Project Cost An updated cost spreadsheet reflecting the current forecasted cost vs. the latest approved budget vs. the baseline budget should be included in this section. One way to track project cost is to show: (1) Baseline Budget, (2) Latest Approved Budget, (3) Current Forecasted Cost Estimate, (4) Expenditures or Commitments to Date, and (5) Variance between Current Forecasted Cost and Latest Approved Budget. Line items should include all significant cost centers, such as prior costs, right-of-way, preliminary engineering, environmental mitigation, general engineering consultant, section design contracts, construction administration, utilities, construction packages, force accounts/task orders, wrap-up insurance, construction contingencies, management contingencies, and other contingencies. The line items can be broken-up in enough detail such that specific areas of cost change can be sufficiently tracked and future improvements made to the overall cost estimating methodology. A Program Total line should be included at the bottom of the spreadsheet. Narratives, tables, and/or graphs should accompany the updated cost spreadsheet, basically detailing the current cost status, reasons for cost deviations, impacts of cost overruns, and efforts to mitigate cost overruns. The following information should be provided:
At Cost Any of the above services when performed outside regular working hours of Agent may be billed at 150 percent of the above.
Total Project Cost With regard to any Real Property acquired prior to or during the development, construction or improvement stages, all hard and soft costs and expenses paid or incurred by or on behalf of the Corporation that are in any way related to the development, construction, improvement or stabilization (including tenant improvements) of such Real Property, including, but not limited to, any debt, whether borrowed or assumed, land and construction costs.
Estimated Cost Estimated costs by construction phases for Specified Roads listed in A7 are stated by segments in the Schedule of Items. Such estimated costs are subject to adjustment under B3.3, B5.2, B5.21, B5.212, B5.25, and B5.26. Appropriately adjusted costs shall be made a part of a revised Schedule of Items and shown as adjustments to Timber Sale Account. The revised Schedule of Items shall supersede any prior Schedule of Items when it is dated and signed by Contracting Officer and a copy is furnished to Purchaser.
Total Cost It is estimated that the total cost to Princeton University for the performance of this Contract shall not exceed the Not-to-Exceed Price set forth in the Contract and the Contractor agrees to use its best efforts to perform the Work specified in the Contract and all obligations under this Contract within such Not-to- Exceed Price. If at any time the Contractor has reason to believe that the hourly rate payments and material costs that will accrue in performing this Contract in the next succeeding thirty (30) days, if added to all other payments and costs previously accrued, will exceed eighty-five percent (85%) of the Not-to-Exceed Price in the Contract, the Contractor shall notify Princeton University giving a revised estimate of the total price for performing this Contract with supporting reasons and documentation. If at any time during performing this Contract, the Contractor has reason to believe that the total price to Princeton University for performing this Contract will be substantially greater or less than stated Not-to-Exceed Price, the Contractor shall so notify Princeton University, giving a revised estimate of the total price for performing this Contract, with supporting reasons and documentation. If at any time during performance of this Contract, Princeton University has reason to believe that the cost required to perform the Work of this Contract will be substantially greater or less than the stated Not-to-Exceed Price, Princeton University will so advise the Contractor, giving the then- revised estimate of the total amount of effort to be required under the Contract.