Procedure for Change of Scope. In the event of the Authority determining that a Change of Scope is necessary, it shall issue to the Concessionaire a notice specifying in reasonable detail the works and services contemplated there under (the "Change of Scope Notice").
Appears in 5 contracts
Sources: Concession Agreement, Concession Agreement, Concession Agreement
Procedure for Change of Scope. In the event of the Authority determining that a Change of Scope is necessary, it shall issue to the Concessionaire a notice specifying in reasonable detail the works and services contemplated there under thereunder (the "“Change of Scope Notice"”).
Appears in 4 contracts
Sources: Concession Agreement, Concession Agreement, Concession Agreement
Procedure for Change of Scope. 15.2.1 In the event of the Authority determining that a Change of Scope is necessary, it shall issue to the Concessionaire Operator a notice specifying in reasonable detail the works and services contemplated there under thereunder (the "“Change of Scope Notice"”).
15.2.2 Upon receipt of a Change of Scope Notice, the Operator shall, with due diligence, provide to the Authority such information as is necessary, together with preliminary Documentation in support of:
Appears in 2 contracts
Sources: Concession Agreement, Concession Agreement
Procedure for Change of Scope. a In the event of the Authority determining that a Change of Scope is necessary, it shall issue to the Concessionaire a notice specifying in reasonable detail the works and services contemplated there under thereunder (the "Change of Scope Notice").
Appears in 2 contracts
Sources: Concession Agreement, Concession Agreement
Procedure for Change of Scope. 13.2.1 In the event of the Authority determining that a Change of Scope is necessary, it shall may direct the Authority Engineer to issue to the Concessionaire Contractor a notice specifying in reasonable detail the works and services contemplated there under (the "“Change of Scope Notice"”).
Appears in 2 contracts
Sources: Epc Agreement, Epc Agreement
Procedure for Change of Scope. In the event of the Authority determining that a Change of Scope is necessary, it shall may direct the Authority’s Engineer to issue to the Concessionaire Contractor a notice specifying in reasonable detail the works and services contemplated there under (the "“ Change of Scope Notice"”).
Appears in 1 contract
Sources: Construction Contract
Procedure for Change of Scope. 16.2.1 In the event of the Authority determining that a Change of Scope is necessary, it shall issue to the Concessionaire a notice specifying in reasonable detail the works and services contemplated there under thereunder (the "“Change of Scope Notice"”).
16.2.2 Upon receipt of a Change of Scope Notice, the Concessionaire shall, with due diligence, provide to the Authority such information as is necessary, together with preliminary Documentation in support of:
Appears in 1 contract
Sources: Concession Agreement
Procedure for Change of Scope. In the event of the Authority determining that a Change of Scope is necessary, it shall issue to the Concessionaire a notice specifying in reasonable detail the works and services contemplated there under (the "“Change of Scope Notice"”).
Appears in 1 contract
Sources: Concession Agreement
Procedure for Change of Scope. In the event of the Contracting Authority determining that a Change of Scope is necessary, it shall issue to the Concessionaire a notice specifying in reasonable detail the works and services contemplated there under (the "Change of Scope Notice")thereunder.
Appears in 1 contract
Sources: Concession Agreement
Procedure for Change of Scope. 16.2.1. In the event of the Authority determining that a Change of Scope is necessary, it shall issue to the Concessionaire a notice specifying in reasonable detail the works and services contemplated there under (the "Change of Scope Notice")thereunder.
Appears in 1 contract
Sources: Concession Agreement