Changes Requested by Owner Sample Clauses
The "Changes Requested by Owner" clause defines the process by which an owner can request modifications to the scope, design, or execution of a project after the contract has been signed. Typically, this clause outlines the steps for submitting change requests, how those requests are evaluated, and the method for adjusting the contract price or timeline to reflect the changes. Its core practical function is to provide a structured and fair mechanism for accommodating the owner's evolving needs while ensuring that both parties understand the implications of such changes, thereby minimizing disputes and maintaining project clarity.
POPULAR SAMPLE Copied 1 times
Changes Requested by Owner. Owner may unilaterally, at any time, on written order, without notice to the surety, and without invalidating the Contract, make changes in the work herein contracted for. Owner shall notify the Contractor that it is considering such a change and Contractor shall provide Owner with a proposed price and scheduling proposal for all costs and impacts arising from the changed work in writing within seven (7) calendar days of Owner's written notice. Thereafter, if the parties are in agreement, Owner and Contractor shall execute a written change order which modifies this Agreement. In the absence of such an agreement, the parties shall proceed pursuant to Article 4.
Changes Requested by Owner. CCPRC may unilaterally, at any time, on written order, without notice to the surety, and without invalidating the Contract, make changes in the work herein contracted for. CCPRC shall notify the Contractor that it is considering such a change and Contractor shall provide with a proposed price and scheduling proposal for all costs and impacts arising from the changed work in writing within seven (7) calendar days of CCPRC's written notice. Thereafter, if the parties are in agreement, CCPRC and Contractor shall execute a written change order which modifies this Agreement. In the absence of such an agreement, the parties shall proceed pursuant to Article 3.
Changes Requested by Owner. (a) Subject to paragraphs (b), (c), and (d) below, Owner shall be entitled to direct, during the performance of this Contract, any change within the general scope of this Contract, including any change that will add, delete, or change the Work, affect the design or construction of any Site or the time for performance of the Work set forth in the Initial City Schedules and/or Acceptance Date; provided, however, (i) this Article 11 (Changes in Scope of Work) shall not be used by Owner to terminate this Contract in part for convenience; (ii) Owner shall be entitled only to direct additions or changes to the Work for which Contractor has, or will have within a reasonable period of time using commercially reasonable efforts, the resources to perform such addition or change; (iii) the additions or changes to the Work involve services Contractor provides as part of its ordinary business; and (iv) the additions or changes to the Work will not materially adversely affect Contractor's performance under the Initial City Schedules.
(b) Any change directed by Owner as described in paragraph (a) above shall be submitted in writing to Contractor. Contractor shall respond to such directed change in writing to Owner within fourteen (14) Calendar Days after receipt of such directed change and shall include in such response the details of the impact of such change in the Work on the Contract Sum and/or Initial City Schedules and/or Acceptance Date. In the event Contractor, using commercially reasonable efforts, cannot prepare such details within such period, Contractor shall so advise Owner and shall submit, for Owner's approval, a request for an extension of such period that in no event shall exceed sixteen (16) Calendar Days, such request to set forth the reasons that the details of the impact of such change could not be documented within such fourteen (14) Calendar Days using commercially reasonable efforts. Upon Owner's approval, Contractor shall be granted such extension.
(c) If Owner and Contractor agree upon the change in the Contract Sum and/or the Initial City Schedule and/or Acceptance Date caused by the change in the Work, Contractor shall proceed with the performance of this Contract as changed immediately upon the execution by both Parties of a Change Order reflecting such agreement.
(d) If the Parties cannot agree on a change to the Contract Sum and/or Initial City Schedule and/or Acceptance Date, as occasioned by the additions or changes in the Work directed b...
Changes Requested by Owner. Owner may unilaterally, at any time, on written order, without notice to the surety, and without invalidating the Contract, make changes in the work herein contracted for. Owner shall notify the Contractor that it is considering such a change and Contractor shall provide Owner with a proposed price and scheduling proposal for all costs and impacts arising from the changed work in writing within seven (7) calendar days of Owner's written notice. Thereafter, if the parties are in agreement, Owner and Contractor shall execute a written change order which modifies this Agreement. In the absence of such an agreement, the parties shall proceed pursuant to Article 3.
1. The agreed amount of payment and adjustment in Contract schedule, if any, in a written executed change order constitutes a full, complete, and final payment for all work arising from the change order. Contractor, in executing any such change order, waives any entitlement to additional compensation or extensions of time arising from the change.
Changes Requested by Owner. CLARENDON COUNTY may unilaterally, at any time, on written order, without notice to the surety, and without invalidating the Contract, make changes in the work herein contracted for. CLARENDON COUNTY shall notify the Contractor that it is considering such a change and Contractor shall provide with a proposed price and scheduling proposal for all costs and impacts arising from the changed work in writing within seven (7) calendar days of CLARENDON COUNTY's written notice. Thereafter, if the parties are in agreement, CLARENDON COUNTY and Contractor shall execute a written change order which modifies this Agreement. In the absence of such an agreement, the parties shall proceed pursuant to Article 4.
Changes Requested by Owner. Owner may unilaterally, at any time, on written order, without notice to the surety, and without invalidating the Contract, make changes in the work herein contracted for. Owner shall notify the Contractor that it is considering such a change and Contractor shall provide Owner with a proposed price and scheduling proposal for all costs and impacts arising from the changed work in writing within seven (7) calendar days of Owner's written notice. Thereafter, if the parties are in agreement, Owner