Restrictions on Change of Scope Clause Samples

Restrictions on Change of Scope. (i) No Change of Scope shall be executed unless the Authority has issued the Change of Scope Order save and except any Works necessary for meeting any Emergency. (ii) The total value of all Change of Scope Orders shall not exceed 10% (ten per cent) of the Contract Price. (iii) Notwithstanding anything to the contrary in this Article 13, if any change is necessitated because of any default of the Contractor in the performance of its obligations under this Agreement, the same shall not be deemed to be Change of Scope, and shall not result in any adjustment of the Contract Price or the Project Completion Schedule.
Restrictions on Change of Scope. (i) No Change of Scope shall be executed unless the Authority has issued the Change of Scope Order save and except any Works necessary for meeting any Emergency.
Restrictions on Change of Scope. (i) No Change of Scope shall be executed unless the Authority has issued the Change of Scope Order save and except any Works necessary for meeting any Emergency. (ii) The total value of all Change of Scope Orders shall not exceed 10% (ten per cent) of the Contract Price. Page 83 of 146 Border including Dawki Bridge from (Design km 63+530 to km 71+520) design length of 7.99 km in the State of Meghalaya for execution on EPC mode under JICA funding - (Package-V)-Balance Work (iii) Notwithstanding anything to the contrary in this Article 13, if any change is necessitated because of any default of the Contractor in the performance of its obligations under this Agreement, the same shall not be deemed to be Change of Scope, and shall not result in any adjustment of the Contract Price or the Project Completion Schedule.
Restrictions on Change of Scope. 11.4.1 No Change of Scope shall be executed unless the RSCL has issued the Change of Scope Order save and except any Works necessary for meeting any Emergency. 11.4.2 Change made because of any default of the Contractor in the performance of its obligations under this Agreement shall not be deemed to be Change of Scope, and shall not result in any adjustment of the Contract Price or the Project Completion Schedule.
Restrictions on Change of Scope. (i) No Change of Scope shall be executed unless the Authority has issued the Change of Scope Order save and except any Works necessary for meeting any Emergency. (ii) The total value of all Change of Scope Orders shall not exceed 10% (ten per cent) of the Contract Price. Page 83 of 146 (Km 47.075 to Km 77.055) on EPC Mode through ADB Loan assistance (iii) Notwithstanding anything to the contrary in this Article 13, if any change is necessitated because of any default of the Contractor in the performance of its obligations under this Agreement, the same shall not be deemed to be Change of Scope, and shall not result in any adjustment of the Contract Price or the Project Completion Schedule.
Restrictions on Change of Scope. (i) No Change of Scope shall be executed unless the Authority has issued the Change of Scope Order save and except any Works necessary for meeting any Emergency. Draft Contract AgreementPage 84 of 261 S-D Tunnel 2022 (ii) The total value of all Change of Scope Orders shall not exceed 10% (ten per cent) of the Contract Price.
Restrictions on Change of Scope. Rangagara to Kaliabor Tiniali of NH-37 (Old) from Km 297+000 to Km 315+315 (18.315 Km), under SARDP-NE, under EPC Mode at the Risk and Cost of EPC Contractor-2nd Call (i) No Change of Scope shall be executed unless the Authority has issued the Change of Scope Order save and except any Works necessary for meeting any Emergency. (ii) The total value of all Change of Scope Orders shall not exceed 10% (ten per cent) of the Contract Price. (iii) Notwithstanding anything to the contrary in this Article 13, if any change is necessitated because of any default of the Contractor in the performance of its obligationsunderthisAgreement,thesameshallnotbedeemedtobeChangeofScope, and shall not result in any adjustment of the Contract Price or the Project Completion Schedule.
Restrictions on Change of Scope. (i) No Change of Scope shall be executed unless the Authority has issued the Change of Scope Order save and except any Works necessary for meeting any Emergency. (ii) The total value of all Change of Scope Orders shall not exceed 10% (ten per cent) of Improvement and widening to two lane with paved shoulder of road from Km 63.700 to Km 75.700 (Total length: 12.000 km) i.e. Bamanchara - Srirampur section of NH-208 (Package-IV) in the state of Tripura on EPC basis the Contract Price. Improvement and widening to two lane with paved shoulder of road from Km 63.700 to Km 75.700 (Total length: 12.000 km) i.e. Bamanchara - Srirampur section of NH- 208 (Package-IV) in the state of Tripura on EPC basis (iii) Notwithstanding anything to the contrary in this Article 13, if any change is necessitated because of any default of the Contractor in the performance of its obligations under this Agreement, the same shall not be deemed to be Change of Scope, and shall not result in any adjustment of the Contract Price or the Project Completion Schedule.
Restrictions on Change of Scope. 9.4.1 No Change of Scope shall be executed unless K D A has issued the Change of Scope Order. 9.4.2 The total value of all Change of Scope shall not exceed the 10 % (ten per cent) ( plus/ minus) of the Contract Price for the Works. 9.4.3 Notwithstanding anything to the contrary in this Clause 9.4, no change made necessary because of any default of the Contractor in the performance of its obligations under the Agreement shall be deemed to be Change of Scope, and such Change of Scope shall not result in any adjustment of the Contract Price or the Construction Period.
Restrictions on Change of Scope. 14.4.1 No Change of Scope shall be executed unless the Authority has issued the Change of Scope Order save and except any Works necessary for meeting any Emergency. 14.4.2 Unless the Parties mutually agree to the contrary, the total value of all Change of Scope Orders shall not exceed 10% (ten per cent) of the Contract Price. 14.4.3 Notwithstanding anything to the contrary in this Article 14, no change arising from any default of the Concessionaire in the performance of its obligations under this Agreement shall be deemed to be Change of Scope, and shall not result in any adjustment of the Contract Price or the Project Completion Schedule. 14.4.4 Notwithstanding anything to the contrary contained in this Article 14, but subject to the provisions of Clause 14.1.2, the Authority shall not require the Concessionaire to undertake any works or services if such works or services are likely to delay completion of the Project by the Scheduled Completion Date; provided that in the event that the Authority considers such works or services to be essential, it may issue a Change of Scope Order, subject to the condition that the works forming part of or affected by such Change of Scope Order shall not be reckoned for purposes of determining completion of the Project and issuing the Provisional Certificate.