Delivery of Request for Change Order Clause Samples

The "Delivery of Request for Change Order" clause defines the process by which one party formally submits a request to modify the terms, scope, or conditions of an existing contract. Typically, this clause outlines the required method of delivery—such as written notice, electronic communication, or a specific form—and may specify the information that must be included in the request, such as a description of the proposed change and its rationale. Its core function is to ensure that all change requests are communicated clearly and consistently, reducing misunderstandings and providing a documented process for managing contract modifications.
Delivery of Request for Change Order. Maintenance Contractor shall deliver a Request for Change Order under this Section 10.3.2.5 to TxDOT within 30 days after delivery of the PCO Notice, or such longer period of time as may be allowed in writing by TxDOT. TxDOT may require design and construction costs to be covered by separate Requests for Change Order. If Maintenance Contractor fails to deliver a complete Request for Change Order or incomplete Request for Change Order meeting all of the requirements of Section 10.3.2.6 within the appropriate time period, Maintenance Contractor shall be required to provide a new PCO Notice before it may submit a Request for Change Order.
Delivery of Request for Change Order. DB Contractor shall deliver a Request for Change Order under this Section 10.3.2.5 to TxDOT within 30 Days after delivery of the PCO Notice, or such longer period of time as may be allowed in writing by TxDOT. TxDOT may require design and construction costs to be covered by separate Requests for Change Order.
Delivery of Request for Change Order. DB Contractor shall deliver a Request for Change Order under this Section 4.5.6.1 to TxDOT within 30 days after delivery of the PCO Notice or within 10 Business Days after receipt of TxDOT’s determination to require a Request for Change Order in accordance with Section 4.5.4.1.3, whichever is applicable. TxDOT may require design and construction costs to be covered by separate Requests for Change Order. If DB Contractor fails to deliver a complete Request for Change Order meeting all of the requirements of Section 4.5.6.2 within the appropriate time period, DB Contractor shall be required to provide a new PCO Notice before it may submit a Request for Change Order.
Delivery of Request for Change Order. DB Contractor shall deliver a Request for Change Order under this Section 13.3.2.4 to TxDOT within 30 days after delivery of the PCO Notice, or such longer period of time as may be allowed in writing by TxDOT. TxDOT may require design and construction costs to be covered by separate Requests for Change Order. If DB Contractor requests a time extension, then TxDOT, in its sole discretion, may require DB Contractor to provide two alternative Requests for Change Order, one of which shall provide for a time extension and any additional costs permitted hereunder, and the other of which shall show all Acceleration Costs associated with meeting the non-extended Completion Deadlines, as well as any additional costs permitted hereunder. If it is not feasible to recover to the non-extended Completion Deadline or if DB Contractor believes that the costs associated with such a recovery are prohibitive, then DB Contractor shall recommend a date to be shown in the alternative Change Order form. If DB Contractor fails to deliver a complete Request for Change Order or incomplete Request for Change Order meeting all of the requirements of this Section 13.3.2.4 within the appropriate time period, DB Contractor shall be required to provide a new PCO Notice before it may submit a Request for Change Order.
Delivery of Request for Change Order. Design-Builder shall deliver a Request for Change Order to VPRA within sixty (60) Days after Design-Builder’s delivery of the Change Notice. If Design-Builder fails to submit a complete Request for Change Order within sixty (60) Days after Design-Builder’s delivery of the Change Notice, Design-Builder shall be deemed to have irrevocably and forever waived and released any right to any relief whatsoever for any effect attributable or related to the Relief Event and the acts or omissions comprising such Relief Event; provided, however, that if Design-Builder submits a Request for Change Order within sixty (60) Days of the date of Design-Builder’s delivery of the Change Notice and VPRA responds as provided in Section 12.5.1 that Design-Builder’s Request for Change Order is incomplete, Design-Builder shall have until the later of (a) fifteen (15) Days after receipt of VPRA’s notice pursuant to Section 12.5.1 or (b) sixty (60) Days after Design- Builder’s delivery of the Change Notice, to comply in full with Section 12.4.1 before the waiver herein becomes effective.
Delivery of Request for Change Order. Integrator shall deliver all Requests for Change Order under this Section 13.3 to TxDOT within 30 days after delivery of the PCO Notice, or such longer period of time as may be allowed in writing by TxDOT. TxDOT may require design and construction costs to be covered by separate Requests for Change Order. If Integrator requests a time extension, then TxDOT, in its sole discretion, may require Integrator to provide two alternative Requests for Change Order, one of which shall provide for a time extension and any additional costs permitted hereunder, and the other of which shall show all Acceleration Costs associated with meeting the original Completion Deadlines, as well as any additional costs permitted hereunder. If it is not feasible to recover to the original Completion Deadline or if Integrator believes that the costs associated with such a recovery are prohibitive, then Integrator shall recommend a date to be shown in the alternative Change Order form. If Integrator fails to deliver a complete Request for Change Order or incomplete Request for Change Order meeting all of the requirements of Section 13.3.2.6 within the appropriate time period, Integrator shall be required to provide a new PCO Notice before it may submit a Request for Change Order.
Delivery of Request for Change Order. Contractor shall deliver a Request for Change Order to VPRA within sixty (60) Days after Contractor’s delivery of the Change Notice. If Contractor fails to submit a complete Request for Change Order within sixty (60) Days after Contractor’s delivery of the Change Notice, Contractor shall be deemed to have irrevocably and forever waived and released any right to any relief whatsoever for any effect attributable or related to the Relief Event and the acts or omissions comprising such Relief Event; provided, however, that if Contractor submits a Request for Change Order within sixty (60) Days of the date of Contractor’s delivery of the Change Notice and VPRA responds as provided in Section 14.5.1 of these General Terms and Conditions that Contractor’s Request for Change Order is incomplete, Contractor shall have until the later of (a) fifteen (15) Days after receipt of VPRA’s notice pursuant to Section 14.5.1 of these General Terms and Conditions or (b) sixty (60) Days after Contractor’s delivery of the Change Notice, to comply in full with Section 14.4.1 of these General Terms and Conditions before the waiver herein becomes effective.