DAMAGES FOR DELAY IN COMPLETION Clause Samples

The "Damages for Delay in Completion" clause establishes the contractor's liability to pay compensation if a project is not finished by the agreed-upon deadline. Typically, this clause specifies a daily or weekly monetary penalty for each period the completion is delayed beyond the contractual date, often capped at a maximum amount. Its core function is to incentivize timely performance and compensate the client for losses or inconvenience caused by late delivery, thereby allocating the risk of delay to the contractor.
DAMAGES FOR DELAY IN COMPLETION. 29.1 If Completion does not occur by the Date for Completion, due to the default of either Party, the Party who is at fault must pay the other Party as liquidated damages on Completion: (a) interest on the Price at the rate of 10% per annum calculated on a daily basis from the date 7 days after the Date for Completion to Completion (inclusive); and (b) the amount of $660.00 (including GST) to be applied towards any legal costs and disbursements incurred by the Party not at default if Completion occurs later than 7 days after the Date for Completion. 29.2 The Party at fault must pay the amount specified in clause 29.1 in addition to any other damages to which the Party not at fault is entitled both at law and under this Contract. 29.3 The Parties agree that: (a) the amount of any damages payable under clause 29.1(a) to the Party not in default is a genuine and honest pre-estimate of loss to that Party for the delay in Completion; and (b) the damages must be paid on Completion.
DAMAGES FOR DELAY IN COMPLETION. 30.1 If Completion does not occur by the Date for Completion, due to the default of either party, the party who is at fault must pay the other party as liquidated damages on Completion: (a) interest on the Price at the rate of 10% per annum calculated on a daily basis from the Date for Completion to Completion; and (b) the amount of $660 (including GST) to be applied towards any legal costs and disbursements incurred by the party not at default if Completion occurs later than 5 Working Days after the Date for Completion. 30.2 The party at fault must pay the amount specified in clause 30.1 in addition to any other damages to which the party not at fault is entitled both at law and under this Contract. 30.3 The parties agree that: (a) the amount of any damages payable under clauses 30.1(a) to the party not in default is a genuine and honest pre-estimate of loss to that party for the delay in Completion, and (b) the damages must be paid on Completion.
DAMAGES FOR DELAY IN COMPLETION. 43.1 If the Contractor fails to complete the Works by the date for practical completion stated in the appendix to these conditions, or within any extended time fixed under clause 36.0 of these conditions, and the Architect certifies in writing that in his opinion the same ought reasonably so to have been completed, then the Contractor shall pay or allow to the Employer a sum calculated at the rate stated in the said appendix as liquidated damages for the period during which the Works shall so remain or have remained incomplete, and the Employer may deduct such sum from any money due or to become due to the Contractor under the contract or recover the same from the Contractor as a debt. 43.2 The payment or deduction of such damages shall not relieve the Contractor from his obligations to complete the Works or any part thereof or from any other obligations and liabilities under the contract.
DAMAGES FOR DELAY IN COMPLETION. 23.1 If Completion does not occur by the Date for Completion, due to the default of the Buyer, then the Buyer must pay the Seller as liquidated damages on Completion: (a) interest on the unpaid balance of the Price at the rate of 10% per annum calculated on a daily basis from the Date for Completion to Completion; and (b) the amount of $1,100 (GST inclusive) to be applied towards any legal costs and disbursements incurred by the Seller if Completion occurs later than 5 Working Days after the Date for Completion. 23.2 The Buyer agrees that: (a) the amount of any damages payable under clause 23.1 to the Seller is a genuine and honest pre-estimate of loss to that party for the delay in Completion; and (b) the damages must be paid on Completion.
DAMAGES FOR DELAY IN COMPLETION. If the Work is uncompleted after the Contract Time, including all extensions and adjustments in accordance with General Provisions Section 80-07 “Determination and Extension of Contract Time”, the sum stipulated in General Provisions Section 80-08 “Failure to Complete on Time” will be deducted from any money due or to become due the Contractor or their surety. Such deducted sums shall not be deducted as a penalty but shall be considered as liquidation of a reasonable portion of damages including but not limited to additional engineering services that will be incurred by the Owner should the Contractor fail to complete the work in the Contract Time provided in this Contract.
DAMAGES FOR DELAY IN COMPLETION. 16.1 If Completion does not occur on or before the Date for Completion, due to the default of the Buyer, the Buyer must pay to the Seller as liquidated damages on Completion: (a) interest on the Price at the rate of 10% per annum calculated on a daily basis from the Date for Completion to Completion; and (b) the sum of $550.00 (including GST) to be applied towards any additional legal costs and disbursements incurred by the party not at fault if Completion occurs later than 7 days after the Date for Completion. 16.2 The Buyer must pay the sum specified in clause 16.1(b) in addition to any other damages to which the Seller is entitled both at law and under this Contract. 16.3 The Buyer agrees that: (a) the amount of any damages payable pursuant to clauses 16.1 to the Seller is a genuine and honest pre-estimate of loss to the Seller for the delay in completion; and (b) the damages will be paid on Completion. 16.4 This clause is an essential term of this Contract.
DAMAGES FOR DELAY IN COMPLETION. 27.1 If the Sub-Contractor fails to complete the sub-contract works by the date for practical completion stated in the appendix to these conditions or within any extended time fixed under clause 25.0 herein, and the Architect certifies in writing that in his opinion the same ought reasonably so to have been completed, then the Sub-Contractor shall pay or allow to the Contractor a sum calculated at the rate stated in the said appendix as liquidated damages for the period during which the works shall so remain or have remained incomplete. 27.2 The Contractor may deduct such sum from any money due or to become due to the Sub-Contractor under the sub-contract or recover the same from the Sub-Contractor as a debt. Provided that the Contractor shall not be entitled to recover any liquidated damages from the Sub- Contractor without first obtaining the Architect‟s certificate of delay prescribed herein.
DAMAGES FOR DELAY IN COMPLETION. A. Liquidated Damages for Delay (Not Used) B. COUNTY's Rights Cumulative C. Waiver of Liquidated Damages (Not Used)

