Restrictions on Change of Scope. (i) No Change of Scope shall be executed unless the Authority has issued the Change of Scope Order save and except any Works necessary for meeting any Emergency.
Appears in 9 contracts
Sources: Contract Agreement, Construction Contract, Contract Agreement
Restrictions on Change of Scope. (i) No Change of Scope shall be executed unless the Authority has issued the Change of Scope Order save and except any Works necessary for meeting any Emergency.
(ii) The total value of all Change of Scope Orders shall not exceed 10% (ten per cent) of the Contract Price.
Appears in 7 contracts
Sources: Contract Agreement, Contract Agreement, Contract Agreement
Restrictions on Change of Scope. (i) No Change of Scope shall be executed unless the Authority has issued the Change of Scope Order save and except any Works necessary for meeting any Emergency.
Appears in 5 contracts
Sources: Engineering Procurement and Construction Agreement, Engineering Procurement and Construction Agreement, Engineering, Procurement and Construction Agreement
Restrictions on Change of Scope. (icxliv) No Change of Scope shall be executed unless the Authority has issued the Change of Scope Order save and except any Works necessary for meeting any Emergency.
Appears in 1 contract
Sources: Engineering Procurement and Construction (Epc) Agreement
Restrictions on Change of Scope. (i) No Change of Scope shall be executed unless the Authority has issued the Change of Scope Order save and except any Works necessary for meeting any Emergency.
(ii) The total value of all Change of Scope Orders shall not exceed 10% (ten per cent) of
Appears in 1 contract
Sources: Contract Agreement