Monthly Progress Reports. During the Construction Period, the Contractor shall, no later than 10 (ten) days after the close of each month, furnish to the Authority and the Authority’s Engineer a monthly report on progress of the Works and shall promptly give such other relevant information as may be required by the Authority’s Engineer.
Appears in 32 contracts
Sources: Construction Contract, Epc Agreement, Engineering, Procurement & Construction (Epc) Agreement
Monthly Progress Reports. During the Construction Period, the Contractor Concessionaire shall, no later than 10 7 (tenseven) days after the close of each month, furnish to the Authority and the Authority’s Independent Engineer a monthly report on progress of the Construction Works and shall promptly give such other relevant information as may be required by the Authority’s Independent Engineer.
Appears in 28 contracts
Sources: Concession Agreement, Concession Agreement, Concession Agreement
Monthly Progress Reports. During the Construction Period, the Contractor shall, no later than 10 (ten) days after the close of each month, furnish to the Authority and the Authority’s Authority Engineer a monthly report on the progress of the Works and shall promptly give such other relevant information as may be required by the Authority’s EngineerAuthority Engineer along with all resources deployed and all problems faced during work.
Appears in 12 contracts
Sources: Engineering, Procurement and Construction (Epc) Agreement, Engineering, Procurement and Construction (Epc) Agreement, Epc Agreement
Monthly Progress Reports. During the Construction Period, the Contractor shall, no later than 10 (ten) days after the close of each month, furnish to the Authority and the Authority’s Engineer a monthly report on progress of the Works and shall promptly give such other relevant information as may be required by the Authority’s Engineer. The monthly progress reports shall include safety statistics, including details of any hazardous incidents and activities relating to environmental, resettlement and other obligations under Clauses 3.10 to 3.14.
Appears in 8 contracts
Sources: Draft Contract Agreement, Draft Contract Agreement (Dca), Draft Contract Agreement
Monthly Progress Reports. During the Construction Period, the Contractor shall, no later than 10 (ten) days after the close of each month, furnish to the Authority and the Authority’s Authority Engineer a monthly report on the progress of the Works and shall promptly give such other relevant information as may be required by the Authority’s EngineerAuthorityEngineeralong with all resources deployed and all problems faced during work.
Appears in 7 contracts
Sources: Standard Engineering, Procurement and Construction (Epc) Agreement, Standard Engineering, Procurement and Construction (Epc) Agreement, Standard Engineering, Procurement and Construction (Epc) Agreement
Monthly Progress Reports. During the Construction Period, the Contractor shall, no later than 10 (ten) days after the close of each month, furnish to the Authority and the Authority’s Authority‟s Engineer a monthly report on progress of the Works and shall promptly give such other relevant information as may be required by the Authority’s Authority‟s Engineer.
Appears in 7 contracts
Sources: Engineering, Procurement and Construction Agreement, Construction Contract, Epc Agreement
Monthly Progress Reports. During the Construction Period, the Contractor Concessionaire shall, no later than 10 (ten7(seven) days after the close of each month, furnish to the Authority and the Authority’s Independent Engineer a monthly report on progress of the Construction Works and shall promptly give such other relevant information as may be required by the Authority’s Independent Engineer.
Appears in 4 contracts
Sources: Concession Agreement, Concession Agreement, Concession Agreement
Monthly Progress Reports. During the Construction Period, the Contractor shall, no later than 10 (ten) days after the close of each month, furnish to the Authority and the Authority’s Engineer a monthly report on the progress of the Works and shall promptly give such other relevant information as may be required by the Authority’s EngineerEngineer along with all resources deployed and all problems faced during work.
Appears in 3 contracts
Sources: Standard Engineering, Procurement and Construction (Epc) Agreement for Railway Projects, Standard Engineering, Procurement and Construction (Epc) Agreement for Railway Projects, Standard Engineering, Procurement and Construction (Epc) Agreement for Railway Projects
Monthly Progress Reports. During the Construction Period, the Contractor shall, no later than 10 (ten) days after the close of each month, furnish to the Authority Employer and the Authority’s Employer's Engineer a monthly report on progress of the Works and shall promptly give such other relevant information as may be required by the Authority’s Employer's Engineer.
