DELETED WORK. In the event of Deleted Work results in a shortening of the Contract Time, the Contract Sum shall be reduced by an amount calculated as the product of (1) by the number of Days in the period of shortening, multiplied by (2) the liquidated damages amount stated in this Section 3.5.
Appears in 2 contracts
Sources: Design Build Contract, Design Build Contract
DELETED WORK. In the event of Deleted Work results in a shortening of the Contract Time, the Contract Sum shall be reduced by an amount calculated as the product of (1) by the number of Days in the period of shortening, multiplied by (2) the liquidated damages amount daily rate stated in this Section 3.53.4.6.
Appears in 1 contract
Sources: Design Build Contract