Common use of ACCEPTANCE OF DEFECTIVE OR NON-CONFORMING WORK Clause in Contracts

ACCEPTANCE OF DEFECTIVE OR NON-CONFORMING WORK. ‌ If Owner prefers to accept defective or nonconforming Work, it may do so instead of requiring its removal and correction, in which case a Change Order will be issued to reflect a reduction in the Contract Price, or, if the amount is determined after Final Payment, it shall be paid by Contractor.

Appears in 3 contracts

Sources: Construction Agreement, Design Build Agreement, Progressive Design Build Agreement

ACCEPTANCE OF DEFECTIVE OR NON-CONFORMING WORK. 16.3.1 If the Owner prefers to accept defective or nonconforming non-conforming Work, it he may do so instead of requiring its removal and correction, in which case a Change Order will be issued to reflect a an appropriate reduction in the Contract PriceAmount, or, if the amount is determined after Final Paymentfinal payment, it shall be paid by the Contractor.

Appears in 3 contracts

Sources: Construction Manager at Risk Services Agreement, Construction Manager at Risk (Cmar) Services Agreement, Guaranteed Maximum Price Agreement

ACCEPTANCE OF DEFECTIVE OR NON-CONFORMING WORK. If the Owner prefers to accept defective or nonconforming non-conforming Work, it Owner may do so instead of requiring its removal and correction, in which case a Change Order will be issued to reflect a reduction in the Contract Price, or, if the amount is determined after Final Payment, it Sum where appropriate and equitable. Such adjustment shall be paid by Contractoreffected whether or not final payment has been made.

Appears in 2 contracts

Sources: General Conditions, General Conditions

ACCEPTANCE OF DEFECTIVE OR NON-CONFORMING WORK. If the Owner prefers to accept defective or nonconforming non-conforming Work, it he may do so instead of requiring its removal and correction, in which case a Change Order will be issued to reflect a an appropriate reduction in the Contract PriceAmount, or, if the amount is determined after Final Paymentfinal payment, it shall be paid by the Contractor.

Appears in 2 contracts

Sources: Contract and General Conditions, Contract and General Conditions

ACCEPTANCE OF DEFECTIVE OR NON-CONFORMING WORK. 13.3.1 If the Owner prefers to accept defective or nonconforming Work, it he may do so instead of requiring its removal and correction, in which case a Change Order will be issued to reflect a reduction in the Contract Price, or, if the Sum in an amount is determined after Final Payment, it appropriate and equitable. Such adjustment shall be paid by Contractoreffective whether or not final payment has been made.

Appears in 1 contract

Sources: Owner Contractor Agreement (Wells Real Estate Investment Trust Inc)

ACCEPTANCE OF DEFECTIVE OR NON-CONFORMING WORK. If the Owner prefers to accept defective or nonconforming Work, it he may do so instead of requiring its removal and correction, in which case a Change Order will be issued to reflect a reduction in the Contract Price, or, if the Sum in an amount is determined after Final Payment, it appropriate and equitable. Such adjustment shall be paid by Contractoreffective whether or not final payment has been made.

Appears in 1 contract

Sources: Owner Contractor Agreement (Wells Real Estate Fund Ix Lp)