update SWMM Model. The SWMM model developed as part of the existing conditions modeling will be updated. The network will be developed to the manhole level. Inflow hydrographs will be imported, and the impacted outflows will be developed for the 2-, 10-, and 100-year storm events. • Increased Storm Sewer Conveyance – Impacted conditions modeling will be done to reflect the proposed changes to land use from the additional lanes. The impacted conditions models will determine the impacts due to the changes in land use. The resulting hydrographs will be extracted. • Quantify Flows and WSEs - A results comparison table showing the 2-year HGLs, 10- and 100-year WSEs, as well critical elevations (gutter and Maximum Ponding Elevation) will be developed as part of this task. Associated peak flows will also be summarized as part of this task.

Related to Update SWMM Model

  • Price Adjustments for OGS Centralized Contracts Periodic price adjustments will occur no more than twice per year on a schedule to be established solely by OGS. Pricing offered shall be fixed for the first twelve (12) months of the Contract term. Such price increases will only apply to the OGS Centralized Contracts and shall not be applied retroactively to Authorized User Agreements or any Mini-bids already submitted to an Authorized User. Price decreases may be made at any time. Additionally, some price decreases shall be calculated in accordance with Appendix B, section 17, Pricing.

  • Equipment Specifications All equipment must meet the contract specifications and all federal and State safety codes and regulations in effect at the date of manufacture. All equipment must be Original Equipment Manufacturer (OEM) equipment unless otherwise stated in the contract. All products, materials, supplies, replacement parts, and equipment offered and furnished must be new, of current manufacturer production, and must have been formally announced by the manufacturer as being commercially available, unless otherwise stated in this Contract.

  • Construction Schedule The progress schedule of construction of the Project as provided by Developer and approved by District.

  • Development Schedule The Project shall substantially comply with the specific timetables and triggers for action set forth in Article 5 of this Agreement. The parties acknowledge that, as provided in G.S. 160A-400.25(b), the failure to meet a commencement or completion date shall not, in and of itself, constitute a material breach of this Agreement pursuant to G.S. 160A-400.27 but must be judged based upon the totality of the circumstances.

  • Recovery Schedule If the initial schedule or any current updates fail to reflect the Work’s actual plan or method of operation, or a contractual milestone date is more than fifteen (15) days behind, Owner may require that a recovery schedule for completion of the remaining Work be submitted. The Recovery Schedule must be submitted within seven (7) calendar days of Owner’s request. The Recovery Schedule shall describe in detail Construction Contractor’s plan to complete the remaining Work by the required Contract milestone date. The Recovery Schedule submitted shall meet the same requirements as the original Construction Schedule. The narrative submitted with the Recovery Schedule should describe in detail all changes that have been made to meet the Contract milestone dates.