Appears in 3 contracts
Sources: Epc Agreement, Epc Agreement, Engineering, Procurement and Construction Agreement
Monthly Progress Reports. During the Construction Period, the Contractor shall, no later than 10 (ten) days after the close of each month, furnish to the Authority Employer and the AuthorityEmployer’s Engineer a monthly report on progress of the Works and shall promptly give such other relevant information as may be required by the AuthorityEmployer’s Engineer.
Appears in 2 contracts
Sources: Epc Agreement, Contract Agreement for Design and Construction
Monthly Progress Reports. During the Construction Period, the Contractor shall, no later than 10 (ten) days after the close of each month, furnish to the Authority and the Authority’s Engineer a monthly report on progress of the Works and shall promptly give such other relevant information as may be required by the Authority’s Engineer.. The Contractor agrees that reporting under this Clause 11.7 shall continue until the date of the completion of the Works. Each report shall include:
Appears in 2 contracts
Sources: Construction Contract, Construction Contract
Monthly Progress Reports. During the Construction Period, the Contractor Developer shall, no later than 10 7 (tenseven) days after the close of each month, furnish to the Authority Client and the Authority’s Independent Engineer a monthly report on progress of the Construction Works and shall promptly give such other relevant information as may be required by the Authority’s EngineerClient.
Appears in 2 contracts
Sources: Development Agreement, Development Agreement
Monthly Progress Reports. During the Construction Period, the Contractor shall, no later than 10 (ten) days after the close of each month, furnish to the Authority and the Authority’s Engineer a monthly report on the progress of the Works and shall promptly give such other relevant information as may be required by the Authority’s Engineer.
Appears in 1 contract
Sources: Engineering, Procurement and Construction (Epc) Agreement
Monthly Progress Reports. During the Construction Period, the Contractor shall, no later than 10 (ten) days after the close of each month, furnish to the Authority SPV and the AuthoritySPV’s Engineer a monthly report on the progress of the Works and shall promptly give such other relevant information as may be required by the AuthoritySPV’s EngineerEngineer along with all resources deployed and all problems faced during work.
Appears in 1 contract
Sources: Epc Agreement
Monthly Progress Reports. During the Construction Period, the Contractor shall, no later than 10 (ten) days after the close of each month, furnish to the Authority Authority/GMDA and the Authority’s AUTHORITY’S/GMDAs Engineer a monthly report on progress of the Works and shall promptly give such other relevant information as may be required by the Authority’s AUTHORITY’S/GMDAs Engineer.
Appears in 1 contract
Monthly Progress Reports. During the Construction Period, the Contractor shall, no later than 10 (ten) days after the close of each month, furnish to the Authority Employer and the Authority’s Employer‟s Engineer a monthly report on progress of the Works and shall promptly give such other relevant information as may be required by the Authority’s Employer‟s Engineer.
Appears in 1 contract
Sources: Epc Agreement
Monthly Progress Reports. During the Construction Period, the Contractor shall, no later than 10 (ten) days after the close of each month, furnish to the Authority and the Authority’s Engineer a monthly report on progress of the Works and shall promptly give such other relevant information as may be required by the Authority’s Engineer.. The Contractor agrees that reporting under this Clause 11.7 shall continue until the
Appears in 1 contract
Sources: Construction Contract
Monthly Progress Reports. During the Construction Period, the Contractor shall, no later than 10 (ten) days after the close of each month, furnish to the Authority and the Authority’s Engineer a monthly report on progress of the Works and shall promptly give such other relevant information as may be required by the Authority’s Engineer.. The Contractor agrees that reporting under this Clause 11.7 shall continue until the date of the completion of the Works. Each report shall include: Improvement and widening to two lane with paved shoulder of road from Km 21.100 to Km
Appears in 1 contract
Sources: Contract Agreement
Monthly Progress Reports. During the Construction Period, the Contractor Developer shall, no later than 10 7 (tenseven) days after the close of each month, furnish to the Authority SH&DB and the Authority’s Independent Engineer a monthly report on progress of the Construction Works and shall promptly give such other relevant information as may be required by the Authority’s Independent Engineer.
Appears in 1 contract
Sources: Development Agreement
Monthly Progress Reports. During the Construction Period, the Contractor shall, no later than 10 (ten) days after the close of each month, furnish to the Authority and the Authority’s Engineer a monthly report re- port on progress of the Works and shall promptly give such other relevant information as may be required by the Authority’s Engineer.
Appears in 1 contract
Sources: Construction Contract