Related to DAMAGES FOR DELAY IN COMPLETION

  • Damages for delay Subject to the provisions of Clause 12.4, if COD does not occur prior to the 91st day after the Scheduled Completion Date, unless the delay is on account of reasons solely attributable to the Authority or due to Force Majeure, the Concessionaire shall pay Damages to the Authority in a sum calculated at the rate of 0.1% (zero point one per cent) of the amount of Performance Security for delay of each day until COD is achieved.

  • Liquidated Damages for Delay In addition to the Contractor bearing the actual cost of correcting any non-compliant work or any other actual damages resulting from Contractor’s breach of this Agreement, the Contractor agrees to pay the Contractor delay damages in the amount of $500.00 per day for every day that the goods and/or services to be provided pursuant to this Agreement have not been timely delivered to the District in compliance with the Scope of Services set forth above, unless the delay has been properly excused by the terms of this Agreement. The parties agree that the District’s actual damages for delay are difficult to estimate and that this $500.00 per day sum is a reasonable pre-estimate of the District’s actual damages for each day of delay and that the is $500.00 per day sum is intended by the parties to be in the nature of liquidated damages, not a penalty. It is not the parties’ intent for this provision to limit either party’s remedies against the other for the breach of this Agreement, except for the District’s money damages for unexcused delays caused by the Contractor.

  • No Damages for Delay The Contractor has no claim for monetary damages for delay or hindrances to the Work from any cause, including without limitation any act or omission of the Owner.

  • Force Majeure, Notice of Delay, and No Damages for Delay The Contractor will not be responsible for delay resulting from its failure to perform if neither the fault nor the negligence of the Contractor or its employees, subcontractors, or agents contributed to the delay and the delay is due directly to acts of God, wars, acts of public enemies, strikes, fires, floods, or other similar cause wholly beyond the Contractor’s control, or for any of the foregoing that affect suppliers if no alternate source of supply is available to the Contractor. In case of any delay the Contractor believes is excusable, the Contractor shall notify the Department in writing of the delay or potential delay and describe the cause of the delay either (i) within ten (10) calendar days after the cause that creates or will create the delay first arose, if the Contractor could reasonably foresee that a delay could occur as a result; or (ii) if a delay is not reasonably foreseeable, within five (5) calendar days after the date the Contractor first had reason to believe that a delay could result. THE FOREGOING WILL CONSTITUTE THE CONTRACTOR’S SOLE REMEDY OR EXCUSE WITH RESPECT TO ANY DELAY except if such delay is caused by the fraud, bad faith, or active interference of the Department. Providing notice in strict accordance with this paragraph is a condition precedent to such remedy, and a rebuttable presumption of prejudice will exist based on Contractor’s untimely notice. The Contractor shall not assert any claim for damages related to such delay. The Contractor will not be entitled to an increase in the Term Contract price or payment of any kind from the Department for direct, indirect, consequential, impact, or other costs, expenses, or damages, including costs of acceleration or inefficiency, arising because of delay, disruption, interference, or hindrance from any cause whatsoever. If performance is suspended or delayed, in whole or in part, due to any of the causes described in this subsection, the Department may unilaterally (and with no recourse on the part of the Contractor) identify and use an alternate source to complete any work under the Term Contract as the Department deems necessary, in its sole discretion. After the causes have ceased to exist, the Contractor shall perform at no increased cost, unless the Department determines, in its sole discretion, that the delay will significantly impair the value of the Contract to the Department or State, in which case the Department may (i) accept allocated performance or deliveries from the Contractor, provided that the Contractor grants preferential treatment to the Department with respect to Products subjected to allocation; or (ii) terminate the Term Contract in whole or in part.

  • Effect of Failure or Delay in Requesting Compensation Failure or delay on the part of any Lender or the Issuing Bank to demand compensation pursuant to this Section 5.01 shall not constitute a waiver of such Lender’s or the Issuing Bank’s right to demand such compensation; provided that the Borrower shall not be required to compensate a Lender or the Issuing Bank pursuant to this Section 5.01 for any increased costs or reductions incurred more than 180 days prior to the date that such Lender or the Issuing Bank, as the case may be, notifies the Borrower of the Change in Law giving rise to such increased costs or reductions and of such Lender’s or the Issuing Bank’s intention to claim compensation therefor; provided further that, if the Change in Law giving rise to such increased costs or reductions is retroactive, then the 180-day period referred to above shall be extended to include the period of retroactive effect thereof.