Interim Dates Sample Clauses

Interim Dates. Interim milestone dates, if any, of identified portions of the services set forth in this Agreement shall be achieved as described in a separate exhibit to this Agreement.
Interim Dates. Interim milestone dates, if any, of identified portions of the services set forthin this Contract shall be achieved as described in a separate attachment to this Contract.
Interim Dates. Interim milestone dates are as follows:
Interim Dates. Fire Station 11 a. Begin design of projects within 5 working days of project award (Nov. 20) b. Submit preliminary design drawings and specification within 30 working days of project award. Public Works staff will review & respond within 5 working days. (Dec. 28) c. Submit permit application, final design and Construction/Work Plan within working 60 days of project award. (Feb. 8)
Interim Dates a. Anticipated Notice To Proceed: April 14, 2021 b. Start of design: Within 5 days of NTP
Interim Dates 

Related to Interim Dates

  • Due Dates If the payment due date falls on a Sunday or on a holiday that is observed on a Monday, the payment due date shall be the first non-holiday day following such Sunday or holiday. If the payment due date falls on a Saturday or on a holiday which is observed on Tuesday, Wednesday, Thursday, or Friday, the payment due date shall be the last non-holiday day preceding such Saturday or holiday. If payment is not received by the payment due date, a late payment charge, as set forth in Section 1.4.1.2, below, shall apply.

  • Effective Dates This Letter of Understanding shall take effect for all grievances filed on or after February 1, 2022. This ▇▇▇ shall expire upon successful ratification of a Memorandum of Agreement with respect to central terms. Should a Memorandum of Agreement with respect to central terms not be successfully ratified, the parties will meet within thirty (30) calendar days of the unsuccessful ratification vote to either extend or terminate this ▇▇▇. If this ▇▇▇ is terminated, the parties agree to move grievances filed under the interim procedure back to the appropriate central or local grievance procedure and to their respective steps in those procedures.

  • Review Periods Owner shall have up to ten (10) Business Days from its receipt of the documents listed in Sections 1.3 and 1.4 above, to issue to Contractor written comments on such documents, Drawings and Specifications. The Owner’s approval rights only apply to documents listed in Section 1.3. If comments are not received for items listed in Section 1.3 in ten (10) Business Days, the Contractor may proceed with the development of the Drawings and Specifications with the design reflected in the uncommented document. Owner will annotate the Drawings and Specifications as appropriate and return to Contractor. In the event that Owner disapproves the Drawings or Specifications, Owner shall provide Contractor with a written statement of the reasons for such rejection within the time period required for Owner’s response, and Contractor shall provide Owner with agreed to revised and corrected Drawings and Specifications as soon as possible thereafter.

  • Payment Dates Whenever any payment or other obligation hereunder shall be due on a day other than a Business Day, such payment shall be made on the next succeeding Business Day.

  • Coverage Changes and Effective Dates 39 40 Subd. 1. When Coverage May Be Chosen.