No Time Extensions Clause Samples

The "No Time Extensions" clause establishes that the deadlines or timeframes set forth in the agreement are strict and cannot be extended under any circumstances. In practice, this means that parties must complete their obligations within the specified periods, regardless of delays or unforeseen events, and cannot request additional time. This clause ensures certainty and predictability in project timelines, preventing disputes over schedule changes and encouraging timely performance.
No Time Extensions. Except as otherwise specifically provided in Section 13, TxDOT shall have no obligation to extend a Completion Deadline and DB Contractor shall not be relieved of its obligation to comply with the Project Schedule and to achieve Substantial Completion and Final Acceptance of the Project by the applicable Completion Deadlines for any reason.
No Time Extensions. Except as otherwise specifically provided in Section 12, TxDOT shall have no obligation to extend a Completion Deadline and Developer shall not be relieved of its obligation to comply with the Project Schedule and to achieve Substantial Completion and Final Acceptance of each Phase of the Project and complete the Bridge Demolition Work by the applicable Completion Deadlines for any reason.
No Time Extensions. ‌ Except as otherwise specifically provided in Section 13, IFA shall have no obligation to extend a Completion Deadline and Design-Build Contractor shall not be relieved of its obligation to comply with the Project Schedule and to achieve Substantial Completion and Final Acceptance by the applicable Completion Deadlines for any reason.‌
No Time Extensions. Except as otherwise specifically provided in this Contract, Owner has no obligation to extend the Scheduled Substantial Completion Date, and Contractor shall not be relieved of its obligation to achieve Substantial Completion for any reason.
No Time Extensions. Except as otherwise specifically provided in this Contract, Owner has no obligation to extend the Contract Time(s), and Contractor shall not be relieved of its obligation to achieve completion within the Contract Time(s) for any reason.
No Time Extensions. Except in the instances where a specified product is not commercially available, the Project Schedule shall not be adjusted as a result of any circumstance relating to a proposed Substitution.
No Time Extensions. Except as otherwise specifically provided in Section 14, the Alamo RMA shall have no obligation to extend the Interim Completion Deadline, Completion Deadline or Acceptance Deadline, and Design/Builder shall not be relieved of its obligations to achieve (a) the milestones described in the Project Schedule; (b) Interim Substantial Completion of the Interim Milestone by the Interim Completion Deadline, (c) Substantial Completion of the Project by the Completion Deadline; or (d) Final Acceptance by the Acceptance Deadline.
No Time Extensions. Except as otherwise specifically provided in Section 14.10, the Mobility Authority shall have no obligation to extend the Interim Completion Deadline. Except as otherwise specifically provided in Section 14, the Mobility Authority shall have no obligation to extend the Completion Deadline or Acceptance Deadline, and the DB Contractor shall not be relieved of its obligations to achieve (a) the milestones described in the Project Schedule; (b) Substantial Completion of the Project by the Completion Deadline; or (c) Final Acceptance by the Acceptance Deadline.
No Time Extensions. Except as otherwise specifically provided in Article 19, Department shall have no obligation to extend the Substantial Completion, and Contractor shall not be relieved of its obligation to achieve Substantial Completion by the Substantial Completion Date for any reason.
No Time Extensions. ‌ Except as otherwise specifically provided in Section 14, the District shall have no obligation to extend any Completion Dates, and the DB Contractor shall not be relieved of its obligation to comply with the Contract Schedule and the applicable Completion Dates for any reason.