Primary Documents Sample Clauses
Primary Documents. 1. The DOE shall com plete and submit document s for the following primary document s to EPA and SCDHEC for review and comment in accordance with the provisions of this Section:
a. Community Relations Plan (CRP);
b. RFI/RI Work Plan(s);
c. RFI/RI Report(s);
d. Baseline Risk Assessment Report(s);
e. CMS/FS Report(s);
f. Statement of Basis/Proposed Plan(s);
g. Record(s) of Decision;
h. Corrective Measures Design/Remedial Design Work Plan(s);
i. Corrective Measures Design/Remedial Design Report(s);
j. Corrective Measures Implementation/Remedial Action Work Plan(s);
k. Post-Construction Report(s); and
l. Final Remediation Report(s).
2. The documents h. through l., listed in Subsection C, herein, will be submitted, as appropriate for each remedial action and may be submitted in phased packages when necessary to expedite con struction work under this Agreement. In such cases, the Recor d(s) of Decision shall describe the phased submittals which shall be con sidered primary document s for purposes of Section XLVII (Stipulated Penalties) under this Agreement.
3. Only the Revision.1 document s for the primary document s identified above shall be subject to dispute resolution. The DOE shall com plete and submit primary document s in accor dance with Section XX (Timetables and Deadlines) of this Agreement.
Primary Documents. Dispute resolution shall be available to the Parties for Revision.1 primary document s as set forth in Section XXVII (Resolution of Disputes).
Primary Documents. 8.5 As required by the Action Plan, U.S. DOE shall complete and transmit for each OU WAG the applicable primary documents to U.S. EPA and IDHW for review and comment in accordance with the provisions of this part:
(a) Remedial Investigation ("RI")/Feasibility Study ("FS") Scope of Work ("SOW")
(b) RI/FS Work Plan
(c) RI/FS Report
(d) Record of Decision ("ROD")
(e) Remedial Design ("RD")
(f) Remedial Action ("RA") Work Plan
(g) RA Report
(h) Operations and Maintenance Report
8.6 Only the draft final versions for the primary documents identified above shall be subject to dispute resolution. U.S. DOE shall complete and transmit draft primary documents in accordance with the deadlines established in Table A.1 of Appendix A of the Action Plan. The Action Plan is appended to the Agreement as Attachment A.
Primary Documents. 10.3.1 USACE shall complete and transmit draft reports for the following Primary Documents to EPA, ODEQ, and WDOE for review and comment in accordance with the provisions of this Section, except that the Site Management Plan shall be reviewed and commented on in accordance with Sections XI – DEADLINES AND CONTENTS OF SITE MANAGEMENT PLAN and XII – BUDGET DEVELOPMENT AND AMENDMENT OF SITE MANAGEMENT PLAN:
(1) RI/FS and FFS Work Plans including Sampling and Analysis Plan and Quality Assurance Project Plan (QAPP)
(2) Remedial Investigation Reports (including Risk Assessments for human health and the environment)
(3) FS and FFS Reports
Primary Documents. A. Prior to the Effective Date of this Agreement, Navy has completed and transmitted the following draft Primary Documents listed below to EPA, Interior, and the Commonwealth for review and comment. These documents are identified in Appendix D to this Agreement.
B. All Primary Documents shall be prepared in accordance with the NCP and applicable EPA Guidance. Navy shall complete and transmit drafts of the following Primary Documents and their amendments to EPA, Interior, and the Commonwealth for review and comment in accordance with the provisions of this Section: 1. RI/FS Workplans, including Sampling and Analysis Plan and QAPP
Primary Documents. 10.3.1 VA shall complete and transmit draft reports for the following Primary Documents to EPA and the UDEQ for review and comment in accordance with the provisions of this Section, except that the Site Management Plan shall be reviewed and commented on in accordance with Sections XI – DEADLINES AND CONTENTS OF SITE MANAGEMENT PLAN and XII – BUDGET DEVELOPMENT AND AMENDMENT OF SITE MANAGEMENT PLAN:
(1) the Site Management Plan and each annual amendment
(2) RI/FS and FFS Work Plans including Sampling and Analysis Plan and Quality Assurance Project Plan (QAPP)
(3) Remedial Investigation Reports (including Risk Assessments for human health and the environment)
(4) FS and FFS Reports
(5) Proposed Plans
(6) Records of Decision
(7) Final Remedial Designs
(8) Remedial Action or Emergency Removal Action Work Plans
(9) Remedial Action Completion Reports
(10) Community Involvement Plan
10.3.2 Only the draft final Primary Documents identified above (and their amendments) shall be subject to dispute resolution. VA shall complete and transmit draft Primary Documents in accordance with the Schedule and Deadlines established in Section XI – DEADLINES AND CONTENTS OF SITE MANAGEMENT PLAN.
