Change Orders and Contract Amendments. 14.1.1. APDCL may at any time direct the AMISP through a written notice to change the number of meters proposed to be installed (“Change Order”). No Change Order that has the effect of varying the number of meters to be installed beyond +/- 20% of the original number of meters shall be issued by the Utility without prior consent of AMISP. Provided however that upon expiry of time period specified in 3.3.2(o) of this AMISP Contract if the Utility has not been able to provide clearance/ approval/ permits for installation of the meters, the Utility shall issue a Change Order no later than 7 days of expiry of such time period confirming the actual number of meters for which clearance/ approval/ permits is available. 14.1.2. In the event a Change Order causes an increase or decrease in the time required for, the AMISP’s performance of any provisions under the Contract, an equitable adjustment shall be made in the Project Implementation Schedule as provided in Schedule A of this AMISP Contract and the Contract shall accordingly be amended. Any claims by the AMISP or the Utility for adjustment under this Article must be asserted within 28 (twenty-eight) days from the date of the AMISP’s receipt of the Change Order. The Parties agree that any change in the delivery and Project Implementation Schedule shall result in an proportional change in the Term of the Contract. 14.1.3. In the event a Change Order, issued up to 24 months after the date of execution of this AMISP Contract, modifies the total number of Smart Meters to be installed then such revised quantity shall be deemed to be the basis for determination of Work Completion. 14.1.4. The Total meter-months of operating the AMI System after Operational Go-Live shall be computed taking into account all Change Orders issued by the Utility. 14.1.5. No Change Order for reduction of quantity shall be issued after Work Completion. In the event of loss of a consumer after Work Completion the Utility may request the AMISP to relocate a Smart Meter at a different location, however AMISP shall continue to receive the AMISP Service Charge qua all the Smart Meters installed.
Appears in 2 contracts
Sources: Contract for Appointment of Advanced Metering Infrastructure (Ami) Service Provider, Contract for Appointment of Advanced Metering Infrastructure (Ami) Service Provider
Change Orders and Contract Amendments. 14.1.1. APDCL [Utility] may at any time direct the AMISP through a written notice to change the number of meters proposed to be installed (“Change Order”). No Change Order that has the effect of varying the number of meters to be installed beyond +/- 20% of the original number of meters shall be issued by the Utility without prior consent of AMISP. Provided however that upon expiry of time period specified in 3.3.2(o) of this AMISP Contract if the Utility has not been able to provide clearance/ approval/ permits for installation of the meters, the Utility shall issue a Change Order no later than 7 days of expiry of such time period confirming the actual number of meters for which clearance/ approval/ permits is available.
14.1.2. In the event a Change Order causes an increase or decrease in the time required for, the AMISP’s performance of any provisions under the Contract, an equitable adjustment shall be made in the Project Implementation Schedule as provided in Schedule A of this AMISP Contract and the Contract shall accordingly be amended. Any claims by the AMISP or the Utility for adjustment under this Article must be asserted within 28 (twenty-eight) days from the date of the AMISP’s receipt of the Change Order. The Parties agree that any change in the delivery and Project Implementation Schedule shall result in an proportional change in the Term of the Contract.
14.1.3. In the event a Change Order, issued up to 24 months after the date of execution of this AMISP Contract, modifies the total number of Smart Meters to be installed then such revised quantity shall be deemed to be the basis for determination of Work Completion.
14.1.4. The Total meter-months of operating the AMI System after Operational Go-Live shall be computed taking into account all Change Orders issued by the Utility.
14.1.5. No Change Order for reduction of quantity shall be issued after Work Completion. In the event of loss of a consumer after Work Completion the Utility may request the AMISP to relocate a Smart Meter at a different location, however AMISP shall continue to receive the AMISP Service Charge qua all the Smart Meters installed.