O&M Manual Sample Clauses
POPULAR SAMPLE Copied 4 times
O&M Manual. At least sixty (60) Days prior to the start-up of the Facility or any portion thereof, Contractor shall deliver to Company four (4) copies of the preliminary draft of the O&M Manual for the Facility as provided in the Scope of Work. The O&M Manual shall include the information for that manual described in the Scope of Work. Such preliminary draft shall be as reasonably complete as available information shall allow and at a minimum with sufficient information to permit the training of Company’s operation and maintenance personnel and the normal operation and maintenance of the Facility by persons generally familiar with facilities and plants similar to the Facility. Contractor thereafter shall provide to Company four (4) copies of the final and complete O&M Manual for the Facility prior to Final Completion.
O&M Manual. (a) The Concessionaire shall prepare a detailed O&M Manual for the STP Facilities based on the Proposed Technology and in accordance with the Technical Specifications, the ESHS Documents, Applicable Laws and Applicable Permits. The O&M Manual shall specify the operation procedures (separately for each component of the STP Facilities) and maintenance procedures. If there any errors or deficiencies in the Technical Specifications, the O&M Manual shall take in account, address or rectify such errors or deficiencies. The Language for O &M Manual shall be English.
(b) At least 30 days prior to the Scheduled STP Construction Completion Date, the Concessionaire shall submit 4 hard copies and 1 soft copy on a compact disc of the draft O&M Manual to BUIDCO for its review and approval.
(c) BUIDCO shall review and provide comments, if any, on the draft O&M Manual to the Concessionaire or notify the Concessionaire of its approval of the draft O&M Manual within 20 days from the date of receipt of the draft O&M Manual from the Concessionaire. BUIDCO may require the Concessionaire to amend or modify the draft O&M Manual if BUIDCO identifies any deficiencies, inaccuracies or shortcomings in the draft O&M Manual. If the Concessionaire receives any comments, suggestions or instructions to modify the draft O&M Manual from BUIDCO, then the Concessionaire shall modify the draft O&M Manual to correct any shortcomings, inaccuracies or deficiencies identified by BUIDCO and/or address, in writing, BUIDCO's comments on the draft O&M Manual and submit the revised O&M Manual to BUIDCO for its approval. The process set out in this Clause 8.2(c) shall continue until the O&M Manual is approved by BUIDCO in accordance with this Clause 8.2(c).
(d) The Concessionaire shall revise the O&M Manual as and when the Concessionaire thinks it necessary to do so and in such case the provisions of Clause 8.2(c) will apply as is to the approval of the revised manual.
(e) The Concessionaire shall undertake the O&M of the STP Facilities strictly in accordance with the approved O&M Manual. The Concessionaire shall not deviate from or make any amendment to the approved O&M Manual without the prior written approval of BUIDCO. The Concessionaire shall not commence operation of the STP Facilities prior to approval of the O&M Manual in accordance with this Clause 8.2.
(f) Notwithstanding any approval of the O&M Manual by BUIDCO, the Concessionaire shall bear all risk, responsibility and liability for the sui...
O&M Manual. Assist CLIENT in preparing operating, maintenance, and staffing manuals. No
O&M Manual. The Consultant shall organize and prepare materials related to the new dewatering equipment and all ancillary equipment and any impacts it has on the operation of other treatment processes as needed for the City to update the existing O&M manual The O&M manual materials will be submitted to the City at approximately 60 percent construction completion.
O&M Manual. The O&M Manual serves as a guide to the purpose and function of the equipment and systems that make up the remedy. Respondents shall develop the O&M Manual in accordance with Guidance for Management of Superfund Remedies in Post Construction, OLEM 9200.3-105 (Feb. 2017).
O&M Manual. In accordance with WAC ▇▇▇-▇▇▇-▇▇▇, we will prepare an operations and maintenance (O&M) manual to describe and explain the design intent, function, and operational and maintenance requirements of the new facilities at the treatment plant. The hard copy manual will include cross referencing, with specific equipment operation and maintenance requirements provided by the Contractor (and by equipment suppliers in the case of City-procured equipment items). The O&M Manual will include: • Process control • Operational strategies • Troubleshooting guidance • Specific maintenance data for: o Headworks o Anoxic selector and aeration basins o UV disinfection o Blowers o Miscellaneous piping, valving and hydraulic structures o General plant facilities • Functional descriptions for programming • Record drawings (as completed in Task 8.2) The Draft O&M Manual will be prepared prior to construction completion and submitted to the City for review. After review comments have been incorporated, three printed and electronic copies of the Final O&M Manual will be submitted prior to the initial plant startup.
O&M Manual. The Company shall have provided to the County 5 copies of a draft Operation and Maintenance Manual 90 days before the Operations Commencement Date, and the final Operation and Maintenance Manual prior to the Operations Commencement Date;
O&M Manual. Consultant will receive from the Contractor an operation and maintenance manual (O&M) that includes all major equipment and an O&M from the LPMF supplier. Consultant to provide brief supplement outlining the purpose, design criteria, operations/controls (including normal operations, theory of operation, pump isolation), and a summary of recommended preventative maintenance activities. Consultant will submit a draft to the Owner. Upon receiving comments, Consultant will address comments and submit final O&M.
O&M Manual. At least three (3) months prior to the Completion Date, the Project Company will deliver to the Contracting Authority and the Independent Expert, the completed O&M Manual prepared on the basis of the Project Company O&M Plan . The Project Company O&M Plan, as incorporated in the O&M Manual, shall be the updated version of the O&M Plan (incorporating the Project Company Monitoring and Inspection System) which is attached in Schedule 17 (Project Company O&M Plan) to this Agreement.
O&M Manual. On or before the Substantial Completion Date for the Facility, Contractor shall deliver to Owner an operation and maintenance manual for the Facility (the “O&M Manual”) which shall contain all instruction manuals and special directions provided by Equipment manufacturers or vendors and all information necessary and appropriate for the start-up, operation, maintenance and repair of the Facility, including complete Equipment and system instructions and procedures for the start-up, operation, maintenance and repair of the Facility. The O&M Manual shall be consistent with Prudent Industry Standards and Legal Requirements.