Monthly Progress Schedule Sample Clauses

Monthly Progress Schedule. ‌ 13 Developer shall prepare a Monthly Progress Schedule that updates the Project Baseline 14 Schedule during the D&C Period, commencing after issuance of NTP 2, until the closing for final 15 payment for the Work associated with NTP 2. The Monthly Progress Schedule must reflect 16 progress up to the closing date, forecast finish for in-progress activities and re-forecast early 17 dates for activities planned in the next update period. The Monthly Progress Schedule must 18 include the following:
Monthly Progress Schedule. ‌ 4 Developer shall prepare a Monthly Progress Schedule that updates the Project Baseline 5 Schedule during the D&C Period, commencing after issuance of NTP 2, until the closing for final 6 payment for the Work associated with NTP 2. The Monthly Progress Schedule must reflect 7 progress up to the closing date, forecast finish for in-progress activities and re-forecast early 8 dates for activities planned in the next update period. The Monthly Progress Schedule must 9 include the following:
Monthly Progress Schedule. 27 Developer shall prepare a Monthly Progress Schedule that updates the Project Baseline Schedule during 28 the Work, commencing after issuance of NTP 2, until the closing for Final Payment. The Monthly Progress 29 Schedule shall reflect progress up to the closing date, forecast finish for in-progress activities and re- 30 forecast early dates for activities planned in the next update period. The Monthly Progress Schedule shall 31 include the following: 32 Actual start and finish dates for completed activities; 1 Actual start dates, percentage complete, and remaining duration for activities in progress; 2 All proposed activities, logic, and restraint date revisions required to:
Monthly Progress Schedule. The term “Monthly Progress Schedule(s)” means the updated Contract Schedule provided monthly by Contractor to Judicial Council updates to the Approved Construction Schedule consistent with the requirements of the Contract Documents.

Related to Monthly Progress Schedule

  • PROGRESS SCHEDULE The Contractor, within ten (10) working days of receiving notice of the award of the contract, shall prepare and submit for the State's and Architect's information an estimated progress schedule for the Work. The progress schedule shall be related to the entire Project to the extent required by the Contract Documents, and shall provide for expeditious and practicable execution of the Work.

  • Construction Progress Schedule A schedule indicating proposed activity sequences and durations, milestone dates for receipt and approval of pertinent information, preparation, submittal, and processing of Shop Drawings and Samples, delivery of materials or equipment requiring long-lead time procurement, and proposed date(s) of Material Completion and Occupancy and Final Completion. The schedule will be developed to represent the sixteen or seventeen CSI Specification Divisions. It shall have a minimum number of activities as required to adequately represent to Owner the complete scope of work and define the Project’s critical path and associated activities. If the Project is to be phased, then each individual Phase should be identified from start through completion of the overall Project and should be individually scheduled and described, including any Owner’s occupancy requirements and showing portions of the Project having occupancy priority. The format of the schedule will have dependencies indicated on a monthly grid identifying milestone dates such as construction start, phase construction, structural top out, dry-in, rough-in completion, metal stud and drywall completion, equipment installation, systems operational, Material Completion and Occupancy Date, final inspection dates, Punchlist, and Final Completion date.

  • DISTRIBUTION OF CONTRACTOR PRICE LIST AND CONTRACT APPENDICES Contractor shall provide Authorized Users with electronic copies of the Contract, including price lists and Appendices, upon request. Contract Updates will be handled as provided in Appendix C – Contract Modification Procedures.

  • Recovery Schedule If the initial schedule or any current updates fail to reflect the Work’s actual plan or method of operation, or a contractual milestone date is more than fifteen (15) days behind, Owner may require that a recovery schedule for completion of the remaining Work be submitted. The Recovery Schedule must be submitted within seven (7) calendar days of Owner’s request. The Recovery Schedule shall describe in detail Construction Contractor’s plan to complete the remaining Work by the required Contract milestone date. The Recovery Schedule submitted shall meet the same requirements as the original Construction Schedule. The narrative submitted with the Recovery Schedule should describe in detail all changes that have been made to meet the Contract milestone dates.

  • Shift Schedule The words "shift schedule" when used in this Agreement shall mean a timetable of the shifts and off days assigned to a position or group of positions which commences at the beginning of a pay period and includes one complete rotation of said shifts.