Scheduled Commissioning Date definition

Scheduled Commissioning Date or “SCD” of the Project shall mean [Insert Date];
Scheduled Commissioning Date means 12 (twelve) months from the Effective Date.
Scheduled Commissioning Date means 18 (Eighteen) months from the Effective Date.

Examples of Scheduled Commissioning Date in a sentence

  • However, the Scheduled Commissioning Date shall not get altered due to Part Commissioning of the Project.

  • Further, any delay in adoption of tariff by the Appropriate Commission, beyond 120 days of Effective Date after this Agreement, shall entail a corresponding extension in Scheduled Commissioning Date.

  • SECI shall also designate a bank account at New Delhi("SECI Designated Account") for payments to be made by the WPD to SECI, if any, and notify the WPD of the details of such account ninety (90) Days before the Scheduled Commissioning Date.

  • However, if the requisite SERC and/or CERC (as applicable) order is issued after the timeline as per Article 2.1.3, this shall entail a corresponding extension in Scheduled Financial Closure and the Scheduled Commissioning Date for equal number of days for which the SERC and / or CERC order has been delayed beyond such period as specified in Article 2.1.

  • Such extension of time by APDCL shall not affect the Commissioning of the Project within the Scheduled Commissioning Date.


More Definitions of Scheduled Commissioning Date

Scheduled Commissioning Date or “SCD” shall mean 9 months from the effective date as defined in Article 1 of PPA;
Scheduled Commissioning Date or “SCD” of the Project Shall mean date that is nine (9) Months from the Date of execution of this PPA between _PGVCL
Scheduled Commissioning Date or “SCD” shall mean date as on thirteen (13)/fifteen (15) months (as applicable) from the effective date of the SECI-SPD PPA;
Scheduled Commissioning Date or “SCD” : shall mean [Insert a date as on 18 months from the Effective Date];
Scheduled Commissioning Date means the actual commissioning date of respective unit(s) of the power Project where upon the Biogas Project Developer starts injecting power from the power Project to PSPCL grid / production of Bio CNG.
Scheduled Commissioning Date has the meaning as specified in Section A of Part I (Individual Terms);
Scheduled Commissioning Date means [Insert a date 4 months from the date of signing of this Agreement];