Restrictions on Change of Scope. (i) No Change of Scope shall be executed unless the Authority has issued the Change of Scope Order save and except any Works necessary for meeting any Emergency. (ii) The total value of all Change of Scope Orders shall not exceed 10% (ten per cent) of the Contract Price. Page 83 of 146 Border including Dawki Bridge from (Design km 63+530 to km 71+520) design length of 7.99 km in the State of Meghalaya for execution on EPC mode under JICA funding - (Package-V)-Balance Work (iii) Notwithstanding anything to the contrary in this Article 13, if any change is necessitated because of any default of the Contractor in the performance of its obligations under this Agreement, the same shall not be deemed to be Change of Scope, and shall not result in any adjustment of the Contract Price or the Project Completion Schedule.
Appears in 2 contracts
Sources: Contract Agreement, Contract Agreement
Restrictions on Change of Scope. (i) No Change of Scope shall be executed unless the Authority has issued the Change of Scope Order save and except any Works necessary for meeting any Emergency.
(ii) The total value of all Change of Scope Orders shall not exceed 10% (ten per cent) of the Contract Price. Page 83 of 146 Border including Dawki Bridge from km 60.900 of old NH-40) to NH-106 (Design old NH-44E), (Package-II) km 6312+530 800 to km 7124+520) design length of 7.99 km 700 under SARDP-NE ‘Phase A’ in the State of Meghalaya for execution on EPC mode under JICA funding - (Package-V)-Balance WorkMode
(iii) Notwithstanding anything to the contrary in this Article 13, if any change is necessitated because of any default of the Contractor in the performance of its obligations under this Agreement, the same shall not be deemed to be Change of Scope, and shall not result in any adjustment of the Contract Price or the Project Completion Schedule.
Appears in 1 contract
Sources: Construction Contract
Restrictions on Change of Scope. (i) No Change of Scope shall be executed unless the Authority has issued the Change of Scope Order save and except any Works necessary for meeting any Emergency.
(ii) The total value of all Change of Scope Orders shall not exceed 10% (ten per cent) of the Contract Price. Page 83 of 146 Border including Dawki Bridge shoulder from design Km 0+000 to Km 36+635 (Design km 63Length= 36.635 Km) (existing Km 112+530 000 to km 71Km 151+520060 of Old NH-62) design length of 7.99 km in the State of Meghalaya for execution under Bharatmala Pariyojana (Lot-1) Pkg-1B on EPC mode under JICA funding - (Package-V)-Balance Workin the state of Meghalaya
(iii) Notwithstanding anything to the contrary in this Article 13, if any change is necessitated because of any default of the Contractor in the performance of its obligations under this Agreement, the same shall not be deemed to be Change of Scope, and shall not result in any adjustment of the Contract Price or the Project Completion Schedule.
Appears in 1 contract
Sources: Contract Agreement
Restrictions on Change of Scope. (i) No Change of Scope shall be executed unless the Authority has issued the Change of Scope Order save and except any Works necessary for meeting any Emergency.
(ii) The total value of all Change of Scope Orders shall not exceed 10% (ten per cent) of the Contract Price. Page 83 of 146 Border including Dawki Bridge from old NH-40) to NH-106 (Design old NH-44E), km 630+530 000 to km 7112+520800 (Package-I) design length of 7.99 km under SARDP-NE ‘PHASE A’ in the State of Meghalaya for execution on EPC mode under JICA funding - (Package-V)-Balance WorkMode
(iii) Notwithstanding anything to the contrary in this Article 13, if any change is necessitated because of any default of the Contractor in the performance of its obligations under this Agreement, the same shall not be deemed to be Change of Scope, and shall not result in any adjustment of the Contract Price or the Project Completion Schedule.
Appears in 1 contract
Sources: Construction Contract
Restrictions on Change of Scope. (i) No Change of Scope shall be executed unless the Authority has issued the Change of Scope Order save and except any Works necessary for meeting any Emergency.
(ii) The total value of all Change of Scope Orders shall not exceed 10% (ten per cent) of the Contract Price. Page 83 of 146 Border including Dawki Bridge from (Design km 6310+530 670 to km 7137+520550) design length of 7.99 26.550 km in the State of Meghalaya for execution on of EPC mode under JICA funding - (Package-V)-Balance II)-Balance Work
(iii) Notwithstanding anything to the contrary in this Article 13, if any change is necessitated because of any default of the Contractor in the performance of its obligations under this Agreement, the same shall not be deemed to be Change of Scope, and shall not result in any adjustment of the Contract Price or the Project Completion Schedule.
Appears in 1 contract
Sources: Contract Agreement