Payments Not Acceptance of Work Sample Clauses
The "Payments Not Acceptance of Work" clause establishes that making a payment does not constitute formal acceptance of the work performed. In practice, this means that even if the client pays an invoice or makes progress payments, they retain the right to inspect, reject, or require correction of the work if it does not meet contractual standards. This clause protects the client by ensuring that payment alone does not waive their right to enforce quality or compliance, thereby preventing the contractor from claiming that payment equals approval or final acceptance.
POPULAR SAMPLE Copied 2 times
Payments Not Acceptance of Work. No payment made hereunder by Owner shall be considered as approval or acceptance of any Work by Owner or a waiver of any claim or right Owner may have hereunder. All payments shall be subject to correction in subsequent payments.
Payments Not Acceptance of Work. No payment made by Company to Contractor shall be considered or deemed to represent that Company has inspected the Work or checked the quality or quantity of the Work and shall not be deemed or construed as an approval or acceptance of any Work or as a waiver of any claim or right Company may have hereunder.
Payments Not Acceptance of Work. Owner may, upon prior written notice to Contractor, offset any amount due and payable from Contractor to Owner under this Agreement against any amount due and payable to Contractor hereunder. No payment made hereunder by Owner shall be considered as approval or acceptance of any Work by Owner or a waiver of any claim or right Owner may have hereunder. All payments shall be subject to correction or adjustment in subsequent payments.
Payments Not Acceptance of Work. Owner shall not be obligated to make any payments hereunder or release any Retainage or payments withheld, at any time in which (i) a Contractor Default shall have occurred and is continuing, or (ii) an event has occurred which, with the passage of time, will constitute a Contractor Default. Owner may, upon prior written notice to Contractor, offset any amount due and payable from Contractor to Owner against any amount due and payable to Contractor hereunder. No payment made hereunder by Owner shall be considered as approval or acceptance of any Work by Owner or a waiver of any claim or right Owner may have hereunder. All payments shall be subject to correction or adjustment in subsequent payments.
Payments Not Acceptance of Work. Owner shall not be obligated to make any payments hereunder or release any Retainage or payments withheld for any amount necessary to protect the Owner from a Contractor Default which has occurred or is continuing. Owner may, upon prior written notice to Contractor, offset any amount due and payable from Contractor to Owner against any amount due and payable to Contractor hereunder. No payment made hereunder by Owner shall be considered as approval or acceptance of any Work by Owner or a waiver of any claim or right Owner may have hereunder. All payments shall be subject to correction or adjustment in subsequent payments.
Payments Not Acceptance of Work. No payment made hereunder shall be considered as approval of acceptance of any Work. All payments shall be subject to correction or adjustment in subsequent progress reviews and payments.
Payments Not Acceptance of Work. No payment made hereunder shall be deemed an acknowledgement that the Joint Board has inspected or accepted the Work or checked the compliance, quality or quantity of the Work or that the Joint Board knows or has ascertained how or for what purpose TSP has used sums previously paid and shall not be deemed as approval or acceptance of any Work or constitute a waiver of any claim or right that the Joint Board may then or thereafter have, including among others, warranty and indemnity rights. All payments made by the Joint Board shall be subject to correction or adjustment in subsequent progress reviews and payments; provided; however, that the Joint Board may only seek a correction or adjustment within 60 days after obtaining Actual Knowledge of the basis for such correction or adjustment.