Primary Documents. On or prior to the date of the first Loan, Agent shall have received one (1) fully executed copy of each of the following documents, previously approved by Agent:
5.4.1 this Loan Agreement;
5.4.2 the Notes;
5.4.3 the Mortgage and Assignment of Copyright;
5.4.4 the Laboratory Pledgeholder Agreement side letters;
5.4.5 the Harv▇▇ ▇▇▇rantee;
5.4.6 UCC-1 Financing Statements from Borrower in favor of Agent with respect to the Collateral;
5.4.7 the Pledgor Security Agreements and all agreements, documents and instruments contemplated thereby;
5.4.8 all Current License Agreements, other than those heretofore delivered to Agent, all of which are identified in Schedule 5.3.8 attached hereto;
5.4.9 the Notice and Acceptance Agreements for all Current License Agreements or, in lieu thereof, where approved by Agent, License Agreement Amendments, other than those heretofore delivered to Agent, all of which are identified in Schedule 5.4.9 attached hereto;
5.4.10 Copyright Office, UCC and litigation search reports, signed by Borrower, demonstrating that all of the Collateral is free and clear of any liens, claims or encumbrances, except
Primary Documents. A. Prior to the Effective Date of this Agreement, the Navy has completed and transmitted the following draft Primary Documents listed below to the EPA and the VDEQ for review and comment: None at present time.
B. All Primary Documents shall be prepared in accordance with the NCP and applicable EPA Guidance. The Navy shall complete and transmit drafts of the following Primary Documents and their amendments to the EPA and the VDEQ for review and comment in accordance with the provisions of this Section:
1. RI/FS (including Baseline Risk Assessment for human health and the environment) and FFS Work Plans
2. Remedial Investigation Reports (including Baseline Risk Assessments for human health and the environment)
3. FS and FFS Reports
Primary Documents are documents which confirm the validity of the Monetary Claim. The list of the Primary Documents is provided in Appendix No. 3 to this Agreement.
Primary Documents. 10.3.1 The Army shall complete and transmit draft reports for the following Primary Documents to EPA and the VDEQ for review and comment in accordance with the provisions of this Section, except that the Site Management Plan shall be reviewed and commented on in accordance with Sections XI – DEADLINES AND CONTENTS OF SITE MANAGEMENT PLAN and XII – BUDGET DEVELOPMENT AND AMENDMENT OF SITE MANAGEMENT PLAN:
(1) RI/FS and FFS Work Plans including Sampling and Analysis Plan and Quality Assurance Project Plan (QAPP)
(2) Remedial Investigation Reports (including Risk Assessments for human health and the environment)
(3) FS and FFS Reports
(4) Proposed Plans
(5) Records of Decision
(6) Final Remedial Designs
(7) Remedial Action Work Plans
(8) Remedial Action Completion Reports
(9) the Site Management Plan and each annual amendment
10.3.2 Only the draft final Primary Documents identified above (and their amendments) shall be subject to dispute resolution. The Army shall complete and transmit draft Primary Documents in accordance with the Schedule and Deadlines established in Section XI – DEADLINES AND CONTENTS OF SITE MANAGEMENT PLAN.
10.3.3 Prior to the Effective Date of this Agreement, the Army has completed and transmitted the following draft Primary Documents listed below to EPA and the VDEQ for review and comment: Remedial Investigations and Feasibility Studies for: FTEUST-30 ▇▇▇▇▇▇ Creek FTEUST-29 ▇▇▇▇▇’▇ Lake FTEUST-06 Fire Training Area FTEUST-27 ▇▇▇▇▇▇▇▇ Island Creek FTEUST-36 Eustis Lake FTEUST-34 DOL Storage Yard FTEUST-19 Oil/Sludge Holding Pond FTEUST-32 ▇▇▇▇▇▇ Army Airfield Proposed Plans for: FTEUST-29 ▇▇▇▇▇’▇ Lake FTEUST-27 ▇▇▇▇▇▇▇▇ Island Creek FTEUST-34 DOL Storage Yard FTEUST-19 Oil/Sludge Holding Pond FTEUST-04 Landfill #7/South Landfill FTEUST-01 Officers’ Club Landfill #1 Records of Decision for: FTEUST-29 ▇▇▇▇▇’▇ Lake FTEUST-34 DOL Storage Yard FTEUST-19 Oil/Sludge Holding Pond FTEUST-27 ▇▇▇▇▇▇▇▇ Island Creek