Work Program. 14.1. The Work program regarding the SPP shall be submitted to the Contracting Authority in accordance with the Specifications. 14.2. The work program shall be prepared in such a way and with such level of detail that it includes the work items, parts of the work, distribution of the work by months, timelines, construction timeframes and work completion dates, and the SPP capacity to be commissioned each month. 14.3. The Contracting Authority shall review the Work program submitted to it and notify the Auction Winner of its comments and requests for correction, if any. In order for the Auction Winner to complete its obligations in accordance with the provisions of the REZ Project Documents, the required revisions shall be made in the Work program within the specified period of time.